10 | 6 | Optimize schedule for 10 Jobs across 6 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 2 duration 10 mins.
Operation 1 on Machine 4 duration 17 mins.
Operation 2 on Machine 1 duration 18 mins.
Operation 3 on Machine 0 duration 20 mins.
Operation 4 on Machine 5 duration 23 mins.
Operation 5 on Machine 3 duration 7 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 5 duration 24 mins.
Operation 1 on Machine 4 duration 13 mins.
Operation 2 on Machine 0 duration 40 mins.
Operation 3 on Machine 3 duration 14 mins.
Operation 4 on Machine 1 duration 37 mins.
Operation 5 on Machine 2 duration 10 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 1 duration 36 mins.
Operation 1 on Machine 5 duration 14 mins.
Operation 2 on Machine 2 duration 1 mins.
Operation 3 on Machine 3 duration 3 mins.
Operation 4 on Machine 0 duration 25 mins.
Operation 5 on Machine 4 duration 15 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 1 duration 15 mins.
Operation 1 on Machine 5 duration 28 mins.
Operation 2 on Machine 0 duration 40 mins.
Operation 3 on Machine 3 duration 4 mins.
Operation 4 on Machine 4 duration 33 mins.
Operation 5 on Machine 2 duration 39 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 0 duration 1 mins.
Operation 1 on Machine 1 duration 33 mins.
Operation 2 on Machine 2 duration 7 mins.
Operation 3 on Machine 4 duration 35 mins.
Operation 4 on Machine 5 duration 22 mins.
Operation 5 on Machine 3 duration 6 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 1 duration 39 mins.
Operation 1 on Machine 5 duration 1 mins.
Operation 2 on Machine 4 duration 37 mins.
Operation 3 on Machine 3 duration 40 mins.
Operation 4 on Machine 0 duration 13 mins.
Operation 5 on Machine 2 duration 6 mins.
Job 6 consists of the following Operations:
Operation 0 on Machine 1 duration 25 mins.
Operation 1 on Machine 5 duration 40 mins.
Operation 2 on Machine 0 duration 17 mins.
Operation 3 on Machine 2 duration 34 mins.
Operation 4 on Machine 3 duration 10 mins.
Operation 5 on Machine 4 duration 1 mins.
Job 7 consists of the following Operations:
Operation 0 on Machine 5 duration 12 mins.
Operation 1 on Machine 4 duration 2 mins.
Operation 2 on Machine 3 duration 35 mins.
Operation 3 on Machine 0 duration 16 mins.
Operation 4 on Machine 1 duration 23 mins.
Operation 5 on Machine 2 duration 34 mins.
Job 8 consists of the following Operations:
Operation 0 on Machine 5 duration 23 mins.
Operation 1 on Machine 1 duration 17 mins.
Operation 2 on Machine 2 duration 8 mins.
Operation 3 on Machine 0 duration 16 mins.
Operation 4 on Machine 3 duration 11 mins.
Operation 5 on Machine 4 duration 10 mins.
Job 9 consists of the following Operations:
Operation 0 on Machine 1 duration 31 mins.
Operation 1 on Machine 0 duration 20 mins.
Operation 2 on Machine 2 duration 1 mins.
Operation 3 on Machine 3 duration 4 mins.
Operation 4 on Machine 4 duration 10 mins.
Operation 5 on Machine 5 duration 31 mins.
| Optimize schedule for 10 Jobs across 6 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 4 Operation 0 duration 1 mins.
Job 9 Operation 1 duration 20 mins.
Job 1 Operation 2 duration 40 mins.
Job 3 Operation 2 duration 40 mins.
Job 6 Operation 2 duration 17 mins.
Job 0 Operation 3 duration 20 mins.
Job 7 Operation 3 duration 16 mins.
Job 8 Operation 3 duration 16 mins.
Job 2 Operation 4 duration 25 mins.
Job 5 Operation 4 duration 13 mins.
Machine 1 is used for the following Operations:
Job 2 Operation 0 duration 36 mins.
Job 3 Operation 0 duration 15 mins.
Job 5 Operation 0 duration 39 mins.
Job 6 Operation 0 duration 25 mins.
Job 9 Operation 0 duration 31 mins.
Job 4 Operation 1 duration 33 mins.
Job 8 Operation 1 duration 17 mins.
Job 0 Operation 2 duration 18 mins.
Job 1 Operation 4 duration 37 mins.
Job 7 Operation 4 duration 23 mins.
Machine 2 is used for the following Operations:
Job 0 Operation 0 duration 10 mins.
Job 2 Operation 2 duration 1 mins.
Job 4 Operation 2 duration 7 mins.
Job 8 Operation 2 duration 8 mins.
Job 9 Operation 2 duration 1 mins.
Job 6 Operation 3 duration 34 mins.
Job 1 Operation 5 duration 10 mins.
Job 3 Operation 5 duration 39 mins.
Job 5 Operation 5 duration 6 mins.
Job 7 Operation 5 duration 34 mins.
Machine 3 is used for the following Operations:
Job 7 Operation 2 duration 35 mins.
Job 1 Operation 3 duration 14 mins.
Job 2 Operation 3 duration 3 mins.
Job 3 Operation 3 duration 4 mins.
Job 5 Operation 3 duration 40 mins.
Job 9 Operation 3 duration 4 mins.
Job 6 Operation 4 duration 10 mins.
Job 8 Operation 4 duration 11 mins.
Job 0 Operation 5 duration 7 mins.
Job 4 Operation 5 duration 6 mins.
Machine 4 is used for the following Operations:
Job 0 Operation 1 duration 17 mins.
Job 1 Operation 1 duration 13 mins.
Job 7 Operation 1 duration 2 mins.
Job 5 Operation 2 duration 37 mins.
Job 4 Operation 3 duration 35 mins.
Job 3 Operation 4 duration 33 mins.
Job 9 Operation 4 duration 10 mins.
Job 2 Operation 5 duration 15 mins.
Job 6 Operation 5 duration 1 mins.
Job 8 Operation 5 duration 10 mins.
Machine 5 is used for the following Operations:
Job 1 Operation 0 duration 24 mins.
Job 7 Operation 0 duration 12 mins.
Job 8 Operation 0 duration 23 mins.
Job 2 Operation 1 duration 14 mins.
Job 3 Operation 1 duration 28 mins.
Job 5 Operation 1 duration 1 mins.
Job 6 Operation 1 duration 40 mins.
Job 0 Operation 4 duration 23 mins.
Job 4 Operation 4 duration 22 mins.
Job 9 Operation 5 duration 31 mins.
| Solution:
Job 4 Operation 0 on Machine 0 : 0 + 1 -> 1
Job 6 Operation 0 on Machine 1 : 0 + 25 -> 25
Job 0 Operation 0 on Machine 2 : 0 + 10 -> 10
Job 1 Operation 0 on Machine 5 : 0 + 24 -> 24
Job 0 Operation 1 on Machine 4 : 10 + 17 -> 27
Job 5 Operation 0 on Machine 1 : 25 + 39 -> 64
Job 6 Operation 1 on Machine 5 : 25 + 40 -> 65
Job 1 Operation 1 on Machine 4 : 27 + 13 -> 40
Job 1 Operation 2 on Machine 0 : 40 + 40 -> 80
Job 3 Operation 0 on Machine 1 : 64 + 15 -> 79
Job 5 Operation 1 on Machine 5 : 65 + 1 -> 66
Job 5 Operation 2 on Machine 4 : 66 + 37 -> 103
Job 7 Operation 0 on Machine 5 : 66 + 12 -> 78
Job 9 Operation 0 on Machine 1 : 79 + 31 -> 110
Job 3 Operation 1 on Machine 5 : 79 + 28 -> 107
Job 6 Operation 2 on Machine 0 : 80 + 17 -> 97
Job 6 Operation 3 on Machine 2 : 97 + 34 -> 131
Job 5 Operation 3 on Machine 3 : 103 + 40 -> 143
Job 7 Operation 1 on Machine 4 : 103 + 2 -> 105
Job 3 Operation 2 on Machine 0 : 107 + 40 -> 147
Job 8 Operation 0 on Machine 5 : 107 + 23 -> 130
Job 2 Operation 0 on Machine 1 : 110 + 36 -> 146
Job 4 Operation 1 on Machine 1 : 146 + 33 -> 179
Job 2 Operation 1 on Machine 5 : 146 + 14 -> 160
Job 5 Operation 4 on Machine 0 : 147 + 13 -> 160
Job 3 Operation 3 on Machine 3 : 147 + 4 -> 151
Job 7 Operation 2 on Machine 3 : 151 + 35 -> 186
Job 3 Operation 4 on Machine 4 : 151 + 33 -> 184
Job 9 Operation 1 on Machine 0 : 160 + 20 -> 180
Job 5 Operation 5 on Machine 2 : 160 + 6 -> 166
Job 0 Operation 2 on Machine 1 : 179 + 18 -> 197
Job 9 Operation 2 on Machine 2 : 180 + 1 -> 181
Job 4 Operation 2 on Machine 2 : 181 + 7 -> 188
Job 7 Operation 3 on Machine 0 : 186 + 16 -> 202
Job 9 Operation 3 on Machine 3 : 186 + 4 -> 190
Job 2 Operation 2 on Machine 2 : 188 + 1 -> 189
Job 3 Operation 5 on Machine 2 : 189 + 39 -> 228
Job 6 Operation 4 on Machine 3 : 190 + 10 -> 200
Job 9 Operation 4 on Machine 4 : 190 + 10 -> 200
Job 8 Operation 1 on Machine 1 : 197 + 17 -> 214
Job 2 Operation 3 on Machine 3 : 200 + 3 -> 203
Job 4 Operation 3 on Machine 4 : 200 + 35 -> 235
Job 9 Operation 5 on Machine 5 : 200 + 31 -> 231
Job 0 Operation 3 on Machine 0 : 202 + 20 -> 222
Job 1 Operation 3 on Machine 3 : 203 + 14 -> 217
Job 7 Operation 4 on Machine 1 : 214 + 23 -> 237
Job 2 Operation 4 on Machine 0 : 222 + 25 -> 247
Job 8 Operation 2 on Machine 2 : 228 + 8 -> 236
Job 0 Operation 4 on Machine 5 : 231 + 23 -> 254
Job 6 Operation 5 on Machine 4 : 235 + 1 -> 236
Job 1 Operation 4 on Machine 1 : 237 + 37 -> 274
Job 7 Operation 5 on Machine 2 : 237 + 34 -> 271
Job 8 Operation 3 on Machine 0 : 247 + 16 -> 263
Job 2 Operation 5 on Machine 4 : 247 + 15 -> 262
Job 0 Operation 5 on Machine 3 : 254 + 7 -> 261
Job 4 Operation 4 on Machine 5 : 254 + 22 -> 276
Job 8 Operation 4 on Machine 3 : 263 + 11 -> 274
Job 1 Operation 5 on Machine 2 : 274 + 10 -> 284
Job 8 Operation 5 on Machine 4 : 274 + 10 -> 284
Job 4 Operation 5 on Machine 3 : 276 + 6 -> 282
Makespan: 284.0, as it is the maximum end completion time of Operation 5 |
6 | 4 | Optimize schedule for 6 Jobs across 4 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 0 duration 122 mins.
Operation 1 on Machine 1 duration 59 mins.
Operation 2 on Machine 3 duration 112 mins.
Operation 3 on Machine 2 duration 22 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 1 duration 110 mins.
Operation 1 on Machine 3 duration 56 mins.
Operation 2 on Machine 2 duration 63 mins.
Operation 3 on Machine 0 duration 3 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 3 duration 130 mins.
Operation 1 on Machine 2 duration 105 mins.
Operation 2 on Machine 0 duration 32 mins.
Operation 3 on Machine 1 duration 68 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 2 duration 87 mins.
Operation 1 on Machine 0 duration 28 mins.
Operation 2 on Machine 1 duration 115 mins.
Operation 3 on Machine 3 duration 131 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 2 duration 149 mins.
Operation 1 on Machine 3 duration 129 mins.
Operation 2 on Machine 1 duration 119 mins.
Operation 3 on Machine 0 duration 15 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 1 duration 32 mins.
Operation 1 on Machine 0 duration 142 mins.
Operation 2 on Machine 2 duration 101 mins.
Operation 3 on Machine 3 duration 15 mins.
| Optimize schedule for 6 Jobs across 4 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 0 Operation 0 duration 122 mins.
Job 3 Operation 1 duration 28 mins.
Job 5 Operation 1 duration 142 mins.
Job 2 Operation 2 duration 32 mins.
Job 1 Operation 3 duration 3 mins.
Job 4 Operation 3 duration 15 mins.
Machine 1 is used for the following Operations:
Job 1 Operation 0 duration 110 mins.
Job 5 Operation 0 duration 32 mins.
Job 0 Operation 1 duration 59 mins.
Job 3 Operation 2 duration 115 mins.
Job 4 Operation 2 duration 119 mins.
Job 2 Operation 3 duration 68 mins.
Machine 2 is used for the following Operations:
Job 3 Operation 0 duration 87 mins.
Job 4 Operation 0 duration 149 mins.
Job 2 Operation 1 duration 105 mins.
Job 1 Operation 2 duration 63 mins.
Job 5 Operation 2 duration 101 mins.
Job 0 Operation 3 duration 22 mins.
Machine 3 is used for the following Operations:
Job 2 Operation 0 duration 130 mins.
Job 1 Operation 1 duration 56 mins.
Job 4 Operation 1 duration 129 mins.
Job 0 Operation 2 duration 112 mins.
Job 3 Operation 3 duration 131 mins.
Job 5 Operation 3 duration 15 mins.
| Solution:
Job 0 Operation 0 on Machine 0 : 0 + 122 -> 122
Job 1 Operation 0 on Machine 1 : 0 + 110 -> 110
Job 4 Operation 0 on Machine 2 : 0 + 149 -> 149
Job 2 Operation 0 on Machine 3 : 0 + 130 -> 130
Job 0 Operation 1 on Machine 1 : 122 + 59 -> 181
Job 1 Operation 1 on Machine 3 : 130 + 56 -> 186
Job 3 Operation 0 on Machine 2 : 149 + 87 -> 236
Job 5 Operation 0 on Machine 1 : 181 + 32 -> 213
Job 4 Operation 1 on Machine 3 : 186 + 129 -> 315
Job 3 Operation 1 on Machine 0 : 236 + 28 -> 264
Job 1 Operation 2 on Machine 2 : 236 + 63 -> 299
Job 3 Operation 2 on Machine 1 : 264 + 115 -> 379
Job 1 Operation 3 on Machine 0 : 299 + 3 -> 302
Job 2 Operation 1 on Machine 2 : 299 + 105 -> 404
Job 5 Operation 1 on Machine 0 : 302 + 142 -> 444
Job 0 Operation 2 on Machine 3 : 315 + 112 -> 427
Job 4 Operation 2 on Machine 1 : 379 + 119 -> 498
Job 0 Operation 3 on Machine 2 : 427 + 22 -> 449
Job 3 Operation 3 on Machine 3 : 427 + 131 -> 558
Job 2 Operation 2 on Machine 0 : 444 + 32 -> 476
Job 5 Operation 2 on Machine 2 : 449 + 101 -> 550
Job 4 Operation 3 on Machine 0 : 498 + 15 -> 513
Job 2 Operation 3 on Machine 1 : 498 + 68 -> 566
Job 5 Operation 3 on Machine 3 : 558 + 15 -> 573
Makespan: 573.0, as it is the maximum end completion time of Operation 3 |
8 | 5 | Optimize schedule for 8 Jobs across 5 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 4 duration 148 mins.
Operation 1 on Machine 0 duration 394 mins.
Operation 2 on Machine 3 duration 213 mins.
Operation 3 on Machine 2 duration 329 mins.
Operation 4 on Machine 1 duration 45 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 0 duration 339 mins.
Operation 1 on Machine 1 duration 219 mins.
Operation 2 on Machine 4 duration 343 mins.
Operation 3 on Machine 2 duration 122 mins.
Operation 4 on Machine 3 duration 305 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 4 duration 144 mins.
Operation 1 on Machine 1 duration 446 mins.
Operation 2 on Machine 3 duration 166 mins.
Operation 3 on Machine 0 duration 2 mins.
Operation 4 on Machine 2 duration 29 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 0 duration 424 mins.
Operation 1 on Machine 4 duration 231 mins.
Operation 2 on Machine 1 duration 363 mins.
Operation 3 on Machine 2 duration 41 mins.
Operation 4 on Machine 3 duration 351 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 2 duration 28 mins.
Operation 1 on Machine 3 duration 304 mins.
Operation 2 on Machine 1 duration 80 mins.
Operation 3 on Machine 4 duration 239 mins.
Operation 4 on Machine 0 duration 60 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 0 duration 434 mins.
Operation 1 on Machine 4 duration 20 mins.
Operation 2 on Machine 3 duration 33 mins.
Operation 3 on Machine 2 duration 345 mins.
Operation 4 on Machine 1 duration 319 mins.
Job 6 consists of the following Operations:
Operation 0 on Machine 1 duration 92 mins.
Operation 1 on Machine 0 duration 472 mins.
Operation 2 on Machine 2 duration 375 mins.
Operation 3 on Machine 3 duration 224 mins.
Operation 4 on Machine 4 duration 470 mins.
Job 7 consists of the following Operations:
Operation 0 on Machine 0 duration 310 mins.
Operation 1 on Machine 3 duration 368 mins.
Operation 2 on Machine 2 duration 75 mins.
Operation 3 on Machine 1 duration 415 mins.
Operation 4 on Machine 4 duration 192 mins.
| Optimize schedule for 8 Jobs across 5 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 1 Operation 0 duration 339 mins.
Job 3 Operation 0 duration 424 mins.
Job 5 Operation 0 duration 434 mins.
Job 7 Operation 0 duration 310 mins.
Job 0 Operation 1 duration 394 mins.
Job 6 Operation 1 duration 472 mins.
Job 2 Operation 3 duration 2 mins.
Job 4 Operation 4 duration 60 mins.
Machine 1 is used for the following Operations:
Job 6 Operation 0 duration 92 mins.
Job 1 Operation 1 duration 219 mins.
Job 2 Operation 1 duration 446 mins.
Job 3 Operation 2 duration 363 mins.
Job 4 Operation 2 duration 80 mins.
Job 7 Operation 3 duration 415 mins.
Job 0 Operation 4 duration 45 mins.
Job 5 Operation 4 duration 319 mins.
Machine 2 is used for the following Operations:
Job 4 Operation 0 duration 28 mins.
Job 6 Operation 2 duration 375 mins.
Job 7 Operation 2 duration 75 mins.
Job 0 Operation 3 duration 329 mins.
Job 1 Operation 3 duration 122 mins.
Job 3 Operation 3 duration 41 mins.
Job 5 Operation 3 duration 345 mins.
Job 2 Operation 4 duration 29 mins.
Machine 3 is used for the following Operations:
Job 4 Operation 1 duration 304 mins.
Job 7 Operation 1 duration 368 mins.
Job 0 Operation 2 duration 213 mins.
Job 2 Operation 2 duration 166 mins.
Job 5 Operation 2 duration 33 mins.
Job 6 Operation 3 duration 224 mins.
Job 1 Operation 4 duration 305 mins.
Job 3 Operation 4 duration 351 mins.
Machine 4 is used for the following Operations:
Job 0 Operation 0 duration 148 mins.
Job 2 Operation 0 duration 144 mins.
Job 3 Operation 1 duration 231 mins.
Job 5 Operation 1 duration 20 mins.
Job 1 Operation 2 duration 343 mins.
Job 4 Operation 3 duration 239 mins.
Job 6 Operation 4 duration 470 mins.
Job 7 Operation 4 duration 192 mins.
| Solution:
Job 1 Operation 0 on Machine 0 : 0 + 339 -> 339
Job 6 Operation 0 on Machine 1 : 0 + 92 -> 92
Job 4 Operation 0 on Machine 2 : 0 + 28 -> 28
Job 2 Operation 0 on Machine 4 : 0 + 144 -> 144
Job 4 Operation 1 on Machine 3 : 28 + 304 -> 332
Job 2 Operation 1 on Machine 1 : 144 + 446 -> 590
Job 0 Operation 0 on Machine 4 : 144 + 148 -> 292
Job 7 Operation 0 on Machine 0 : 339 + 310 -> 649
Job 4 Operation 2 on Machine 1 : 590 + 80 -> 670
Job 2 Operation 2 on Machine 3 : 590 + 166 -> 756
Job 6 Operation 1 on Machine 0 : 649 + 472 -> 1121
Job 1 Operation 1 on Machine 1 : 670 + 219 -> 889
Job 4 Operation 3 on Machine 4 : 670 + 239 -> 909
Job 7 Operation 1 on Machine 3 : 756 + 368 -> 1124
Job 1 Operation 2 on Machine 4 : 909 + 343 -> 1252
Job 3 Operation 0 on Machine 0 : 1121 + 424 -> 1545
Job 7 Operation 2 on Machine 2 : 1124 + 75 -> 1199
Job 7 Operation 3 on Machine 1 : 1199 + 415 -> 1614
Job 1 Operation 3 on Machine 2 : 1252 + 122 -> 1374
Job 6 Operation 2 on Machine 2 : 1374 + 375 -> 1749
Job 1 Operation 4 on Machine 3 : 1374 + 305 -> 1679
Job 5 Operation 0 on Machine 0 : 1545 + 434 -> 1979
Job 3 Operation 1 on Machine 4 : 1545 + 231 -> 1776
Job 6 Operation 3 on Machine 3 : 1749 + 224 -> 1973
Job 3 Operation 2 on Machine 1 : 1776 + 363 -> 2139
Job 0 Operation 1 on Machine 0 : 1979 + 394 -> 2373
Job 5 Operation 1 on Machine 4 : 1979 + 20 -> 1999
Job 5 Operation 2 on Machine 3 : 1999 + 33 -> 2032
Job 6 Operation 4 on Machine 4 : 1999 + 470 -> 2469
Job 5 Operation 3 on Machine 2 : 2032 + 345 -> 2377
Job 2 Operation 3 on Machine 0 : 2373 + 2 -> 2375
Job 0 Operation 2 on Machine 3 : 2373 + 213 -> 2586
Job 4 Operation 4 on Machine 0 : 2375 + 60 -> 2435
Job 5 Operation 4 on Machine 1 : 2377 + 319 -> 2696
Job 2 Operation 4 on Machine 2 : 2377 + 29 -> 2406
Job 3 Operation 3 on Machine 2 : 2406 + 41 -> 2447
Job 7 Operation 4 on Machine 4 : 2469 + 192 -> 2661
Job 0 Operation 3 on Machine 2 : 2586 + 329 -> 2915
Job 3 Operation 4 on Machine 3 : 2586 + 351 -> 2937
Job 0 Operation 4 on Machine 1 : 2915 + 45 -> 2960
Makespan: 2960.0, as it is the maximum end completion time of Operation 4 |
15 | 10 | Optimize schedule for 15 Jobs across 10 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 9 duration 427 mins.
Operation 1 on Machine 5 duration 52 mins.
Operation 2 on Machine 4 duration 180 mins.
Operation 3 on Machine 7 duration 280 mins.
Operation 4 on Machine 3 duration 330 mins.
Operation 5 on Machine 8 duration 56 mins.
Operation 6 on Machine 6 duration 183 mins.
Operation 7 on Machine 1 duration 39 mins.
Operation 8 on Machine 2 duration 217 mins.
Operation 9 on Machine 0 duration 168 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 5 duration 168 mins.
Operation 1 on Machine 4 duration 345 mins.
Operation 2 on Machine 3 duration 392 mins.
Operation 3 on Machine 6 duration 414 mins.
Operation 4 on Machine 0 duration 451 mins.
Operation 5 on Machine 2 duration 198 mins.
Operation 6 on Machine 7 duration 61 mins.
Operation 7 on Machine 8 duration 225 mins.
Operation 8 on Machine 1 duration 301 mins.
Operation 9 on Machine 9 duration 123 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 1 duration 150 mins.
Operation 1 on Machine 8 duration 238 mins.
Operation 2 on Machine 2 duration 145 mins.
Operation 3 on Machine 9 duration 190 mins.
Operation 4 on Machine 0 duration 225 mins.
Operation 5 on Machine 5 duration 176 mins.
Operation 6 on Machine 4 duration 116 mins.
Operation 7 on Machine 6 duration 141 mins.
Operation 8 on Machine 7 duration 402 mins.
Operation 9 on Machine 3 duration 296 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 8 duration 362 mins.
Operation 1 on Machine 6 duration 207 mins.
Operation 2 on Machine 2 duration 15 mins.
Operation 3 on Machine 3 duration 368 mins.
Operation 4 on Machine 9 duration 480 mins.
Operation 5 on Machine 0 duration 190 mins.
Operation 6 on Machine 5 duration 190 mins.
Operation 7 on Machine 4 duration 44 mins.
Operation 8 on Machine 7 duration 243 mins.
Operation 9 on Machine 1 duration 343 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 3 duration 111 mins.
Operation 1 on Machine 8 duration 363 mins.
Operation 2 on Machine 9 duration 82 mins.
Operation 3 on Machine 0 duration 398 mins.
Operation 4 on Machine 4 duration 112 mins.
Operation 5 on Machine 5 duration 57 mins.
Operation 6 on Machine 2 duration 49 mins.
Operation 7 on Machine 1 duration 484 mins.
Operation 8 on Machine 7 duration 189 mins.
Operation 9 on Machine 6 duration 162 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 8 duration 105 mins.
Operation 1 on Machine 7 duration 165 mins.
Operation 2 on Machine 3 duration 332 mins.
Operation 3 on Machine 5 duration 216 mins.
Operation 4 on Machine 2 duration 30 mins.
Operation 5 on Machine 9 duration 284 mins.
Operation 6 on Machine 6 duration 311 mins.
Operation 7 on Machine 0 duration 15 mins.
Operation 8 on Machine 4 duration 431 mins.
Operation 9 on Machine 1 duration 453 mins.
Job 6 consists of the following Operations:
Operation 0 on Machine 8 duration 425 mins.
Operation 1 on Machine 7 duration 124 mins.
Operation 2 on Machine 3 duration 353 mins.
Operation 3 on Machine 9 duration 156 mins.
Operation 4 on Machine 5 duration 242 mins.
Operation 5 on Machine 2 duration 205 mins.
Operation 6 on Machine 6 duration 417 mins.
Operation 7 on Machine 0 duration 243 mins.
Operation 8 on Machine 4 duration 406 mins.
Operation 9 on Machine 1 duration 200 mins.
Job 7 consists of the following Operations:
Operation 0 on Machine 6 duration 325 mins.
Operation 1 on Machine 1 duration 138 mins.
Operation 2 on Machine 4 duration 96 mins.
Operation 3 on Machine 9 duration 347 mins.
Operation 4 on Machine 8 duration 14 mins.
Operation 5 on Machine 0 duration 352 mins.
Operation 6 on Machine 7 duration 327 mins.
Operation 7 on Machine 2 duration 275 mins.
Operation 8 on Machine 5 duration 353 mins.
Operation 9 on Machine 3 duration 157 mins.
Job 8 consists of the following Operations:
Operation 0 on Machine 5 duration 200 mins.
Operation 1 on Machine 8 duration 454 mins.
Operation 2 on Machine 0 duration 98 mins.
Operation 3 on Machine 3 duration 71 mins.
Operation 4 on Machine 4 duration 436 mins.
Operation 5 on Machine 6 duration 458 mins.
Operation 6 on Machine 9 duration 431 mins.
Operation 7 on Machine 2 duration 49 mins.
Operation 8 on Machine 1 duration 468 mins.
Operation 9 on Machine 7 duration 177 mins.
Job 9 consists of the following Operations:
Operation 0 on Machine 1 duration 85 mins.
Operation 1 on Machine 9 duration 114 mins.
Operation 2 on Machine 4 duration 50 mins.
Operation 3 on Machine 0 duration 189 mins.
Operation 4 on Machine 8 duration 226 mins.
Operation 5 on Machine 6 duration 111 mins.
Operation 6 on Machine 5 duration 169 mins.
Operation 7 on Machine 2 duration 98 mins.
Operation 8 on Machine 3 duration 104 mins.
Operation 9 on Machine 7 duration 474 mins.
Job 10 consists of the following Operations:
Operation 0 on Machine 3 duration 113 mins.
Operation 1 on Machine 7 duration 2 mins.
Operation 2 on Machine 5 duration 84 mins.
Operation 3 on Machine 2 duration 386 mins.
Operation 4 on Machine 6 duration 92 mins.
Operation 5 on Machine 0 duration 310 mins.
Operation 6 on Machine 9 duration 369 mins.
Operation 7 on Machine 4 duration 464 mins.
Operation 8 on Machine 8 duration 5 mins.
Operation 9 on Machine 1 duration 182 mins.
Job 11 consists of the following Operations:
Operation 0 on Machine 5 duration 456 mins.
Operation 1 on Machine 8 duration 419 mins.
Operation 2 on Machine 3 duration 244 mins.
Operation 3 on Machine 9 duration 207 mins.
Operation 4 on Machine 1 duration 209 mins.
Operation 5 on Machine 0 duration 315 mins.
Operation 6 on Machine 7 duration 64 mins.
Operation 7 on Machine 6 duration 449 mins.
Operation 8 on Machine 4 duration 334 mins.
Operation 9 on Machine 2 duration 142 mins.
Job 12 consists of the following Operations:
Operation 0 on Machine 1 duration 220 mins.
Operation 1 on Machine 4 duration 143 mins.
Operation 2 on Machine 8 duration 257 mins.
Operation 3 on Machine 7 duration 487 mins.
Operation 4 on Machine 9 duration 36 mins.
Operation 5 on Machine 6 duration 258 mins.
Operation 6 on Machine 3 duration 449 mins.
Operation 7 on Machine 5 duration 285 mins.
Operation 8 on Machine 2 duration 299 mins.
Operation 9 on Machine 0 duration 343 mins.
Job 13 consists of the following Operations:
Operation 0 on Machine 0 duration 283 mins.
Operation 1 on Machine 3 duration 420 mins.
Operation 2 on Machine 1 duration 254 mins.
Operation 3 on Machine 5 duration 102 mins.
Operation 4 on Machine 7 duration 202 mins.
Operation 5 on Machine 2 duration 386 mins.
Operation 6 on Machine 4 duration 272 mins.
Operation 7 on Machine 9 duration 105 mins.
Operation 8 on Machine 6 duration 121 mins.
Operation 9 on Machine 8 duration 120 mins.
Job 14 consists of the following Operations:
Operation 0 on Machine 0 duration 236 mins.
Operation 1 on Machine 8 duration 288 mins.
Operation 2 on Machine 4 duration 215 mins.
Operation 3 on Machine 2 duration 65 mins.
Operation 4 on Machine 1 duration 272 mins.
Operation 5 on Machine 7 duration 461 mins.
Operation 6 on Machine 9 duration 109 mins.
Operation 7 on Machine 6 duration 124 mins.
Operation 8 on Machine 5 duration 100 mins.
Operation 9 on Machine 3 duration 166 mins.
| Optimize schedule for 15 Jobs across 10 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 13 Operation 0 duration 283 mins.
Job 14 Operation 0 duration 236 mins.
Job 8 Operation 2 duration 98 mins.
Job 4 Operation 3 duration 398 mins.
Job 9 Operation 3 duration 189 mins.
Job 1 Operation 4 duration 451 mins.
Job 2 Operation 4 duration 225 mins.
Job 3 Operation 5 duration 190 mins.
Job 7 Operation 5 duration 352 mins.
Job 10 Operation 5 duration 310 mins.
Job 11 Operation 5 duration 315 mins.
Job 5 Operation 7 duration 15 mins.
Job 6 Operation 7 duration 243 mins.
Job 0 Operation 9 duration 168 mins.
Job 12 Operation 9 duration 343 mins.
Machine 1 is used for the following Operations:
Job 2 Operation 0 duration 150 mins.
Job 9 Operation 0 duration 85 mins.
Job 12 Operation 0 duration 220 mins.
Job 7 Operation 1 duration 138 mins.
Job 13 Operation 2 duration 254 mins.
Job 11 Operation 4 duration 209 mins.
Job 14 Operation 4 duration 272 mins.
Job 0 Operation 7 duration 39 mins.
Job 4 Operation 7 duration 484 mins.
Job 1 Operation 8 duration 301 mins.
Job 8 Operation 8 duration 468 mins.
Job 3 Operation 9 duration 343 mins.
Job 5 Operation 9 duration 453 mins.
Job 6 Operation 9 duration 200 mins.
Job 10 Operation 9 duration 182 mins.
Machine 2 is used for the following Operations:
Job 2 Operation 2 duration 145 mins.
Job 3 Operation 2 duration 15 mins.
Job 10 Operation 3 duration 386 mins.
Job 14 Operation 3 duration 65 mins.
Job 5 Operation 4 duration 30 mins.
Job 1 Operation 5 duration 198 mins.
Job 6 Operation 5 duration 205 mins.
Job 13 Operation 5 duration 386 mins.
Job 4 Operation 6 duration 49 mins.
Job 7 Operation 7 duration 275 mins.
Job 8 Operation 7 duration 49 mins.
Job 9 Operation 7 duration 98 mins.
Job 0 Operation 8 duration 217 mins.
Job 12 Operation 8 duration 299 mins.
Job 11 Operation 9 duration 142 mins.
Machine 3 is used for the following Operations:
Job 4 Operation 0 duration 111 mins.
Job 10 Operation 0 duration 113 mins.
Job 13 Operation 1 duration 420 mins.
Job 1 Operation 2 duration 392 mins.
Job 5 Operation 2 duration 332 mins.
Job 6 Operation 2 duration 353 mins.
Job 11 Operation 2 duration 244 mins.
Job 3 Operation 3 duration 368 mins.
Job 8 Operation 3 duration 71 mins.
Job 0 Operation 4 duration 330 mins.
Job 12 Operation 6 duration 449 mins.
Job 9 Operation 8 duration 104 mins.
Job 2 Operation 9 duration 296 mins.
Job 7 Operation 9 duration 157 mins.
Job 14 Operation 9 duration 166 mins.
Machine 4 is used for the following Operations:
Job 1 Operation 1 duration 345 mins.
Job 12 Operation 1 duration 143 mins.
Job 0 Operation 2 duration 180 mins.
Job 7 Operation 2 duration 96 mins.
Job 9 Operation 2 duration 50 mins.
Job 14 Operation 2 duration 215 mins.
Job 4 Operation 4 duration 112 mins.
Job 8 Operation 4 duration 436 mins.
Job 2 Operation 6 duration 116 mins.
Job 13 Operation 6 duration 272 mins.
Job 3 Operation 7 duration 44 mins.
Job 10 Operation 7 duration 464 mins.
Job 5 Operation 8 duration 431 mins.
Job 6 Operation 8 duration 406 mins.
Job 11 Operation 8 duration 334 mins.
Machine 5 is used for the following Operations:
Job 1 Operation 0 duration 168 mins.
Job 8 Operation 0 duration 200 mins.
Job 11 Operation 0 duration 456 mins.
Job 0 Operation 1 duration 52 mins.
Job 10 Operation 2 duration 84 mins.
Job 5 Operation 3 duration 216 mins.
Job 13 Operation 3 duration 102 mins.
Job 6 Operation 4 duration 242 mins.
Job 2 Operation 5 duration 176 mins.
Job 4 Operation 5 duration 57 mins.
Job 3 Operation 6 duration 190 mins.
Job 9 Operation 6 duration 169 mins.
Job 12 Operation 7 duration 285 mins.
Job 7 Operation 8 duration 353 mins.
Job 14 Operation 8 duration 100 mins.
Machine 6 is used for the following Operations:
Job 7 Operation 0 duration 325 mins.
Job 3 Operation 1 duration 207 mins.
Job 1 Operation 3 duration 414 mins.
Job 10 Operation 4 duration 92 mins.
Job 8 Operation 5 duration 458 mins.
Job 9 Operation 5 duration 111 mins.
Job 12 Operation 5 duration 258 mins.
Job 0 Operation 6 duration 183 mins.
Job 5 Operation 6 duration 311 mins.
Job 6 Operation 6 duration 417 mins.
Job 2 Operation 7 duration 141 mins.
Job 11 Operation 7 duration 449 mins.
Job 14 Operation 7 duration 124 mins.
Job 13 Operation 8 duration 121 mins.
Job 4 Operation 9 duration 162 mins.
Machine 7 is used for the following Operations:
Job 5 Operation 1 duration 165 mins.
Job 6 Operation 1 duration 124 mins.
Job 10 Operation 1 duration 2 mins.
Job 0 Operation 3 duration 280 mins.
Job 12 Operation 3 duration 487 mins.
Job 13 Operation 4 duration 202 mins.
Job 14 Operation 5 duration 461 mins.
Job 1 Operation 6 duration 61 mins.
Job 7 Operation 6 duration 327 mins.
Job 11 Operation 6 duration 64 mins.
Job 2 Operation 8 duration 402 mins.
Job 3 Operation 8 duration 243 mins.
Job 4 Operation 8 duration 189 mins.
Job 8 Operation 9 duration 177 mins.
Job 9 Operation 9 duration 474 mins.
Machine 8 is used for the following Operations:
Job 3 Operation 0 duration 362 mins.
Job 5 Operation 0 duration 105 mins.
Job 6 Operation 0 duration 425 mins.
Job 2 Operation 1 duration 238 mins.
Job 4 Operation 1 duration 363 mins.
Job 8 Operation 1 duration 454 mins.
Job 11 Operation 1 duration 419 mins.
Job 14 Operation 1 duration 288 mins.
Job 12 Operation 2 duration 257 mins.
Job 7 Operation 4 duration 14 mins.
Job 9 Operation 4 duration 226 mins.
Job 0 Operation 5 duration 56 mins.
Job 1 Operation 7 duration 225 mins.
Job 10 Operation 8 duration 5 mins.
Job 13 Operation 9 duration 120 mins.
Machine 9 is used for the following Operations:
Job 0 Operation 0 duration 427 mins.
Job 9 Operation 1 duration 114 mins.
Job 4 Operation 2 duration 82 mins.
Job 2 Operation 3 duration 190 mins.
Job 6 Operation 3 duration 156 mins.
Job 7 Operation 3 duration 347 mins.
Job 11 Operation 3 duration 207 mins.
Job 3 Operation 4 duration 480 mins.
Job 12 Operation 4 duration 36 mins.
Job 5 Operation 5 duration 284 mins.
Job 8 Operation 6 duration 431 mins.
Job 10 Operation 6 duration 369 mins.
Job 14 Operation 6 duration 109 mins.
Job 13 Operation 7 duration 105 mins.
Job 1 Operation 9 duration 123 mins.
| Solution:
Job 13 Operation 0 on Machine 0 : 0 + 283 -> 283
Job 9 Operation 0 on Machine 1 : 0 + 85 -> 85
Job 10 Operation 0 on Machine 3 : 0 + 113 -> 113
Job 7 Operation 0 on Machine 6 : 0 + 325 -> 325
Job 5 Operation 0 on Machine 8 : 0 + 105 -> 105
Job 0 Operation 0 on Machine 9 : 0 + 427 -> 427
Job 12 Operation 0 on Machine 1 : 85 + 220 -> 305
Job 3 Operation 0 on Machine 8 : 105 + 362 -> 467
Job 4 Operation 0 on Machine 3 : 113 + 111 -> 224
Job 10 Operation 1 on Machine 7 : 113 + 2 -> 115
Job 10 Operation 2 on Machine 5 : 115 + 84 -> 199
Job 5 Operation 1 on Machine 7 : 115 + 165 -> 280
Job 10 Operation 3 on Machine 2 : 199 + 386 -> 585
Job 1 Operation 0 on Machine 5 : 199 + 168 -> 367
Job 5 Operation 2 on Machine 3 : 280 + 332 -> 612
Job 14 Operation 0 on Machine 0 : 283 + 236 -> 519
Job 12 Operation 1 on Machine 4 : 305 + 143 -> 448
Job 7 Operation 1 on Machine 1 : 325 + 138 -> 463
Job 0 Operation 1 on Machine 5 : 427 + 52 -> 479
Job 9 Operation 1 on Machine 9 : 427 + 114 -> 541
Job 2 Operation 0 on Machine 1 : 463 + 150 -> 613
Job 7 Operation 2 on Machine 4 : 463 + 96 -> 559
Job 12 Operation 2 on Machine 8 : 467 + 257 -> 724
Job 9 Operation 2 on Machine 4 : 559 + 50 -> 609
Job 7 Operation 3 on Machine 9 : 559 + 347 -> 906
Job 10 Operation 4 on Machine 6 : 585 + 92 -> 677
Job 9 Operation 3 on Machine 0 : 609 + 189 -> 798
Job 1 Operation 1 on Machine 4 : 609 + 345 -> 954
Job 13 Operation 1 on Machine 3 : 612 + 420 -> 1032
Job 5 Operation 3 on Machine 5 : 612 + 216 -> 828
Job 3 Operation 1 on Machine 6 : 677 + 207 -> 884
Job 12 Operation 3 on Machine 7 : 724 + 487 -> 1211
Job 4 Operation 1 on Machine 8 : 724 + 363 -> 1087
Job 10 Operation 5 on Machine 0 : 798 + 310 -> 1108
Job 5 Operation 4 on Machine 2 : 828 + 30 -> 858
Job 11 Operation 0 on Machine 5 : 828 + 456 -> 1284
Job 0 Operation 2 on Machine 4 : 954 + 180 -> 1134
Job 13 Operation 2 on Machine 1 : 1032 + 254 -> 1286
Job 1 Operation 2 on Machine 3 : 1032 + 392 -> 1424
Job 2 Operation 1 on Machine 8 : 1087 + 238 -> 1325
Job 4 Operation 2 on Machine 9 : 1087 + 82 -> 1169
Job 4 Operation 3 on Machine 0 : 1169 + 398 -> 1567
Job 10 Operation 6 on Machine 9 : 1169 + 369 -> 1538
Job 0 Operation 3 on Machine 7 : 1211 + 280 -> 1491
Job 8 Operation 0 on Machine 5 : 1284 + 200 -> 1484
Job 2 Operation 2 on Machine 2 : 1325 + 145 -> 1470
Job 6 Operation 0 on Machine 8 : 1325 + 425 -> 1750
Job 1 Operation 3 on Machine 6 : 1424 + 414 -> 1838
Job 0 Operation 4 on Machine 3 : 1491 + 330 -> 1821
Job 2 Operation 3 on Machine 9 : 1538 + 190 -> 1728
Job 4 Operation 4 on Machine 4 : 1567 + 112 -> 1679
Job 10 Operation 7 on Machine 4 : 1679 + 464 -> 2143
Job 4 Operation 5 on Machine 5 : 1679 + 57 -> 1736
Job 2 Operation 4 on Machine 0 : 1728 + 225 -> 1953
Job 5 Operation 5 on Machine 9 : 1728 + 284 -> 2012
Job 4 Operation 6 on Machine 2 : 1736 + 49 -> 1785
Job 6 Operation 1 on Machine 7 : 1750 + 124 -> 1874
Job 7 Operation 4 on Machine 8 : 1750 + 14 -> 1764
Job 14 Operation 1 on Machine 8 : 1764 + 288 -> 2052
Job 4 Operation 7 on Machine 1 : 1785 + 484 -> 2269
Job 3 Operation 2 on Machine 2 : 1785 + 15 -> 1800
Job 6 Operation 2 on Machine 3 : 1874 + 353 -> 2227
Job 1 Operation 4 on Machine 0 : 1953 + 451 -> 2404
Job 2 Operation 5 on Machine 5 : 1953 + 176 -> 2129
Job 5 Operation 6 on Machine 6 : 2012 + 311 -> 2323
Job 12 Operation 4 on Machine 9 : 2012 + 36 -> 2048
Job 8 Operation 1 on Machine 8 : 2052 + 454 -> 2506
Job 13 Operation 3 on Machine 5 : 2129 + 102 -> 2231
Job 2 Operation 6 on Machine 4 : 2143 + 116 -> 2259
Job 3 Operation 3 on Machine 3 : 2227 + 368 -> 2595
Job 6 Operation 3 on Machine 9 : 2227 + 156 -> 2383
Job 13 Operation 4 on Machine 7 : 2231 + 202 -> 2433
Job 14 Operation 2 on Machine 4 : 2259 + 215 -> 2474
Job 2 Operation 7 on Machine 6 : 2323 + 141 -> 2464
Job 6 Operation 4 on Machine 5 : 2383 + 242 -> 2625
Job 5 Operation 7 on Machine 0 : 2404 + 15 -> 2419
Job 7 Operation 5 on Machine 0 : 2419 + 352 -> 2771
Job 12 Operation 5 on Machine 6 : 2464 + 258 -> 2722
Job 2 Operation 8 on Machine 7 : 2464 + 402 -> 2866
Job 14 Operation 3 on Machine 2 : 2474 + 65 -> 2539
Job 5 Operation 8 on Machine 4 : 2474 + 431 -> 2905
Job 10 Operation 8 on Machine 8 : 2506 + 5 -> 2511
Job 10 Operation 9 on Machine 1 : 2511 + 182 -> 2693
Job 0 Operation 5 on Machine 8 : 2511 + 56 -> 2567
Job 11 Operation 1 on Machine 8 : 2567 + 419 -> 2986
Job 3 Operation 4 on Machine 9 : 2595 + 480 -> 3075
Job 6 Operation 5 on Machine 2 : 2625 + 205 -> 2830
Job 14 Operation 4 on Machine 1 : 2693 + 272 -> 2965
Job 0 Operation 6 on Machine 6 : 2722 + 183 -> 2905
Job 8 Operation 2 on Machine 0 : 2771 + 98 -> 2869
Job 1 Operation 5 on Machine 2 : 2830 + 198 -> 3028
Job 7 Operation 6 on Machine 7 : 2866 + 327 -> 3193
Job 8 Operation 3 on Machine 3 : 2869 + 71 -> 2940
Job 6 Operation 6 on Machine 6 : 2905 + 417 -> 3322
Job 8 Operation 4 on Machine 4 : 2940 + 436 -> 3376
Job 5 Operation 9 on Machine 1 : 2965 + 453 -> 3418
Job 11 Operation 2 on Machine 3 : 2986 + 244 -> 3230
Job 9 Operation 4 on Machine 8 : 2986 + 226 -> 3212
Job 3 Operation 5 on Machine 0 : 3075 + 190 -> 3265
Job 7 Operation 7 on Machine 2 : 3193 + 275 -> 3468
Job 1 Operation 6 on Machine 7 : 3193 + 61 -> 3254
Job 12 Operation 6 on Machine 3 : 3230 + 449 -> 3679
Job 11 Operation 3 on Machine 9 : 3230 + 207 -> 3437
Job 14 Operation 5 on Machine 7 : 3254 + 461 -> 3715
Job 1 Operation 7 on Machine 8 : 3254 + 225 -> 3479
Job 3 Operation 6 on Machine 5 : 3265 + 190 -> 3455
Job 6 Operation 7 on Machine 0 : 3322 + 243 -> 3565
Job 8 Operation 5 on Machine 6 : 3376 + 458 -> 3834
Job 0 Operation 7 on Machine 1 : 3418 + 39 -> 3457
Job 3 Operation 7 on Machine 4 : 3455 + 44 -> 3499
Job 11 Operation 4 on Machine 1 : 3457 + 209 -> 3666
Job 13 Operation 5 on Machine 2 : 3468 + 386 -> 3854
Job 6 Operation 8 on Machine 4 : 3565 + 406 -> 3971
Job 11 Operation 5 on Machine 0 : 3666 + 315 -> 3981
Job 1 Operation 8 on Machine 1 : 3666 + 301 -> 3967
Job 12 Operation 7 on Machine 5 : 3679 + 285 -> 3964
Job 3 Operation 8 on Machine 7 : 3715 + 243 -> 3958
Job 9 Operation 5 on Machine 6 : 3834 + 111 -> 3945
Job 8 Operation 6 on Machine 9 : 3834 + 431 -> 4265
Job 0 Operation 8 on Machine 2 : 3854 + 217 -> 4071
Job 9 Operation 6 on Machine 5 : 3964 + 169 -> 4133
Job 3 Operation 9 on Machine 1 : 3967 + 343 -> 4310
Job 13 Operation 6 on Machine 4 : 3971 + 272 -> 4243
Job 11 Operation 6 on Machine 7 : 3981 + 64 -> 4045
Job 11 Operation 7 on Machine 6 : 4045 + 449 -> 4494
Job 4 Operation 8 on Machine 7 : 4045 + 189 -> 4234
Job 0 Operation 9 on Machine 0 : 4071 + 168 -> 4239
Job 9 Operation 7 on Machine 2 : 4133 + 98 -> 4231
Job 7 Operation 8 on Machine 5 : 4133 + 353 -> 4486
Job 9 Operation 8 on Machine 3 : 4231 + 104 -> 4335
Job 8 Operation 7 on Machine 2 : 4265 + 49 -> 4314
Job 1 Operation 9 on Machine 9 : 4265 + 123 -> 4388
Job 8 Operation 8 on Machine 1 : 4314 + 468 -> 4782
Job 12 Operation 8 on Machine 2 : 4314 + 299 -> 4613
Job 2 Operation 9 on Machine 3 : 4335 + 296 -> 4631
Job 9 Operation 9 on Machine 7 : 4335 + 474 -> 4809
Job 14 Operation 6 on Machine 9 : 4388 + 109 -> 4497
Job 11 Operation 8 on Machine 4 : 4494 + 334 -> 4828
Job 14 Operation 7 on Machine 6 : 4497 + 124 -> 4621
Job 13 Operation 7 on Machine 9 : 4497 + 105 -> 4602
Job 12 Operation 9 on Machine 0 : 4613 + 343 -> 4956
Job 14 Operation 8 on Machine 5 : 4621 + 100 -> 4721
Job 13 Operation 8 on Machine 6 : 4621 + 121 -> 4742
Job 7 Operation 9 on Machine 3 : 4631 + 157 -> 4788
Job 4 Operation 9 on Machine 6 : 4742 + 162 -> 4904
Job 13 Operation 9 on Machine 8 : 4742 + 120 -> 4862
Job 6 Operation 9 on Machine 1 : 4782 + 200 -> 4982
Job 14 Operation 9 on Machine 3 : 4788 + 166 -> 4954
Job 8 Operation 9 on Machine 7 : 4809 + 177 -> 4986
Job 11 Operation 9 on Machine 2 : 4828 + 142 -> 4970
Makespan: 4986.0, as it is the maximum end completion time of Operation 9 |
10 | 9 | Optimize schedule for 10 Jobs across 9 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 1 duration 176 mins.
Operation 1 on Machine 2 duration 121 mins.
Operation 2 on Machine 5 duration 53 mins.
Operation 3 on Machine 0 duration 8 mins.
Operation 4 on Machine 7 duration 153 mins.
Operation 5 on Machine 8 duration 200 mins.
Operation 6 on Machine 6 duration 60 mins.
Operation 7 on Machine 4 duration 112 mins.
Operation 8 on Machine 3 duration 280 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 1 duration 260 mins.
Operation 1 on Machine 6 duration 127 mins.
Operation 2 on Machine 0 duration 235 mins.
Operation 3 on Machine 3 duration 256 mins.
Operation 4 on Machine 7 duration 209 mins.
Operation 5 on Machine 8 duration 24 mins.
Operation 6 on Machine 2 duration 268 mins.
Operation 7 on Machine 4 duration 100 mins.
Operation 8 on Machine 5 duration 154 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 1 duration 38 mins.
Operation 1 on Machine 4 duration 12 mins.
Operation 2 on Machine 6 duration 195 mins.
Operation 3 on Machine 0 duration 10 mins.
Operation 4 on Machine 7 duration 117 mins.
Operation 5 on Machine 5 duration 260 mins.
Operation 6 on Machine 2 duration 26 mins.
Operation 7 on Machine 3 duration 179 mins.
Operation 8 on Machine 8 duration 169 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 6 duration 288 mins.
Operation 1 on Machine 1 duration 225 mins.
Operation 2 on Machine 7 duration 267 mins.
Operation 3 on Machine 0 duration 53 mins.
Operation 4 on Machine 8 duration 45 mins.
Operation 5 on Machine 5 duration 280 mins.
Operation 6 on Machine 2 duration 167 mins.
Operation 7 on Machine 4 duration 236 mins.
Operation 8 on Machine 3 duration 32 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 2 duration 152 mins.
Operation 1 on Machine 6 duration 278 mins.
Operation 2 on Machine 8 duration 179 mins.
Operation 3 on Machine 1 duration 61 mins.
Operation 4 on Machine 0 duration 170 mins.
Operation 5 on Machine 3 duration 297 mins.
Operation 6 on Machine 4 duration 78 mins.
Operation 7 on Machine 7 duration 31 mins.
Operation 8 on Machine 5 duration 164 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 8 duration 102 mins.
Operation 1 on Machine 3 duration 203 mins.
Operation 2 on Machine 1 duration 21 mins.
Operation 3 on Machine 7 duration 85 mins.
Operation 4 on Machine 4 duration 15 mins.
Operation 5 on Machine 0 duration 196 mins.
Operation 6 on Machine 5 duration 242 mins.
Operation 7 on Machine 2 duration 208 mins.
Operation 8 on Machine 6 duration 6 mins.
Job 6 consists of the following Operations:
Operation 0 on Machine 8 duration 213 mins.
Operation 1 on Machine 4 duration 70 mins.
Operation 2 on Machine 2 duration 44 mins.
Operation 3 on Machine 7 duration 216 mins.
Operation 4 on Machine 1 duration 10 mins.
Operation 5 on Machine 5 duration 180 mins.
Operation 6 on Machine 0 duration 132 mins.
Operation 7 on Machine 6 duration 275 mins.
Operation 8 on Machine 3 duration 209 mins.
Job 7 consists of the following Operations:
Operation 0 on Machine 2 duration 10 mins.
Operation 1 on Machine 6 duration 79 mins.
Operation 2 on Machine 4 duration 23 mins.
Operation 3 on Machine 7 duration 6 mins.
Operation 4 on Machine 3 duration 185 mins.
Operation 5 on Machine 8 duration 278 mins.
Operation 6 on Machine 1 duration 145 mins.
Operation 7 on Machine 5 duration 47 mins.
Operation 8 on Machine 0 duration 82 mins.
Job 8 consists of the following Operations:
Operation 0 on Machine 3 duration 81 mins.
Operation 1 on Machine 2 duration 274 mins.
Operation 2 on Machine 4 duration 251 mins.
Operation 3 on Machine 5 duration 123 mins.
Operation 4 on Machine 0 duration 92 mins.
Operation 5 on Machine 1 duration 90 mins.
Operation 6 on Machine 6 duration 150 mins.
Operation 7 on Machine 7 duration 13 mins.
Operation 8 on Machine 8 duration 281 mins.
Job 9 consists of the following Operations:
Operation 0 on Machine 0 duration 193 mins.
Operation 1 on Machine 4 duration 90 mins.
Operation 2 on Machine 5 duration 99 mins.
Operation 3 on Machine 8 duration 117 mins.
Operation 4 on Machine 6 duration 202 mins.
Operation 5 on Machine 1 duration 81 mins.
Operation 6 on Machine 7 duration 231 mins.
Operation 7 on Machine 3 duration 249 mins.
Operation 8 on Machine 2 duration 3 mins.
| Optimize schedule for 10 Jobs across 9 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 9 Operation 0 duration 193 mins.
Job 1 Operation 2 duration 235 mins.
Job 0 Operation 3 duration 8 mins.
Job 2 Operation 3 duration 10 mins.
Job 3 Operation 3 duration 53 mins.
Job 4 Operation 4 duration 170 mins.
Job 8 Operation 4 duration 92 mins.
Job 5 Operation 5 duration 196 mins.
Job 6 Operation 6 duration 132 mins.
Job 7 Operation 8 duration 82 mins.
Machine 1 is used for the following Operations:
Job 0 Operation 0 duration 176 mins.
Job 1 Operation 0 duration 260 mins.
Job 2 Operation 0 duration 38 mins.
Job 3 Operation 1 duration 225 mins.
Job 5 Operation 2 duration 21 mins.
Job 4 Operation 3 duration 61 mins.
Job 6 Operation 4 duration 10 mins.
Job 8 Operation 5 duration 90 mins.
Job 9 Operation 5 duration 81 mins.
Job 7 Operation 6 duration 145 mins.
Machine 2 is used for the following Operations:
Job 4 Operation 0 duration 152 mins.
Job 7 Operation 0 duration 10 mins.
Job 0 Operation 1 duration 121 mins.
Job 8 Operation 1 duration 274 mins.
Job 6 Operation 2 duration 44 mins.
Job 1 Operation 6 duration 268 mins.
Job 2 Operation 6 duration 26 mins.
Job 3 Operation 6 duration 167 mins.
Job 5 Operation 7 duration 208 mins.
Job 9 Operation 8 duration 3 mins.
Machine 3 is used for the following Operations:
Job 8 Operation 0 duration 81 mins.
Job 5 Operation 1 duration 203 mins.
Job 1 Operation 3 duration 256 mins.
Job 7 Operation 4 duration 185 mins.
Job 4 Operation 5 duration 297 mins.
Job 2 Operation 7 duration 179 mins.
Job 9 Operation 7 duration 249 mins.
Job 0 Operation 8 duration 280 mins.
Job 3 Operation 8 duration 32 mins.
Job 6 Operation 8 duration 209 mins.
Machine 4 is used for the following Operations:
Job 2 Operation 1 duration 12 mins.
Job 6 Operation 1 duration 70 mins.
Job 9 Operation 1 duration 90 mins.
Job 7 Operation 2 duration 23 mins.
Job 8 Operation 2 duration 251 mins.
Job 5 Operation 4 duration 15 mins.
Job 4 Operation 6 duration 78 mins.
Job 0 Operation 7 duration 112 mins.
Job 1 Operation 7 duration 100 mins.
Job 3 Operation 7 duration 236 mins.
Machine 5 is used for the following Operations:
Job 0 Operation 2 duration 53 mins.
Job 9 Operation 2 duration 99 mins.
Job 8 Operation 3 duration 123 mins.
Job 2 Operation 5 duration 260 mins.
Job 3 Operation 5 duration 280 mins.
Job 6 Operation 5 duration 180 mins.
Job 5 Operation 6 duration 242 mins.
Job 7 Operation 7 duration 47 mins.
Job 1 Operation 8 duration 154 mins.
Job 4 Operation 8 duration 164 mins.
Machine 6 is used for the following Operations:
Job 3 Operation 0 duration 288 mins.
Job 1 Operation 1 duration 127 mins.
Job 4 Operation 1 duration 278 mins.
Job 7 Operation 1 duration 79 mins.
Job 2 Operation 2 duration 195 mins.
Job 9 Operation 4 duration 202 mins.
Job 0 Operation 6 duration 60 mins.
Job 8 Operation 6 duration 150 mins.
Job 6 Operation 7 duration 275 mins.
Job 5 Operation 8 duration 6 mins.
Machine 7 is used for the following Operations:
Job 3 Operation 2 duration 267 mins.
Job 5 Operation 3 duration 85 mins.
Job 6 Operation 3 duration 216 mins.
Job 7 Operation 3 duration 6 mins.
Job 0 Operation 4 duration 153 mins.
Job 1 Operation 4 duration 209 mins.
Job 2 Operation 4 duration 117 mins.
Job 9 Operation 6 duration 231 mins.
Job 4 Operation 7 duration 31 mins.
Job 8 Operation 7 duration 13 mins.
Machine 8 is used for the following Operations:
Job 5 Operation 0 duration 102 mins.
Job 6 Operation 0 duration 213 mins.
Job 4 Operation 2 duration 179 mins.
Job 9 Operation 3 duration 117 mins.
Job 3 Operation 4 duration 45 mins.
Job 0 Operation 5 duration 200 mins.
Job 1 Operation 5 duration 24 mins.
Job 7 Operation 5 duration 278 mins.
Job 2 Operation 8 duration 169 mins.
Job 8 Operation 8 duration 281 mins.
| Solution:
Job 9 Operation 0 on Machine 0 : 0 + 193 -> 193
Job 2 Operation 0 on Machine 1 : 0 + 38 -> 38
Job 7 Operation 0 on Machine 2 : 0 + 10 -> 10
Job 8 Operation 0 on Machine 3 : 0 + 81 -> 81
Job 6 Operation 0 on Machine 8 : 0 + 213 -> 213
Job 4 Operation 0 on Machine 2 : 10 + 152 -> 162
Job 7 Operation 1 on Machine 6 : 10 + 79 -> 89
Job 0 Operation 0 on Machine 1 : 38 + 176 -> 214
Job 2 Operation 1 on Machine 4 : 38 + 12 -> 50
Job 7 Operation 2 on Machine 4 : 89 + 23 -> 112
Job 2 Operation 2 on Machine 6 : 89 + 195 -> 284
Job 7 Operation 3 on Machine 7 : 112 + 6 -> 118
Job 7 Operation 4 on Machine 3 : 118 + 185 -> 303
Job 6 Operation 1 on Machine 4 : 213 + 70 -> 283
Job 5 Operation 0 on Machine 8 : 213 + 102 -> 315
Job 1 Operation 0 on Machine 1 : 214 + 260 -> 474
Job 0 Operation 1 on Machine 2 : 214 + 121 -> 335
Job 9 Operation 1 on Machine 4 : 283 + 90 -> 373
Job 2 Operation 3 on Machine 0 : 284 + 10 -> 294
Job 3 Operation 0 on Machine 6 : 284 + 288 -> 572
Job 2 Operation 4 on Machine 7 : 294 + 117 -> 411
Job 5 Operation 1 on Machine 3 : 315 + 203 -> 518
Job 7 Operation 5 on Machine 8 : 315 + 278 -> 593
Job 6 Operation 2 on Machine 2 : 335 + 44 -> 379
Job 0 Operation 2 on Machine 5 : 335 + 53 -> 388
Job 8 Operation 1 on Machine 2 : 379 + 274 -> 653
Job 0 Operation 3 on Machine 0 : 388 + 8 -> 396
Job 2 Operation 5 on Machine 5 : 411 + 260 -> 671
Job 0 Operation 4 on Machine 7 : 411 + 153 -> 564
Job 5 Operation 2 on Machine 1 : 518 + 21 -> 539
Job 6 Operation 3 on Machine 7 : 564 + 216 -> 780
Job 3 Operation 1 on Machine 1 : 572 + 225 -> 797
Job 1 Operation 1 on Machine 6 : 572 + 127 -> 699
Job 0 Operation 5 on Machine 8 : 593 + 200 -> 793
Job 8 Operation 2 on Machine 4 : 653 + 251 -> 904
Job 2 Operation 6 on Machine 2 : 671 + 26 -> 697
Job 9 Operation 2 on Machine 5 : 671 + 99 -> 770
Job 2 Operation 7 on Machine 3 : 697 + 179 -> 876
Job 1 Operation 2 on Machine 0 : 699 + 235 -> 934
Job 4 Operation 1 on Machine 6 : 699 + 278 -> 977
Job 9 Operation 3 on Machine 8 : 793 + 117 -> 910
Job 6 Operation 4 on Machine 1 : 797 + 10 -> 807
Job 3 Operation 2 on Machine 7 : 797 + 267 -> 1064
Job 7 Operation 6 on Machine 1 : 807 + 145 -> 952
Job 6 Operation 5 on Machine 5 : 807 + 180 -> 987
Job 1 Operation 3 on Machine 3 : 934 + 256 -> 1190
Job 0 Operation 6 on Machine 6 : 977 + 60 -> 1037
Job 4 Operation 2 on Machine 8 : 977 + 179 -> 1156
Job 6 Operation 6 on Machine 0 : 987 + 132 -> 1119
Job 8 Operation 3 on Machine 5 : 987 + 123 -> 1110
Job 0 Operation 7 on Machine 4 : 1037 + 112 -> 1149
Job 9 Operation 4 on Machine 6 : 1037 + 202 -> 1239
Job 5 Operation 3 on Machine 7 : 1064 + 85 -> 1149
Job 7 Operation 7 on Machine 5 : 1110 + 47 -> 1157
Job 3 Operation 3 on Machine 0 : 1119 + 53 -> 1172
Job 5 Operation 4 on Machine 4 : 1149 + 15 -> 1164
Job 4 Operation 3 on Machine 1 : 1156 + 61 -> 1217
Job 3 Operation 4 on Machine 8 : 1172 + 45 -> 1217
Job 0 Operation 8 on Machine 3 : 1190 + 280 -> 1470
Job 1 Operation 4 on Machine 7 : 1190 + 209 -> 1399
Job 4 Operation 4 on Machine 0 : 1217 + 170 -> 1387
Job 3 Operation 5 on Machine 5 : 1217 + 280 -> 1497
Job 9 Operation 5 on Machine 1 : 1239 + 81 -> 1320
Job 6 Operation 7 on Machine 6 : 1239 + 275 -> 1514
Job 8 Operation 4 on Machine 0 : 1387 + 92 -> 1479
Job 9 Operation 6 on Machine 7 : 1399 + 231 -> 1630
Job 1 Operation 5 on Machine 8 : 1399 + 24 -> 1423
Job 1 Operation 6 on Machine 2 : 1423 + 268 -> 1691
Job 2 Operation 8 on Machine 8 : 1423 + 169 -> 1592
Job 4 Operation 5 on Machine 3 : 1470 + 297 -> 1767
Job 5 Operation 5 on Machine 0 : 1479 + 196 -> 1675
Job 8 Operation 5 on Machine 1 : 1479 + 90 -> 1569
Job 8 Operation 6 on Machine 6 : 1569 + 150 -> 1719
Job 7 Operation 8 on Machine 0 : 1675 + 82 -> 1757
Job 5 Operation 6 on Machine 5 : 1675 + 242 -> 1917
Job 3 Operation 6 on Machine 2 : 1691 + 167 -> 1858
Job 8 Operation 7 on Machine 7 : 1719 + 13 -> 1732
Job 8 Operation 8 on Machine 8 : 1732 + 281 -> 2013
Job 6 Operation 8 on Machine 3 : 1767 + 209 -> 1976
Job 4 Operation 6 on Machine 4 : 1767 + 78 -> 1845
Job 1 Operation 7 on Machine 4 : 1845 + 100 -> 1945
Job 4 Operation 7 on Machine 7 : 1845 + 31 -> 1876
Job 5 Operation 7 on Machine 2 : 1917 + 208 -> 2125
Job 4 Operation 8 on Machine 5 : 1917 + 164 -> 2081
Job 3 Operation 7 on Machine 4 : 1945 + 236 -> 2181
Job 9 Operation 7 on Machine 3 : 1976 + 249 -> 2225
Job 1 Operation 8 on Machine 5 : 2081 + 154 -> 2235
Job 5 Operation 8 on Machine 6 : 2125 + 6 -> 2131
Job 9 Operation 8 on Machine 2 : 2225 + 3 -> 2228
Job 3 Operation 8 on Machine 3 : 2225 + 32 -> 2257
Makespan: 2257.0, as it is the maximum end completion time of Operation 8 |
8 | 4 | Optimize schedule for 8 Jobs across 4 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 1 duration 280 mins.
Operation 1 on Machine 0 duration 214 mins.
Operation 2 on Machine 3 duration 313 mins.
Operation 3 on Machine 2 duration 326 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 0 duration 159 mins.
Operation 1 on Machine 1 duration 54 mins.
Operation 2 on Machine 2 duration 236 mins.
Operation 3 on Machine 3 duration 312 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 2 duration 278 mins.
Operation 1 on Machine 0 duration 363 mins.
Operation 2 on Machine 1 duration 297 mins.
Operation 3 on Machine 3 duration 249 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 0 duration 39 mins.
Operation 1 on Machine 3 duration 24 mins.
Operation 2 on Machine 2 duration 261 mins.
Operation 3 on Machine 1 duration 135 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 1 duration 171 mins.
Operation 1 on Machine 0 duration 345 mins.
Operation 2 on Machine 2 duration 131 mins.
Operation 3 on Machine 3 duration 33 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 3 duration 199 mins.
Operation 1 on Machine 1 duration 127 mins.
Operation 2 on Machine 0 duration 314 mins.
Operation 3 on Machine 2 duration 52 mins.
Job 6 consists of the following Operations:
Operation 0 on Machine 0 duration 244 mins.
Operation 1 on Machine 3 duration 23 mins.
Operation 2 on Machine 2 duration 267 mins.
Operation 3 on Machine 1 duration 362 mins.
Job 7 consists of the following Operations:
Operation 0 on Machine 0 duration 228 mins.
Operation 1 on Machine 1 duration 31 mins.
Operation 2 on Machine 2 duration 416 mins.
Operation 3 on Machine 3 duration 283 mins.
| Optimize schedule for 8 Jobs across 4 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 1 Operation 0 duration 159 mins.
Job 3 Operation 0 duration 39 mins.
Job 6 Operation 0 duration 244 mins.
Job 7 Operation 0 duration 228 mins.
Job 0 Operation 1 duration 214 mins.
Job 2 Operation 1 duration 363 mins.
Job 4 Operation 1 duration 345 mins.
Job 5 Operation 2 duration 314 mins.
Machine 1 is used for the following Operations:
Job 0 Operation 0 duration 280 mins.
Job 4 Operation 0 duration 171 mins.
Job 1 Operation 1 duration 54 mins.
Job 5 Operation 1 duration 127 mins.
Job 7 Operation 1 duration 31 mins.
Job 2 Operation 2 duration 297 mins.
Job 3 Operation 3 duration 135 mins.
Job 6 Operation 3 duration 362 mins.
Machine 2 is used for the following Operations:
Job 2 Operation 0 duration 278 mins.
Job 1 Operation 2 duration 236 mins.
Job 3 Operation 2 duration 261 mins.
Job 4 Operation 2 duration 131 mins.
Job 6 Operation 2 duration 267 mins.
Job 7 Operation 2 duration 416 mins.
Job 0 Operation 3 duration 326 mins.
Job 5 Operation 3 duration 52 mins.
Machine 3 is used for the following Operations:
Job 5 Operation 0 duration 199 mins.
Job 3 Operation 1 duration 24 mins.
Job 6 Operation 1 duration 23 mins.
Job 0 Operation 2 duration 313 mins.
Job 1 Operation 3 duration 312 mins.
Job 2 Operation 3 duration 249 mins.
Job 4 Operation 3 duration 33 mins.
Job 7 Operation 3 duration 283 mins.
| Solution:
Job 3 Operation 0 on Machine 0 : 0 + 39 -> 39
Job 4 Operation 0 on Machine 1 : 0 + 171 -> 171
Job 2 Operation 0 on Machine 2 : 0 + 278 -> 278
Job 5 Operation 0 on Machine 3 : 0 + 199 -> 199
Job 1 Operation 0 on Machine 0 : 39 + 159 -> 198
Job 6 Operation 0 on Machine 0 : 198 + 244 -> 442
Job 1 Operation 1 on Machine 1 : 198 + 54 -> 252
Job 3 Operation 1 on Machine 3 : 199 + 24 -> 223
Job 0 Operation 0 on Machine 1 : 252 + 280 -> 532
Job 3 Operation 2 on Machine 2 : 278 + 261 -> 539
Job 7 Operation 0 on Machine 0 : 442 + 228 -> 670
Job 6 Operation 1 on Machine 3 : 442 + 23 -> 465
Job 3 Operation 3 on Machine 1 : 539 + 135 -> 674
Job 1 Operation 2 on Machine 2 : 539 + 236 -> 775
Job 0 Operation 1 on Machine 0 : 670 + 214 -> 884
Job 7 Operation 1 on Machine 1 : 674 + 31 -> 705
Job 5 Operation 1 on Machine 1 : 705 + 127 -> 832
Job 7 Operation 2 on Machine 2 : 775 + 416 -> 1191
Job 1 Operation 3 on Machine 3 : 775 + 312 -> 1087
Job 2 Operation 1 on Machine 0 : 884 + 363 -> 1247
Job 0 Operation 2 on Machine 3 : 1087 + 313 -> 1400
Job 6 Operation 2 on Machine 2 : 1191 + 267 -> 1458
Job 4 Operation 1 on Machine 0 : 1247 + 345 -> 1592
Job 2 Operation 2 on Machine 1 : 1247 + 297 -> 1544
Job 7 Operation 3 on Machine 3 : 1400 + 283 -> 1683
Job 0 Operation 3 on Machine 2 : 1458 + 326 -> 1784
Job 6 Operation 3 on Machine 1 : 1544 + 362 -> 1906
Job 5 Operation 2 on Machine 0 : 1592 + 314 -> 1906
Job 2 Operation 3 on Machine 3 : 1683 + 249 -> 1932
Job 4 Operation 2 on Machine 2 : 1784 + 131 -> 1915
Job 5 Operation 3 on Machine 2 : 1915 + 52 -> 1967
Job 4 Operation 3 on Machine 3 : 1932 + 33 -> 1965
Makespan: 1967.0, as it is the maximum end completion time of Operation 3 |
7 | 7 | Optimize schedule for 7 Jobs across 7 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 0 duration 35 mins.
Operation 1 on Machine 6 duration 53 mins.
Operation 2 on Machine 1 duration 16 mins.
Operation 3 on Machine 3 duration 90 mins.
Operation 4 on Machine 4 duration 85 mins.
Operation 5 on Machine 2 duration 74 mins.
Operation 6 on Machine 5 duration 13 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 0 duration 61 mins.
Operation 1 on Machine 5 duration 62 mins.
Operation 2 on Machine 4 duration 65 mins.
Operation 3 on Machine 2 duration 84 mins.
Operation 4 on Machine 1 duration 57 mins.
Operation 5 on Machine 6 duration 77 mins.
Operation 6 on Machine 3 duration 66 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 0 duration 5 mins.
Operation 1 on Machine 4 duration 71 mins.
Operation 2 on Machine 5 duration 44 mins.
Operation 3 on Machine 6 duration 5 mins.
Operation 4 on Machine 1 duration 46 mins.
Operation 5 on Machine 3 duration 87 mins.
Operation 6 on Machine 2 duration 10 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 3 duration 19 mins.
Operation 1 on Machine 0 duration 51 mins.
Operation 2 on Machine 6 duration 84 mins.
Operation 3 on Machine 2 duration 3 mins.
Operation 4 on Machine 1 duration 5 mins.
Operation 5 on Machine 5 duration 74 mins.
Operation 6 on Machine 4 duration 21 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 3 duration 72 mins.
Operation 1 on Machine 1 duration 90 mins.
Operation 2 on Machine 0 duration 2 mins.
Operation 3 on Machine 6 duration 58 mins.
Operation 4 on Machine 5 duration 81 mins.
Operation 5 on Machine 2 duration 60 mins.
Operation 6 on Machine 4 duration 20 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 3 duration 74 mins.
Operation 1 on Machine 0 duration 44 mins.
Operation 2 on Machine 2 duration 36 mins.
Operation 3 on Machine 5 duration 25 mins.
Operation 4 on Machine 1 duration 94 mins.
Operation 5 on Machine 6 duration 89 mins.
Operation 6 on Machine 4 duration 78 mins.
Job 6 consists of the following Operations:
Operation 0 on Machine 3 duration 70 mins.
Operation 1 on Machine 2 duration 6 mins.
Operation 2 on Machine 6 duration 19 mins.
Operation 3 on Machine 5 duration 80 mins.
Operation 4 on Machine 1 duration 8 mins.
Operation 5 on Machine 0 duration 38 mins.
Operation 6 on Machine 4 duration 93 mins.
| Optimize schedule for 7 Jobs across 7 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 0 Operation 0 duration 35 mins.
Job 1 Operation 0 duration 61 mins.
Job 2 Operation 0 duration 5 mins.
Job 3 Operation 1 duration 51 mins.
Job 5 Operation 1 duration 44 mins.
Job 4 Operation 2 duration 2 mins.
Job 6 Operation 5 duration 38 mins.
Machine 1 is used for the following Operations:
Job 4 Operation 1 duration 90 mins.
Job 0 Operation 2 duration 16 mins.
Job 1 Operation 4 duration 57 mins.
Job 2 Operation 4 duration 46 mins.
Job 3 Operation 4 duration 5 mins.
Job 5 Operation 4 duration 94 mins.
Job 6 Operation 4 duration 8 mins.
Machine 2 is used for the following Operations:
Job 6 Operation 1 duration 6 mins.
Job 5 Operation 2 duration 36 mins.
Job 1 Operation 3 duration 84 mins.
Job 3 Operation 3 duration 3 mins.
Job 0 Operation 5 duration 74 mins.
Job 4 Operation 5 duration 60 mins.
Job 2 Operation 6 duration 10 mins.
Machine 3 is used for the following Operations:
Job 3 Operation 0 duration 19 mins.
Job 4 Operation 0 duration 72 mins.
Job 5 Operation 0 duration 74 mins.
Job 6 Operation 0 duration 70 mins.
Job 0 Operation 3 duration 90 mins.
Job 2 Operation 5 duration 87 mins.
Job 1 Operation 6 duration 66 mins.
Machine 4 is used for the following Operations:
Job 2 Operation 1 duration 71 mins.
Job 1 Operation 2 duration 65 mins.
Job 0 Operation 4 duration 85 mins.
Job 3 Operation 6 duration 21 mins.
Job 4 Operation 6 duration 20 mins.
Job 5 Operation 6 duration 78 mins.
Job 6 Operation 6 duration 93 mins.
Machine 5 is used for the following Operations:
Job 1 Operation 1 duration 62 mins.
Job 2 Operation 2 duration 44 mins.
Job 5 Operation 3 duration 25 mins.
Job 6 Operation 3 duration 80 mins.
Job 4 Operation 4 duration 81 mins.
Job 3 Operation 5 duration 74 mins.
Job 0 Operation 6 duration 13 mins.
Machine 6 is used for the following Operations:
Job 0 Operation 1 duration 53 mins.
Job 3 Operation 2 duration 84 mins.
Job 6 Operation 2 duration 19 mins.
Job 2 Operation 3 duration 5 mins.
Job 4 Operation 3 duration 58 mins.
Job 1 Operation 5 duration 77 mins.
Job 5 Operation 5 duration 89 mins.
| Solution:
Job 2 Operation 0 on Machine 0 : 0 + 5 -> 5
Job 6 Operation 0 on Machine 3 : 0 + 70 -> 70
Job 1 Operation 0 on Machine 0 : 5 + 61 -> 66
Job 2 Operation 1 on Machine 4 : 5 + 71 -> 76
Job 0 Operation 0 on Machine 0 : 66 + 35 -> 101
Job 1 Operation 1 on Machine 5 : 66 + 62 -> 128
Job 6 Operation 1 on Machine 2 : 70 + 6 -> 76
Job 4 Operation 0 on Machine 3 : 70 + 72 -> 142
Job 6 Operation 2 on Machine 6 : 76 + 19 -> 95
Job 0 Operation 1 on Machine 6 : 101 + 53 -> 154
Job 1 Operation 2 on Machine 4 : 128 + 65 -> 193
Job 6 Operation 3 on Machine 5 : 128 + 80 -> 208
Job 4 Operation 1 on Machine 1 : 142 + 90 -> 232
Job 3 Operation 0 on Machine 3 : 142 + 19 -> 161
Job 3 Operation 1 on Machine 0 : 161 + 51 -> 212
Job 5 Operation 0 on Machine 3 : 161 + 74 -> 235
Job 1 Operation 3 on Machine 2 : 193 + 84 -> 277
Job 2 Operation 2 on Machine 5 : 208 + 44 -> 252
Job 3 Operation 2 on Machine 6 : 212 + 84 -> 296
Job 4 Operation 2 on Machine 0 : 232 + 2 -> 234
Job 0 Operation 2 on Machine 1 : 232 + 16 -> 248
Job 5 Operation 1 on Machine 0 : 235 + 44 -> 279
Job 6 Operation 4 on Machine 1 : 248 + 8 -> 256
Job 0 Operation 3 on Machine 3 : 248 + 90 -> 338
Job 1 Operation 4 on Machine 1 : 277 + 57 -> 334
Job 6 Operation 5 on Machine 0 : 279 + 38 -> 317
Job 5 Operation 2 on Machine 2 : 279 + 36 -> 315
Job 4 Operation 3 on Machine 6 : 296 + 58 -> 354
Job 3 Operation 3 on Machine 2 : 315 + 3 -> 318
Job 5 Operation 3 on Machine 5 : 315 + 25 -> 340
Job 6 Operation 6 on Machine 4 : 317 + 93 -> 410
Job 3 Operation 4 on Machine 1 : 334 + 5 -> 339
Job 5 Operation 4 on Machine 1 : 340 + 94 -> 434
Job 4 Operation 4 on Machine 5 : 354 + 81 -> 435
Job 1 Operation 5 on Machine 6 : 354 + 77 -> 431
Job 0 Operation 4 on Machine 4 : 410 + 85 -> 495
Job 1 Operation 6 on Machine 3 : 431 + 66 -> 497
Job 2 Operation 3 on Machine 6 : 431 + 5 -> 436
Job 4 Operation 5 on Machine 2 : 435 + 60 -> 495
Job 3 Operation 5 on Machine 5 : 435 + 74 -> 509
Job 2 Operation 4 on Machine 1 : 436 + 46 -> 482
Job 5 Operation 5 on Machine 6 : 436 + 89 -> 525
Job 0 Operation 5 on Machine 2 : 495 + 74 -> 569
Job 4 Operation 6 on Machine 4 : 495 + 20 -> 515
Job 2 Operation 5 on Machine 3 : 497 + 87 -> 584
Job 3 Operation 6 on Machine 4 : 515 + 21 -> 536
Job 5 Operation 6 on Machine 4 : 536 + 78 -> 614
Job 0 Operation 6 on Machine 5 : 569 + 13 -> 582
Job 2 Operation 6 on Machine 2 : 584 + 10 -> 594
Makespan: 614.0, as it is the maximum end completion time of Operation 6 |
3 | 3 | Optimize schedule for 3 Jobs across 3 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 1 duration 422 mins.
Operation 1 on Machine 2 duration 314 mins.
Operation 2 on Machine 0 duration 414 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 2 duration 320 mins.
Operation 1 on Machine 0 duration 182 mins.
Operation 2 on Machine 1 duration 117 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 0 duration 55 mins.
Operation 1 on Machine 1 duration 128 mins.
Operation 2 on Machine 2 duration 293 mins.
| Optimize schedule for 3 Jobs across 3 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 2 Operation 0 duration 55 mins.
Job 1 Operation 1 duration 182 mins.
Job 0 Operation 2 duration 414 mins.
Machine 1 is used for the following Operations:
Job 0 Operation 0 duration 422 mins.
Job 2 Operation 1 duration 128 mins.
Job 1 Operation 2 duration 117 mins.
Machine 2 is used for the following Operations:
Job 1 Operation 0 duration 320 mins.
Job 0 Operation 1 duration 314 mins.
Job 2 Operation 2 duration 293 mins.
| Solution:
Job 2 Operation 0 on Machine 0 : 0 + 55 -> 55
Job 0 Operation 0 on Machine 1 : 0 + 422 -> 422
Job 1 Operation 0 on Machine 2 : 0 + 320 -> 320
Job 1 Operation 1 on Machine 0 : 320 + 182 -> 502
Job 2 Operation 1 on Machine 1 : 422 + 128 -> 550
Job 0 Operation 1 on Machine 2 : 422 + 314 -> 736
Job 1 Operation 2 on Machine 1 : 550 + 117 -> 667
Job 0 Operation 2 on Machine 0 : 736 + 414 -> 1150
Job 2 Operation 2 on Machine 2 : 736 + 293 -> 1029
Makespan: 1150.0, as it is the maximum end completion time of Operation 2 |
6 | 2 | Optimize schedule for 6 Jobs across 2 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 1 duration 208 mins.
Operation 1 on Machine 0 duration 239 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 0 duration 48 mins.
Operation 1 on Machine 1 duration 199 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 0 duration 10 mins.
Operation 1 on Machine 1 duration 224 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 0 duration 235 mins.
Operation 1 on Machine 1 duration 96 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 0 duration 101 mins.
Operation 1 on Machine 1 duration 111 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 1 duration 151 mins.
Operation 1 on Machine 0 duration 166 mins.
| Optimize schedule for 6 Jobs across 2 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 1 Operation 0 duration 48 mins.
Job 2 Operation 0 duration 10 mins.
Job 3 Operation 0 duration 235 mins.
Job 4 Operation 0 duration 101 mins.
Job 0 Operation 1 duration 239 mins.
Job 5 Operation 1 duration 166 mins.
Machine 1 is used for the following Operations:
Job 0 Operation 0 duration 208 mins.
Job 5 Operation 0 duration 151 mins.
Job 1 Operation 1 duration 199 mins.
Job 2 Operation 1 duration 224 mins.
Job 3 Operation 1 duration 96 mins.
Job 4 Operation 1 duration 111 mins.
| Solution:
Job 2 Operation 0 on Machine 0 : 0 + 10 -> 10
Job 5 Operation 0 on Machine 1 : 0 + 151 -> 151
Job 1 Operation 0 on Machine 0 : 10 + 48 -> 58
Job 4 Operation 0 on Machine 0 : 58 + 101 -> 159
Job 1 Operation 1 on Machine 1 : 151 + 199 -> 350
Job 5 Operation 1 on Machine 0 : 159 + 166 -> 325
Job 3 Operation 0 on Machine 0 : 325 + 235 -> 560
Job 4 Operation 1 on Machine 1 : 350 + 111 -> 461
Job 0 Operation 0 on Machine 1 : 461 + 208 -> 669
Job 0 Operation 1 on Machine 0 : 669 + 239 -> 908
Job 3 Operation 1 on Machine 1 : 669 + 96 -> 765
Job 2 Operation 1 on Machine 1 : 765 + 224 -> 989
Makespan: 989.0, as it is the maximum end completion time of Operation 1 |
9 | 4 | Optimize schedule for 9 Jobs across 4 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 0 duration 2 mins.
Operation 1 on Machine 2 duration 1 mins.
Operation 2 on Machine 1 duration 3 mins.
Operation 3 on Machine 3 duration 4 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 3 duration 4 mins.
Operation 1 on Machine 2 duration 2 mins.
Operation 2 on Machine 1 duration 4 mins.
Operation 3 on Machine 0 duration 3 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 1 duration 3 mins.
Operation 1 on Machine 3 duration 3 mins.
Operation 2 on Machine 0 duration 1 mins.
Operation 3 on Machine 2 duration 4 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 0 duration 1 mins.
Operation 1 on Machine 2 duration 2 mins.
Operation 2 on Machine 3 duration 4 mins.
Operation 3 on Machine 1 duration 3 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 3 duration 1 mins.
Operation 1 on Machine 2 duration 4 mins.
Operation 2 on Machine 0 duration 3 mins.
Operation 3 on Machine 1 duration 2 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 0 duration 1 mins.
Operation 1 on Machine 1 duration 3 mins.
Operation 2 on Machine 2 duration 4 mins.
Operation 3 on Machine 3 duration 2 mins.
Job 6 consists of the following Operations:
Operation 0 on Machine 1 duration 2 mins.
Operation 1 on Machine 3 duration 1 mins.
Operation 2 on Machine 2 duration 1 mins.
Operation 3 on Machine 0 duration 2 mins.
Job 7 consists of the following Operations:
Operation 0 on Machine 0 duration 2 mins.
Operation 1 on Machine 1 duration 4 mins.
Operation 2 on Machine 2 duration 1 mins.
Operation 3 on Machine 3 duration 1 mins.
Job 8 consists of the following Operations:
Operation 0 on Machine 0 duration 3 mins.
Operation 1 on Machine 3 duration 1 mins.
Operation 2 on Machine 1 duration 4 mins.
Operation 3 on Machine 2 duration 2 mins.
| Optimize schedule for 9 Jobs across 4 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 0 Operation 0 duration 2 mins.
Job 3 Operation 0 duration 1 mins.
Job 5 Operation 0 duration 1 mins.
Job 7 Operation 0 duration 2 mins.
Job 8 Operation 0 duration 3 mins.
Job 2 Operation 2 duration 1 mins.
Job 4 Operation 2 duration 3 mins.
Job 1 Operation 3 duration 3 mins.
Job 6 Operation 3 duration 2 mins.
Machine 1 is used for the following Operations:
Job 2 Operation 0 duration 3 mins.
Job 6 Operation 0 duration 2 mins.
Job 5 Operation 1 duration 3 mins.
Job 7 Operation 1 duration 4 mins.
Job 0 Operation 2 duration 3 mins.
Job 1 Operation 2 duration 4 mins.
Job 8 Operation 2 duration 4 mins.
Job 3 Operation 3 duration 3 mins.
Job 4 Operation 3 duration 2 mins.
Machine 2 is used for the following Operations:
Job 0 Operation 1 duration 1 mins.
Job 1 Operation 1 duration 2 mins.
Job 3 Operation 1 duration 2 mins.
Job 4 Operation 1 duration 4 mins.
Job 5 Operation 2 duration 4 mins.
Job 6 Operation 2 duration 1 mins.
Job 7 Operation 2 duration 1 mins.
Job 2 Operation 3 duration 4 mins.
Job 8 Operation 3 duration 2 mins.
Machine 3 is used for the following Operations:
Job 1 Operation 0 duration 4 mins.
Job 4 Operation 0 duration 1 mins.
Job 2 Operation 1 duration 3 mins.
Job 6 Operation 1 duration 1 mins.
Job 8 Operation 1 duration 1 mins.
Job 3 Operation 2 duration 4 mins.
Job 0 Operation 3 duration 4 mins.
Job 5 Operation 3 duration 2 mins.
Job 7 Operation 3 duration 1 mins.
| Solution:
Job 3 Operation 0 on Machine 0 : 0 + 1 -> 1
Job 2 Operation 0 on Machine 1 : 0 + 3 -> 3
Job 1 Operation 0 on Machine 3 : 0 + 4 -> 4
Job 5 Operation 0 on Machine 0 : 1 + 1 -> 2
Job 3 Operation 1 on Machine 2 : 1 + 2 -> 3
Job 0 Operation 0 on Machine 0 : 2 + 2 -> 4
Job 5 Operation 1 on Machine 1 : 3 + 3 -> 6
Job 8 Operation 0 on Machine 0 : 4 + 3 -> 7
Job 1 Operation 1 on Machine 2 : 4 + 2 -> 6
Job 2 Operation 1 on Machine 3 : 4 + 3 -> 7
Job 1 Operation 2 on Machine 1 : 6 + 4 -> 10
Job 0 Operation 1 on Machine 2 : 6 + 1 -> 7
Job 2 Operation 2 on Machine 0 : 7 + 1 -> 8
Job 8 Operation 1 on Machine 3 : 7 + 1 -> 8
Job 7 Operation 0 on Machine 0 : 8 + 2 -> 10
Job 2 Operation 3 on Machine 2 : 8 + 4 -> 12
Job 4 Operation 0 on Machine 3 : 8 + 1 -> 9
Job 3 Operation 2 on Machine 3 : 9 + 4 -> 13
Job 1 Operation 3 on Machine 0 : 10 + 3 -> 13
Job 0 Operation 2 on Machine 1 : 10 + 3 -> 13
Job 5 Operation 2 on Machine 2 : 12 + 4 -> 16
Job 7 Operation 1 on Machine 1 : 13 + 4 -> 17
Job 0 Operation 3 on Machine 3 : 13 + 4 -> 17
Job 3 Operation 3 on Machine 1 : 17 + 3 -> 20
Job 7 Operation 2 on Machine 2 : 17 + 1 -> 18
Job 4 Operation 1 on Machine 2 : 18 + 4 -> 22
Job 7 Operation 3 on Machine 3 : 18 + 1 -> 19
Job 5 Operation 3 on Machine 3 : 19 + 2 -> 21
Job 6 Operation 0 on Machine 1 : 20 + 2 -> 22
Job 4 Operation 2 on Machine 0 : 22 + 3 -> 25
Job 8 Operation 2 on Machine 1 : 22 + 4 -> 26
Job 6 Operation 1 on Machine 3 : 22 + 1 -> 23
Job 6 Operation 2 on Machine 2 : 23 + 1 -> 24
Job 6 Operation 3 on Machine 0 : 25 + 2 -> 27
Job 4 Operation 3 on Machine 1 : 26 + 2 -> 28
Job 8 Operation 3 on Machine 2 : 26 + 2 -> 28
Makespan: 28.0, as it is the maximum end completion time of Operation 3 |
9 | 2 | Optimize schedule for 9 Jobs across 2 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 0 duration 125 mins.
Operation 1 on Machine 1 duration 110 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 1 duration 38 mins.
Operation 1 on Machine 0 duration 81 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 1 duration 142 mins.
Operation 1 on Machine 0 duration 86 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 0 duration 15 mins.
Operation 1 on Machine 1 duration 158 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 0 duration 146 mins.
Operation 1 on Machine 1 duration 93 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 0 duration 184 mins.
Operation 1 on Machine 1 duration 37 mins.
Job 6 consists of the following Operations:
Operation 0 on Machine 0 duration 170 mins.
Operation 1 on Machine 1 duration 10 mins.
Job 7 consists of the following Operations:
Operation 0 on Machine 0 duration 31 mins.
Operation 1 on Machine 1 duration 78 mins.
Job 8 consists of the following Operations:
Operation 0 on Machine 1 duration 15 mins.
Operation 1 on Machine 0 duration 22 mins.
| Optimize schedule for 9 Jobs across 2 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 0 Operation 0 duration 125 mins.
Job 3 Operation 0 duration 15 mins.
Job 4 Operation 0 duration 146 mins.
Job 5 Operation 0 duration 184 mins.
Job 6 Operation 0 duration 170 mins.
Job 7 Operation 0 duration 31 mins.
Job 1 Operation 1 duration 81 mins.
Job 2 Operation 1 duration 86 mins.
Job 8 Operation 1 duration 22 mins.
Machine 1 is used for the following Operations:
Job 1 Operation 0 duration 38 mins.
Job 2 Operation 0 duration 142 mins.
Job 8 Operation 0 duration 15 mins.
Job 0 Operation 1 duration 110 mins.
Job 3 Operation 1 duration 158 mins.
Job 4 Operation 1 duration 93 mins.
Job 5 Operation 1 duration 37 mins.
Job 6 Operation 1 duration 10 mins.
Job 7 Operation 1 duration 78 mins.
| Solution:
Job 3 Operation 0 on Machine 0 : 0 + 15 -> 15
Job 8 Operation 0 on Machine 1 : 0 + 15 -> 15
Job 6 Operation 0 on Machine 0 : 15 + 170 -> 185
Job 3 Operation 1 on Machine 1 : 15 + 158 -> 173
Job 4 Operation 0 on Machine 0 : 185 + 146 -> 331
Job 6 Operation 1 on Machine 1 : 185 + 10 -> 195
Job 1 Operation 0 on Machine 1 : 195 + 38 -> 233
Job 8 Operation 1 on Machine 0 : 331 + 22 -> 353
Job 4 Operation 1 on Machine 1 : 331 + 93 -> 424
Job 7 Operation 0 on Machine 0 : 353 + 31 -> 384
Job 1 Operation 1 on Machine 0 : 384 + 81 -> 465
Job 7 Operation 1 on Machine 1 : 424 + 78 -> 502
Job 0 Operation 0 on Machine 0 : 465 + 125 -> 590
Job 2 Operation 0 on Machine 1 : 502 + 142 -> 644
Job 5 Operation 0 on Machine 0 : 590 + 184 -> 774
Job 0 Operation 1 on Machine 1 : 644 + 110 -> 754
Job 2 Operation 1 on Machine 0 : 774 + 86 -> 860
Job 5 Operation 1 on Machine 1 : 774 + 37 -> 811
Makespan: 860.0, as it is the maximum end completion time of Operation 1 |
6 | 4 | Optimize schedule for 6 Jobs across 4 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 1 duration 110 mins.
Operation 1 on Machine 3 duration 104 mins.
Operation 2 on Machine 0 duration 229 mins.
Operation 3 on Machine 2 duration 320 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 3 duration 173 mins.
Operation 1 on Machine 2 duration 340 mins.
Operation 2 on Machine 0 duration 235 mins.
Operation 3 on Machine 1 duration 302 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 1 duration 399 mins.
Operation 1 on Machine 3 duration 299 mins.
Operation 2 on Machine 0 duration 104 mins.
Operation 3 on Machine 2 duration 332 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 1 duration 144 mins.
Operation 1 on Machine 3 duration 404 mins.
Operation 2 on Machine 2 duration 320 mins.
Operation 3 on Machine 0 duration 62 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 3 duration 28 mins.
Operation 1 on Machine 1 duration 443 mins.
Operation 2 on Machine 0 duration 80 mins.
Operation 3 on Machine 2 duration 362 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 3 duration 8 mins.
Operation 1 on Machine 1 duration 23 mins.
Operation 2 on Machine 0 duration 353 mins.
Operation 3 on Machine 2 duration 337 mins.
| Optimize schedule for 6 Jobs across 4 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 0 Operation 2 duration 229 mins.
Job 1 Operation 2 duration 235 mins.
Job 2 Operation 2 duration 104 mins.
Job 4 Operation 2 duration 80 mins.
Job 5 Operation 2 duration 353 mins.
Job 3 Operation 3 duration 62 mins.
Machine 1 is used for the following Operations:
Job 0 Operation 0 duration 110 mins.
Job 2 Operation 0 duration 399 mins.
Job 3 Operation 0 duration 144 mins.
Job 4 Operation 1 duration 443 mins.
Job 5 Operation 1 duration 23 mins.
Job 1 Operation 3 duration 302 mins.
Machine 2 is used for the following Operations:
Job 1 Operation 1 duration 340 mins.
Job 3 Operation 2 duration 320 mins.
Job 0 Operation 3 duration 320 mins.
Job 2 Operation 3 duration 332 mins.
Job 4 Operation 3 duration 362 mins.
Job 5 Operation 3 duration 337 mins.
Machine 3 is used for the following Operations:
Job 1 Operation 0 duration 173 mins.
Job 4 Operation 0 duration 28 mins.
Job 5 Operation 0 duration 8 mins.
Job 0 Operation 1 duration 104 mins.
Job 2 Operation 1 duration 299 mins.
Job 3 Operation 1 duration 404 mins.
| Solution:
Job 0 Operation 0 on Machine 1 : 0 + 110 -> 110
Job 1 Operation 0 on Machine 3 : 0 + 173 -> 173
Job 3 Operation 0 on Machine 1 : 110 + 144 -> 254
Job 1 Operation 1 on Machine 2 : 173 + 340 -> 513
Job 0 Operation 1 on Machine 3 : 173 + 104 -> 277
Job 2 Operation 0 on Machine 1 : 254 + 399 -> 653
Job 0 Operation 2 on Machine 0 : 277 + 229 -> 506
Job 4 Operation 0 on Machine 3 : 277 + 28 -> 305
Job 3 Operation 1 on Machine 3 : 305 + 404 -> 709
Job 1 Operation 2 on Machine 0 : 513 + 235 -> 748
Job 0 Operation 3 on Machine 2 : 513 + 320 -> 833
Job 4 Operation 1 on Machine 1 : 653 + 443 -> 1096
Job 2 Operation 1 on Machine 3 : 709 + 299 -> 1008
Job 3 Operation 2 on Machine 2 : 833 + 320 -> 1153
Job 2 Operation 2 on Machine 0 : 1008 + 104 -> 1112
Job 5 Operation 0 on Machine 3 : 1008 + 8 -> 1016
Job 1 Operation 3 on Machine 1 : 1096 + 302 -> 1398
Job 3 Operation 3 on Machine 0 : 1153 + 62 -> 1215
Job 2 Operation 3 on Machine 2 : 1153 + 332 -> 1485
Job 4 Operation 2 on Machine 0 : 1215 + 80 -> 1295
Job 5 Operation 1 on Machine 1 : 1398 + 23 -> 1421
Job 5 Operation 2 on Machine 0 : 1421 + 353 -> 1774
Job 4 Operation 3 on Machine 2 : 1485 + 362 -> 1847
Job 5 Operation 3 on Machine 2 : 1847 + 337 -> 2184
Makespan: 2184.0, as it is the maximum end completion time of Operation 3 |
10 | 8 | Optimize schedule for 10 Jobs across 8 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 6 duration 128 mins.
Operation 1 on Machine 2 duration 242 mins.
Operation 2 on Machine 3 duration 188 mins.
Operation 3 on Machine 0 duration 111 mins.
Operation 4 on Machine 5 duration 277 mins.
Operation 5 on Machine 4 duration 184 mins.
Operation 6 on Machine 7 duration 324 mins.
Operation 7 on Machine 1 duration 27 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 3 duration 344 mins.
Operation 1 on Machine 7 duration 242 mins.
Operation 2 on Machine 1 duration 67 mins.
Operation 3 on Machine 6 duration 338 mins.
Operation 4 on Machine 4 duration 24 mins.
Operation 5 on Machine 2 duration 39 mins.
Operation 6 on Machine 0 duration 190 mins.
Operation 7 on Machine 5 duration 173 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 7 duration 155 mins.
Operation 1 on Machine 5 duration 193 mins.
Operation 2 on Machine 6 duration 343 mins.
Operation 3 on Machine 3 duration 306 mins.
Operation 4 on Machine 4 duration 52 mins.
Operation 5 on Machine 1 duration 81 mins.
Operation 6 on Machine 0 duration 271 mins.
Operation 7 on Machine 2 duration 114 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 4 duration 262 mins.
Operation 1 on Machine 2 duration 254 mins.
Operation 2 on Machine 0 duration 164 mins.
Operation 3 on Machine 3 duration 250 mins.
Operation 4 on Machine 6 duration 270 mins.
Operation 5 on Machine 5 duration 310 mins.
Operation 6 on Machine 1 duration 19 mins.
Operation 7 on Machine 7 duration 117 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 0 duration 224 mins.
Operation 1 on Machine 3 duration 123 mins.
Operation 2 on Machine 4 duration 269 mins.
Operation 3 on Machine 2 duration 168 mins.
Operation 4 on Machine 6 duration 20 mins.
Operation 5 on Machine 7 duration 167 mins.
Operation 6 on Machine 1 duration 348 mins.
Operation 7 on Machine 5 duration 62 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 0 duration 175 mins.
Operation 1 on Machine 2 duration 333 mins.
Operation 2 on Machine 6 duration 147 mins.
Operation 3 on Machine 3 duration 97 mins.
Operation 4 on Machine 4 duration 298 mins.
Operation 5 on Machine 7 duration 73 mins.
Operation 6 on Machine 5 duration 43 mins.
Operation 7 on Machine 1 duration 154 mins.
Job 6 consists of the following Operations:
Operation 0 on Machine 5 duration 161 mins.
Operation 1 on Machine 2 duration 273 mins.
Operation 2 on Machine 4 duration 272 mins.
Operation 3 on Machine 0 duration 218 mins.
Operation 4 on Machine 1 duration 311 mins.
Operation 5 on Machine 7 duration 58 mins.
Operation 6 on Machine 6 duration 310 mins.
Operation 7 on Machine 3 duration 187 mins.
Job 7 consists of the following Operations:
Operation 0 on Machine 4 duration 349 mins.
Operation 1 on Machine 0 duration 36 mins.
Operation 2 on Machine 3 duration 171 mins.
Operation 3 on Machine 5 duration 324 mins.
Operation 4 on Machine 6 duration 152 mins.
Operation 5 on Machine 7 duration 114 mins.
Operation 6 on Machine 1 duration 291 mins.
Operation 7 on Machine 2 duration 42 mins.
Job 8 consists of the following Operations:
Operation 0 on Machine 0 duration 285 mins.
Operation 1 on Machine 7 duration 270 mins.
Operation 2 on Machine 5 duration 13 mins.
Operation 3 on Machine 1 duration 117 mins.
Operation 4 on Machine 4 duration 172 mins.
Operation 5 on Machine 3 duration 63 mins.
Operation 6 on Machine 2 duration 318 mins.
Operation 7 on Machine 6 duration 246 mins.
Job 9 consists of the following Operations:
Operation 0 on Machine 6 duration 227 mins.
Operation 1 on Machine 0 duration 334 mins.
Operation 2 on Machine 2 duration 115 mins.
Operation 3 on Machine 1 duration 215 mins.
Operation 4 on Machine 5 duration 125 mins.
Operation 5 on Machine 3 duration 114 mins.
Operation 6 on Machine 7 duration 246 mins.
Operation 7 on Machine 4 duration 334 mins.
| Optimize schedule for 10 Jobs across 8 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 4 Operation 0 duration 224 mins.
Job 5 Operation 0 duration 175 mins.
Job 8 Operation 0 duration 285 mins.
Job 7 Operation 1 duration 36 mins.
Job 9 Operation 1 duration 334 mins.
Job 3 Operation 2 duration 164 mins.
Job 0 Operation 3 duration 111 mins.
Job 6 Operation 3 duration 218 mins.
Job 1 Operation 6 duration 190 mins.
Job 2 Operation 6 duration 271 mins.
Machine 1 is used for the following Operations:
Job 1 Operation 2 duration 67 mins.
Job 8 Operation 3 duration 117 mins.
Job 9 Operation 3 duration 215 mins.
Job 6 Operation 4 duration 311 mins.
Job 2 Operation 5 duration 81 mins.
Job 3 Operation 6 duration 19 mins.
Job 4 Operation 6 duration 348 mins.
Job 7 Operation 6 duration 291 mins.
Job 0 Operation 7 duration 27 mins.
Job 5 Operation 7 duration 154 mins.
Machine 2 is used for the following Operations:
Job 0 Operation 1 duration 242 mins.
Job 3 Operation 1 duration 254 mins.
Job 5 Operation 1 duration 333 mins.
Job 6 Operation 1 duration 273 mins.
Job 9 Operation 2 duration 115 mins.
Job 4 Operation 3 duration 168 mins.
Job 1 Operation 5 duration 39 mins.
Job 8 Operation 6 duration 318 mins.
Job 2 Operation 7 duration 114 mins.
Job 7 Operation 7 duration 42 mins.
Machine 3 is used for the following Operations:
Job 1 Operation 0 duration 344 mins.
Job 4 Operation 1 duration 123 mins.
Job 0 Operation 2 duration 188 mins.
Job 7 Operation 2 duration 171 mins.
Job 2 Operation 3 duration 306 mins.
Job 3 Operation 3 duration 250 mins.
Job 5 Operation 3 duration 97 mins.
Job 8 Operation 5 duration 63 mins.
Job 9 Operation 5 duration 114 mins.
Job 6 Operation 7 duration 187 mins.
Machine 4 is used for the following Operations:
Job 3 Operation 0 duration 262 mins.
Job 7 Operation 0 duration 349 mins.
Job 4 Operation 2 duration 269 mins.
Job 6 Operation 2 duration 272 mins.
Job 1 Operation 4 duration 24 mins.
Job 2 Operation 4 duration 52 mins.
Job 5 Operation 4 duration 298 mins.
Job 8 Operation 4 duration 172 mins.
Job 0 Operation 5 duration 184 mins.
Job 9 Operation 7 duration 334 mins.
Machine 5 is used for the following Operations:
Job 6 Operation 0 duration 161 mins.
Job 2 Operation 1 duration 193 mins.
Job 8 Operation 2 duration 13 mins.
Job 7 Operation 3 duration 324 mins.
Job 0 Operation 4 duration 277 mins.
Job 9 Operation 4 duration 125 mins.
Job 3 Operation 5 duration 310 mins.
Job 5 Operation 6 duration 43 mins.
Job 1 Operation 7 duration 173 mins.
Job 4 Operation 7 duration 62 mins.
Machine 6 is used for the following Operations:
Job 0 Operation 0 duration 128 mins.
Job 9 Operation 0 duration 227 mins.
Job 2 Operation 2 duration 343 mins.
Job 5 Operation 2 duration 147 mins.
Job 1 Operation 3 duration 338 mins.
Job 3 Operation 4 duration 270 mins.
Job 4 Operation 4 duration 20 mins.
Job 7 Operation 4 duration 152 mins.
Job 6 Operation 6 duration 310 mins.
Job 8 Operation 7 duration 246 mins.
Machine 7 is used for the following Operations:
Job 2 Operation 0 duration 155 mins.
Job 1 Operation 1 duration 242 mins.
Job 8 Operation 1 duration 270 mins.
Job 4 Operation 5 duration 167 mins.
Job 5 Operation 5 duration 73 mins.
Job 6 Operation 5 duration 58 mins.
Job 7 Operation 5 duration 114 mins.
Job 0 Operation 6 duration 324 mins.
Job 9 Operation 6 duration 246 mins.
Job 3 Operation 7 duration 117 mins.
| Solution:
Job 8 Operation 0 on Machine 0 : 0 + 285 -> 285
Job 1 Operation 0 on Machine 3 : 0 + 344 -> 344
Job 7 Operation 0 on Machine 4 : 0 + 349 -> 349
Job 6 Operation 0 on Machine 5 : 0 + 161 -> 161
Job 0 Operation 0 on Machine 6 : 0 + 128 -> 128
Job 2 Operation 0 on Machine 7 : 0 + 155 -> 155
Job 0 Operation 1 on Machine 2 : 128 + 242 -> 370
Job 9 Operation 0 on Machine 6 : 128 + 227 -> 355
Job 2 Operation 1 on Machine 5 : 161 + 193 -> 354
Job 8 Operation 1 on Machine 7 : 285 + 270 -> 555
Job 7 Operation 1 on Machine 0 : 349 + 36 -> 385
Job 3 Operation 0 on Machine 4 : 349 + 262 -> 611
Job 2 Operation 2 on Machine 6 : 355 + 343 -> 698
Job 6 Operation 1 on Machine 2 : 370 + 273 -> 643
Job 9 Operation 1 on Machine 0 : 385 + 334 -> 719
Job 7 Operation 2 on Machine 3 : 385 + 171 -> 556
Job 8 Operation 2 on Machine 5 : 555 + 13 -> 568
Job 1 Operation 1 on Machine 7 : 555 + 242 -> 797
Job 0 Operation 2 on Machine 3 : 556 + 188 -> 744
Job 8 Operation 3 on Machine 1 : 568 + 117 -> 685
Job 7 Operation 3 on Machine 5 : 568 + 324 -> 892
Job 8 Operation 4 on Machine 4 : 685 + 172 -> 857
Job 4 Operation 0 on Machine 0 : 719 + 224 -> 943
Job 9 Operation 2 on Machine 2 : 719 + 115 -> 834
Job 2 Operation 3 on Machine 3 : 744 + 306 -> 1050
Job 1 Operation 2 on Machine 1 : 797 + 67 -> 864
Job 3 Operation 1 on Machine 2 : 834 + 254 -> 1088
Job 6 Operation 2 on Machine 4 : 857 + 272 -> 1129
Job 9 Operation 3 on Machine 1 : 864 + 215 -> 1079
Job 7 Operation 4 on Machine 6 : 892 + 152 -> 1044
Job 5 Operation 0 on Machine 0 : 943 + 175 -> 1118
Job 1 Operation 3 on Machine 6 : 1044 + 338 -> 1382
Job 7 Operation 5 on Machine 7 : 1044 + 114 -> 1158
Job 4 Operation 1 on Machine 3 : 1050 + 123 -> 1173
Job 9 Operation 4 on Machine 5 : 1079 + 125 -> 1204
Job 0 Operation 3 on Machine 0 : 1118 + 111 -> 1229
Job 5 Operation 1 on Machine 2 : 1118 + 333 -> 1451
Job 7 Operation 6 on Machine 1 : 1158 + 291 -> 1449
Job 4 Operation 2 on Machine 4 : 1173 + 269 -> 1442
Job 9 Operation 5 on Machine 3 : 1204 + 114 -> 1318
Job 3 Operation 2 on Machine 0 : 1229 + 164 -> 1393
Job 0 Operation 4 on Machine 5 : 1229 + 277 -> 1506
Job 9 Operation 6 on Machine 7 : 1318 + 246 -> 1564
Job 6 Operation 3 on Machine 0 : 1393 + 218 -> 1611
Job 3 Operation 3 on Machine 3 : 1393 + 250 -> 1643
Job 1 Operation 4 on Machine 4 : 1442 + 24 -> 1466
Job 5 Operation 2 on Machine 6 : 1451 + 147 -> 1598
Job 1 Operation 5 on Machine 2 : 1466 + 39 -> 1505
Job 2 Operation 4 on Machine 4 : 1466 + 52 -> 1518
Job 4 Operation 3 on Machine 2 : 1505 + 168 -> 1673
Job 2 Operation 5 on Machine 1 : 1518 + 81 -> 1599
Job 0 Operation 5 on Machine 4 : 1518 + 184 -> 1702
Job 1 Operation 6 on Machine 0 : 1611 + 190 -> 1801
Job 6 Operation 4 on Machine 1 : 1611 + 311 -> 1922
Job 5 Operation 3 on Machine 3 : 1643 + 97 -> 1740
Job 7 Operation 7 on Machine 2 : 1673 + 42 -> 1715
Job 4 Operation 4 on Machine 6 : 1673 + 20 -> 1693
Job 3 Operation 4 on Machine 6 : 1693 + 270 -> 1963
Job 4 Operation 5 on Machine 7 : 1693 + 167 -> 1860
Job 8 Operation 5 on Machine 3 : 1740 + 63 -> 1803
Job 5 Operation 4 on Machine 4 : 1740 + 298 -> 2038
Job 2 Operation 6 on Machine 0 : 1801 + 271 -> 2072
Job 1 Operation 7 on Machine 5 : 1801 + 173 -> 1974
Job 8 Operation 6 on Machine 2 : 1803 + 318 -> 2121
Job 4 Operation 6 on Machine 1 : 1922 + 348 -> 2270
Job 6 Operation 5 on Machine 7 : 1922 + 58 -> 1980
Job 3 Operation 5 on Machine 5 : 1974 + 310 -> 2284
Job 6 Operation 6 on Machine 6 : 1980 + 310 -> 2290
Job 9 Operation 7 on Machine 4 : 2038 + 334 -> 2372
Job 5 Operation 5 on Machine 7 : 2038 + 73 -> 2111
Job 0 Operation 6 on Machine 7 : 2111 + 324 -> 2435
Job 2 Operation 7 on Machine 2 : 2121 + 114 -> 2235
Job 3 Operation 6 on Machine 1 : 2284 + 19 -> 2303
Job 5 Operation 6 on Machine 5 : 2284 + 43 -> 2327
Job 6 Operation 7 on Machine 3 : 2290 + 187 -> 2477
Job 8 Operation 7 on Machine 6 : 2290 + 246 -> 2536
Job 5 Operation 7 on Machine 1 : 2327 + 154 -> 2481
Job 4 Operation 7 on Machine 5 : 2327 + 62 -> 2389
Job 3 Operation 7 on Machine 7 : 2435 + 117 -> 2552
Job 0 Operation 7 on Machine 1 : 2481 + 27 -> 2508
Makespan: 2552.0, as it is the maximum end completion time of Operation 7 |
4 | 4 | Optimize schedule for 4 Jobs across 4 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 2 duration 15 mins.
Operation 1 on Machine 0 duration 83 mins.
Operation 2 on Machine 1 duration 2 mins.
Operation 3 on Machine 3 duration 84 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 3 duration 48 mins.
Operation 1 on Machine 1 duration 38 mins.
Operation 2 on Machine 2 duration 75 mins.
Operation 3 on Machine 0 duration 40 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 2 duration 77 mins.
Operation 1 on Machine 3 duration 12 mins.
Operation 2 on Machine 1 duration 43 mins.
Operation 3 on Machine 0 duration 94 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 0 duration 47 mins.
Operation 1 on Machine 3 duration 98 mins.
Operation 2 on Machine 2 duration 88 mins.
Operation 3 on Machine 1 duration 28 mins.
| Optimize schedule for 4 Jobs across 4 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 3 Operation 0 duration 47 mins.
Job 0 Operation 1 duration 83 mins.
Job 1 Operation 3 duration 40 mins.
Job 2 Operation 3 duration 94 mins.
Machine 1 is used for the following Operations:
Job 1 Operation 1 duration 38 mins.
Job 0 Operation 2 duration 2 mins.
Job 2 Operation 2 duration 43 mins.
Job 3 Operation 3 duration 28 mins.
Machine 2 is used for the following Operations:
Job 0 Operation 0 duration 15 mins.
Job 2 Operation 0 duration 77 mins.
Job 1 Operation 2 duration 75 mins.
Job 3 Operation 2 duration 88 mins.
Machine 3 is used for the following Operations:
Job 1 Operation 0 duration 48 mins.
Job 2 Operation 1 duration 12 mins.
Job 3 Operation 1 duration 98 mins.
Job 0 Operation 3 duration 84 mins.
| Solution:
Job 3 Operation 0 on Machine 0 : 0 + 47 -> 47
Job 0 Operation 0 on Machine 2 : 0 + 15 -> 15
Job 1 Operation 0 on Machine 3 : 0 + 48 -> 48
Job 2 Operation 0 on Machine 2 : 15 + 77 -> 92
Job 0 Operation 1 on Machine 0 : 47 + 83 -> 130
Job 1 Operation 1 on Machine 1 : 48 + 38 -> 86
Job 3 Operation 1 on Machine 3 : 48 + 98 -> 146
Job 1 Operation 2 on Machine 2 : 92 + 75 -> 167
Job 0 Operation 2 on Machine 1 : 130 + 2 -> 132
Job 2 Operation 1 on Machine 3 : 146 + 12 -> 158
Job 2 Operation 2 on Machine 1 : 158 + 43 -> 201
Job 0 Operation 3 on Machine 3 : 158 + 84 -> 242
Job 1 Operation 3 on Machine 0 : 167 + 40 -> 207
Job 3 Operation 2 on Machine 2 : 167 + 88 -> 255
Job 2 Operation 3 on Machine 0 : 207 + 94 -> 301
Job 3 Operation 3 on Machine 1 : 255 + 28 -> 283
Makespan: 301.0, as it is the maximum end completion time of Operation 3 |
7 | 5 | Optimize schedule for 7 Jobs across 5 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 4 duration 130 mins.
Operation 1 on Machine 3 duration 91 mins.
Operation 2 on Machine 1 duration 4 mins.
Operation 3 on Machine 2 duration 30 mins.
Operation 4 on Machine 0 duration 68 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 2 duration 17 mins.
Operation 1 on Machine 0 duration 100 mins.
Operation 2 on Machine 4 duration 32 mins.
Operation 3 on Machine 3 duration 15 mins.
Operation 4 on Machine 1 duration 115 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 2 duration 57 mins.
Operation 1 on Machine 3 duration 78 mins.
Operation 2 on Machine 0 duration 150 mins.
Operation 3 on Machine 1 duration 14 mins.
Operation 4 on Machine 4 duration 26 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 1 duration 112 mins.
Operation 1 on Machine 0 duration 52 mins.
Operation 2 on Machine 4 duration 110 mins.
Operation 3 on Machine 3 duration 120 mins.
Operation 4 on Machine 2 duration 22 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 4 duration 71 mins.
Operation 1 on Machine 3 duration 132 mins.
Operation 2 on Machine 1 duration 4 mins.
Operation 3 on Machine 0 duration 40 mins.
Operation 4 on Machine 2 duration 110 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 3 duration 96 mins.
Operation 1 on Machine 2 duration 105 mins.
Operation 2 on Machine 4 duration 144 mins.
Operation 3 on Machine 0 duration 51 mins.
Operation 4 on Machine 1 duration 48 mins.
Job 6 consists of the following Operations:
Operation 0 on Machine 1 duration 12 mins.
Operation 1 on Machine 0 duration 35 mins.
Operation 2 on Machine 4 duration 141 mins.
Operation 3 on Machine 2 duration 70 mins.
Operation 4 on Machine 3 duration 95 mins.
| Optimize schedule for 7 Jobs across 5 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 1 Operation 1 duration 100 mins.
Job 3 Operation 1 duration 52 mins.
Job 6 Operation 1 duration 35 mins.
Job 2 Operation 2 duration 150 mins.
Job 4 Operation 3 duration 40 mins.
Job 5 Operation 3 duration 51 mins.
Job 0 Operation 4 duration 68 mins.
Machine 1 is used for the following Operations:
Job 3 Operation 0 duration 112 mins.
Job 6 Operation 0 duration 12 mins.
Job 0 Operation 2 duration 4 mins.
Job 4 Operation 2 duration 4 mins.
Job 2 Operation 3 duration 14 mins.
Job 1 Operation 4 duration 115 mins.
Job 5 Operation 4 duration 48 mins.
Machine 2 is used for the following Operations:
Job 1 Operation 0 duration 17 mins.
Job 2 Operation 0 duration 57 mins.
Job 5 Operation 1 duration 105 mins.
Job 0 Operation 3 duration 30 mins.
Job 6 Operation 3 duration 70 mins.
Job 3 Operation 4 duration 22 mins.
Job 4 Operation 4 duration 110 mins.
Machine 3 is used for the following Operations:
Job 5 Operation 0 duration 96 mins.
Job 0 Operation 1 duration 91 mins.
Job 2 Operation 1 duration 78 mins.
Job 4 Operation 1 duration 132 mins.
Job 1 Operation 3 duration 15 mins.
Job 3 Operation 3 duration 120 mins.
Job 6 Operation 4 duration 95 mins.
Machine 4 is used for the following Operations:
Job 0 Operation 0 duration 130 mins.
Job 4 Operation 0 duration 71 mins.
Job 1 Operation 2 duration 32 mins.
Job 3 Operation 2 duration 110 mins.
Job 5 Operation 2 duration 144 mins.
Job 6 Operation 2 duration 141 mins.
Job 2 Operation 4 duration 26 mins.
| Solution:
Job 6 Operation 0 on Machine 1 : 0 + 12 -> 12
Job 1 Operation 0 on Machine 2 : 0 + 17 -> 17
Job 5 Operation 0 on Machine 3 : 0 + 96 -> 96
Job 0 Operation 0 on Machine 4 : 0 + 130 -> 130
Job 3 Operation 0 on Machine 1 : 12 + 112 -> 124
Job 1 Operation 1 on Machine 0 : 17 + 100 -> 117
Job 2 Operation 0 on Machine 2 : 17 + 57 -> 74
Job 5 Operation 1 on Machine 2 : 96 + 105 -> 201
Job 6 Operation 1 on Machine 0 : 117 + 35 -> 152
Job 0 Operation 1 on Machine 3 : 130 + 91 -> 221
Job 1 Operation 2 on Machine 4 : 130 + 32 -> 162
Job 3 Operation 1 on Machine 0 : 152 + 52 -> 204
Job 4 Operation 0 on Machine 4 : 162 + 71 -> 233
Job 0 Operation 2 on Machine 1 : 221 + 4 -> 225
Job 1 Operation 3 on Machine 3 : 221 + 15 -> 236
Job 0 Operation 3 on Machine 2 : 225 + 30 -> 255
Job 3 Operation 2 on Machine 4 : 233 + 110 -> 343
Job 1 Operation 4 on Machine 1 : 236 + 115 -> 351
Job 4 Operation 1 on Machine 3 : 236 + 132 -> 368
Job 0 Operation 4 on Machine 0 : 255 + 68 -> 323
Job 6 Operation 2 on Machine 4 : 343 + 141 -> 484
Job 4 Operation 2 on Machine 1 : 368 + 4 -> 372
Job 2 Operation 1 on Machine 3 : 368 + 78 -> 446
Job 4 Operation 3 on Machine 0 : 372 + 40 -> 412
Job 4 Operation 4 on Machine 2 : 412 + 110 -> 522
Job 2 Operation 2 on Machine 0 : 446 + 150 -> 596
Job 3 Operation 3 on Machine 3 : 446 + 120 -> 566
Job 5 Operation 2 on Machine 4 : 484 + 144 -> 628
Job 6 Operation 3 on Machine 2 : 522 + 70 -> 592
Job 3 Operation 4 on Machine 2 : 592 + 22 -> 614
Job 6 Operation 4 on Machine 3 : 592 + 95 -> 687
Job 2 Operation 3 on Machine 1 : 596 + 14 -> 610
Job 5 Operation 3 on Machine 0 : 628 + 51 -> 679
Job 2 Operation 4 on Machine 4 : 628 + 26 -> 654
Job 5 Operation 4 on Machine 1 : 679 + 48 -> 727
Makespan: 727.0, as it is the maximum end completion time of Operation 4 |
7 | 4 | Optimize schedule for 7 Jobs across 4 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 2 duration 21 mins.
Operation 1 on Machine 1 duration 18 mins.
Operation 2 on Machine 0 duration 4 mins.
Operation 3 on Machine 3 duration 7 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 1 duration 6 mins.
Operation 1 on Machine 2 duration 29 mins.
Operation 2 on Machine 3 duration 45 mins.
Operation 3 on Machine 0 duration 27 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 2 duration 46 mins.
Operation 1 on Machine 1 duration 25 mins.
Operation 2 on Machine 3 duration 35 mins.
Operation 3 on Machine 0 duration 12 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 2 duration 27 mins.
Operation 1 on Machine 1 duration 29 mins.
Operation 2 on Machine 3 duration 15 mins.
Operation 3 on Machine 0 duration 24 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 0 duration 27 mins.
Operation 1 on Machine 3 duration 17 mins.
Operation 2 on Machine 2 duration 23 mins.
Operation 3 on Machine 1 duration 9 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 2 duration 24 mins.
Operation 1 on Machine 1 duration 25 mins.
Operation 2 on Machine 0 duration 44 mins.
Operation 3 on Machine 3 duration 3 mins.
Job 6 consists of the following Operations:
Operation 0 on Machine 0 duration 6 mins.
Operation 1 on Machine 2 duration 38 mins.
Operation 2 on Machine 3 duration 12 mins.
Operation 3 on Machine 1 duration 33 mins.
| Optimize schedule for 7 Jobs across 4 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 4 Operation 0 duration 27 mins.
Job 6 Operation 0 duration 6 mins.
Job 0 Operation 2 duration 4 mins.
Job 5 Operation 2 duration 44 mins.
Job 1 Operation 3 duration 27 mins.
Job 2 Operation 3 duration 12 mins.
Job 3 Operation 3 duration 24 mins.
Machine 1 is used for the following Operations:
Job 1 Operation 0 duration 6 mins.
Job 0 Operation 1 duration 18 mins.
Job 2 Operation 1 duration 25 mins.
Job 3 Operation 1 duration 29 mins.
Job 5 Operation 1 duration 25 mins.
Job 4 Operation 3 duration 9 mins.
Job 6 Operation 3 duration 33 mins.
Machine 2 is used for the following Operations:
Job 0 Operation 0 duration 21 mins.
Job 2 Operation 0 duration 46 mins.
Job 3 Operation 0 duration 27 mins.
Job 5 Operation 0 duration 24 mins.
Job 1 Operation 1 duration 29 mins.
Job 6 Operation 1 duration 38 mins.
Job 4 Operation 2 duration 23 mins.
Machine 3 is used for the following Operations:
Job 4 Operation 1 duration 17 mins.
Job 1 Operation 2 duration 45 mins.
Job 2 Operation 2 duration 35 mins.
Job 3 Operation 2 duration 15 mins.
Job 6 Operation 2 duration 12 mins.
Job 0 Operation 3 duration 7 mins.
Job 5 Operation 3 duration 3 mins.
| Solution:
Job 4 Operation 0 on Machine 0 : 0 + 27 -> 27
Job 1 Operation 0 on Machine 1 : 0 + 6 -> 6
Job 3 Operation 0 on Machine 2 : 0 + 27 -> 27
Job 6 Operation 0 on Machine 0 : 27 + 6 -> 33
Job 3 Operation 1 on Machine 1 : 27 + 29 -> 56
Job 1 Operation 1 on Machine 2 : 27 + 29 -> 56
Job 4 Operation 1 on Machine 3 : 27 + 17 -> 44
Job 5 Operation 0 on Machine 2 : 56 + 24 -> 80
Job 1 Operation 2 on Machine 3 : 56 + 45 -> 101
Job 5 Operation 1 on Machine 1 : 80 + 25 -> 105
Job 6 Operation 1 on Machine 2 : 80 + 38 -> 118
Job 1 Operation 3 on Machine 0 : 101 + 27 -> 128
Job 3 Operation 2 on Machine 3 : 101 + 15 -> 116
Job 2 Operation 0 on Machine 2 : 118 + 46 -> 164
Job 6 Operation 2 on Machine 3 : 118 + 12 -> 130
Job 5 Operation 2 on Machine 0 : 128 + 44 -> 172
Job 6 Operation 3 on Machine 1 : 130 + 33 -> 163
Job 2 Operation 1 on Machine 1 : 164 + 25 -> 189
Job 0 Operation 0 on Machine 2 : 164 + 21 -> 185
Job 3 Operation 3 on Machine 0 : 172 + 24 -> 196
Job 5 Operation 3 on Machine 3 : 172 + 3 -> 175
Job 4 Operation 2 on Machine 2 : 185 + 23 -> 208
Job 0 Operation 1 on Machine 1 : 189 + 18 -> 207
Job 2 Operation 2 on Machine 3 : 189 + 35 -> 224
Job 0 Operation 2 on Machine 0 : 207 + 4 -> 211
Job 4 Operation 3 on Machine 1 : 208 + 9 -> 217
Job 2 Operation 3 on Machine 0 : 224 + 12 -> 236
Job 0 Operation 3 on Machine 3 : 224 + 7 -> 231
Makespan: 236.0, as it is the maximum end completion time of Operation 3 |
9 | 9 | Optimize schedule for 9 Jobs across 9 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 0 duration 27 mins.
Operation 1 on Machine 4 duration 220 mins.
Operation 2 on Machine 3 duration 240 mins.
Operation 3 on Machine 2 duration 212 mins.
Operation 4 on Machine 8 duration 77 mins.
Operation 5 on Machine 6 duration 268 mins.
Operation 6 on Machine 5 duration 62 mins.
Operation 7 on Machine 7 duration 231 mins.
Operation 8 on Machine 1 duration 204 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 7 duration 194 mins.
Operation 1 on Machine 3 duration 155 mins.
Operation 2 on Machine 2 duration 123 mins.
Operation 3 on Machine 6 duration 225 mins.
Operation 4 on Machine 4 duration 157 mins.
Operation 5 on Machine 1 duration 265 mins.
Operation 6 on Machine 8 duration 271 mins.
Operation 7 on Machine 0 duration 228 mins.
Operation 8 on Machine 5 duration 116 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 6 duration 249 mins.
Operation 1 on Machine 7 duration 171 mins.
Operation 2 on Machine 8 duration 135 mins.
Operation 3 on Machine 5 duration 20 mins.
Operation 4 on Machine 0 duration 5 mins.
Operation 5 on Machine 4 duration 102 mins.
Operation 6 on Machine 3 duration 188 mins.
Operation 7 on Machine 1 duration 241 mins.
Operation 8 on Machine 2 duration 41 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 0 duration 156 mins.
Operation 1 on Machine 5 duration 60 mins.
Operation 2 on Machine 3 duration 182 mins.
Operation 3 on Machine 4 duration 83 mins.
Operation 4 on Machine 8 duration 103 mins.
Operation 5 on Machine 1 duration 82 mins.
Operation 6 on Machine 2 duration 198 mins.
Operation 7 on Machine 7 duration 68 mins.
Operation 8 on Machine 6 duration 100 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 0 duration 42 mins.
Operation 1 on Machine 3 duration 258 mins.
Operation 2 on Machine 8 duration 57 mins.
Operation 3 on Machine 5 duration 269 mins.
Operation 4 on Machine 1 duration 26 mins.
Operation 5 on Machine 6 duration 53 mins.
Operation 6 on Machine 7 duration 197 mins.
Operation 7 on Machine 4 duration 205 mins.
Operation 8 on Machine 2 duration 31 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 3 duration 122 mins.
Operation 1 on Machine 5 duration 64 mins.
Operation 2 on Machine 8 duration 136 mins.
Operation 3 on Machine 1 duration 266 mins.
Operation 4 on Machine 0 duration 74 mins.
Operation 5 on Machine 4 duration 25 mins.
Operation 6 on Machine 7 duration 83 mins.
Operation 7 on Machine 6 duration 33 mins.
Operation 8 on Machine 2 duration 9 mins.
Job 6 consists of the following Operations:
Operation 0 on Machine 1 duration 226 mins.
Operation 1 on Machine 6 duration 155 mins.
Operation 2 on Machine 4 duration 238 mins.
Operation 3 on Machine 0 duration 88 mins.
Operation 4 on Machine 8 duration 99 mins.
Operation 5 on Machine 3 duration 226 mins.
Operation 6 on Machine 5 duration 93 mins.
Operation 7 on Machine 7 duration 103 mins.
Operation 8 on Machine 2 duration 47 mins.
Job 7 consists of the following Operations:
Operation 0 on Machine 8 duration 61 mins.
Operation 1 on Machine 4 duration 215 mins.
Operation 2 on Machine 0 duration 162 mins.
Operation 3 on Machine 1 duration 115 mins.
Operation 4 on Machine 2 duration 255 mins.
Operation 5 on Machine 7 duration 213 mins.
Operation 6 on Machine 5 duration 43 mins.
Operation 7 on Machine 3 duration 143 mins.
Operation 8 on Machine 6 duration 33 mins.
Job 8 consists of the following Operations:
Operation 0 on Machine 4 duration 214 mins.
Operation 1 on Machine 1 duration 102 mins.
Operation 2 on Machine 2 duration 271 mins.
Operation 3 on Machine 7 duration 97 mins.
Operation 4 on Machine 6 duration 67 mins.
Operation 5 on Machine 0 duration 197 mins.
Operation 6 on Machine 8 duration 157 mins.
Operation 7 on Machine 3 duration 256 mins.
Operation 8 on Machine 5 duration 268 mins.
| Optimize schedule for 9 Jobs across 9 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 0 Operation 0 duration 27 mins.
Job 3 Operation 0 duration 156 mins.
Job 4 Operation 0 duration 42 mins.
Job 7 Operation 2 duration 162 mins.
Job 6 Operation 3 duration 88 mins.
Job 2 Operation 4 duration 5 mins.
Job 5 Operation 4 duration 74 mins.
Job 8 Operation 5 duration 197 mins.
Job 1 Operation 7 duration 228 mins.
Machine 1 is used for the following Operations:
Job 6 Operation 0 duration 226 mins.
Job 8 Operation 1 duration 102 mins.
Job 5 Operation 3 duration 266 mins.
Job 7 Operation 3 duration 115 mins.
Job 4 Operation 4 duration 26 mins.
Job 1 Operation 5 duration 265 mins.
Job 3 Operation 5 duration 82 mins.
Job 2 Operation 7 duration 241 mins.
Job 0 Operation 8 duration 204 mins.
Machine 2 is used for the following Operations:
Job 1 Operation 2 duration 123 mins.
Job 8 Operation 2 duration 271 mins.
Job 0 Operation 3 duration 212 mins.
Job 7 Operation 4 duration 255 mins.
Job 3 Operation 6 duration 198 mins.
Job 2 Operation 8 duration 41 mins.
Job 4 Operation 8 duration 31 mins.
Job 5 Operation 8 duration 9 mins.
Job 6 Operation 8 duration 47 mins.
Machine 3 is used for the following Operations:
Job 5 Operation 0 duration 122 mins.
Job 1 Operation 1 duration 155 mins.
Job 4 Operation 1 duration 258 mins.
Job 0 Operation 2 duration 240 mins.
Job 3 Operation 2 duration 182 mins.
Job 6 Operation 5 duration 226 mins.
Job 2 Operation 6 duration 188 mins.
Job 7 Operation 7 duration 143 mins.
Job 8 Operation 7 duration 256 mins.
Machine 4 is used for the following Operations:
Job 8 Operation 0 duration 214 mins.
Job 0 Operation 1 duration 220 mins.
Job 7 Operation 1 duration 215 mins.
Job 6 Operation 2 duration 238 mins.
Job 3 Operation 3 duration 83 mins.
Job 1 Operation 4 duration 157 mins.
Job 2 Operation 5 duration 102 mins.
Job 5 Operation 5 duration 25 mins.
Job 4 Operation 7 duration 205 mins.
Machine 5 is used for the following Operations:
Job 3 Operation 1 duration 60 mins.
Job 5 Operation 1 duration 64 mins.
Job 2 Operation 3 duration 20 mins.
Job 4 Operation 3 duration 269 mins.
Job 0 Operation 6 duration 62 mins.
Job 6 Operation 6 duration 93 mins.
Job 7 Operation 6 duration 43 mins.
Job 1 Operation 8 duration 116 mins.
Job 8 Operation 8 duration 268 mins.
Machine 6 is used for the following Operations:
Job 2 Operation 0 duration 249 mins.
Job 6 Operation 1 duration 155 mins.
Job 1 Operation 3 duration 225 mins.
Job 8 Operation 4 duration 67 mins.
Job 0 Operation 5 duration 268 mins.
Job 4 Operation 5 duration 53 mins.
Job 5 Operation 7 duration 33 mins.
Job 3 Operation 8 duration 100 mins.
Job 7 Operation 8 duration 33 mins.
Machine 7 is used for the following Operations:
Job 1 Operation 0 duration 194 mins.
Job 2 Operation 1 duration 171 mins.
Job 8 Operation 3 duration 97 mins.
Job 7 Operation 5 duration 213 mins.
Job 4 Operation 6 duration 197 mins.
Job 5 Operation 6 duration 83 mins.
Job 0 Operation 7 duration 231 mins.
Job 3 Operation 7 duration 68 mins.
Job 6 Operation 7 duration 103 mins.
Machine 8 is used for the following Operations:
Job 7 Operation 0 duration 61 mins.
Job 2 Operation 2 duration 135 mins.
Job 4 Operation 2 duration 57 mins.
Job 5 Operation 2 duration 136 mins.
Job 0 Operation 4 duration 77 mins.
Job 3 Operation 4 duration 103 mins.
Job 6 Operation 4 duration 99 mins.
Job 1 Operation 6 duration 271 mins.
Job 8 Operation 6 duration 157 mins.
| Solution:
Job 0 Operation 0 on Machine 0 : 0 + 27 -> 27
Job 6 Operation 0 on Machine 1 : 0 + 226 -> 226
Job 5 Operation 0 on Machine 3 : 0 + 122 -> 122
Job 8 Operation 0 on Machine 4 : 0 + 214 -> 214
Job 2 Operation 0 on Machine 6 : 0 + 249 -> 249
Job 1 Operation 0 on Machine 7 : 0 + 194 -> 194
Job 7 Operation 0 on Machine 8 : 0 + 61 -> 61
Job 4 Operation 0 on Machine 0 : 27 + 42 -> 69
Job 3 Operation 0 on Machine 0 : 69 + 156 -> 225
Job 4 Operation 1 on Machine 3 : 122 + 258 -> 380
Job 5 Operation 1 on Machine 5 : 122 + 64 -> 186
Job 5 Operation 2 on Machine 8 : 186 + 136 -> 322
Job 0 Operation 1 on Machine 4 : 214 + 220 -> 434
Job 3 Operation 1 on Machine 5 : 225 + 60 -> 285
Job 8 Operation 1 on Machine 1 : 226 + 102 -> 328
Job 6 Operation 1 on Machine 6 : 249 + 155 -> 404
Job 2 Operation 1 on Machine 7 : 249 + 171 -> 420
Job 5 Operation 3 on Machine 1 : 328 + 266 -> 594
Job 8 Operation 2 on Machine 2 : 328 + 271 -> 599
Job 1 Operation 1 on Machine 3 : 380 + 155 -> 535
Job 2 Operation 2 on Machine 8 : 420 + 135 -> 555
Job 7 Operation 1 on Machine 4 : 434 + 215 -> 649
Job 0 Operation 2 on Machine 3 : 535 + 240 -> 775
Job 2 Operation 3 on Machine 5 : 555 + 20 -> 575
Job 4 Operation 2 on Machine 8 : 555 + 57 -> 612
Job 2 Operation 4 on Machine 0 : 575 + 5 -> 580
Job 5 Operation 4 on Machine 0 : 594 + 74 -> 668
Job 1 Operation 2 on Machine 2 : 599 + 123 -> 722
Job 8 Operation 3 on Machine 7 : 599 + 97 -> 696
Job 4 Operation 3 on Machine 5 : 612 + 269 -> 881
Job 2 Operation 5 on Machine 4 : 649 + 102 -> 751
Job 7 Operation 2 on Machine 0 : 668 + 162 -> 830
Job 8 Operation 4 on Machine 6 : 696 + 67 -> 763
Job 6 Operation 2 on Machine 4 : 751 + 238 -> 989
Job 1 Operation 3 on Machine 6 : 763 + 225 -> 988
Job 0 Operation 3 on Machine 2 : 775 + 212 -> 987
Job 3 Operation 2 on Machine 3 : 775 + 182 -> 957
Job 8 Operation 5 on Machine 0 : 830 + 197 -> 1027
Job 7 Operation 3 on Machine 1 : 830 + 115 -> 945
Job 4 Operation 4 on Machine 1 : 945 + 26 -> 971
Job 2 Operation 6 on Machine 3 : 957 + 188 -> 1145
Job 7 Operation 4 on Machine 2 : 987 + 255 -> 1242
Job 0 Operation 4 on Machine 8 : 987 + 77 -> 1064
Job 4 Operation 5 on Machine 6 : 988 + 53 -> 1041
Job 1 Operation 4 on Machine 4 : 989 + 157 -> 1146
Job 6 Operation 3 on Machine 0 : 1027 + 88 -> 1115
Job 4 Operation 6 on Machine 7 : 1041 + 197 -> 1238
Job 0 Operation 5 on Machine 6 : 1064 + 268 -> 1332
Job 8 Operation 6 on Machine 8 : 1064 + 157 -> 1221
Job 1 Operation 5 on Machine 1 : 1146 + 265 -> 1411
Job 5 Operation 5 on Machine 4 : 1146 + 25 -> 1171
Job 3 Operation 3 on Machine 4 : 1171 + 83 -> 1254
Job 8 Operation 7 on Machine 3 : 1221 + 256 -> 1477
Job 6 Operation 4 on Machine 8 : 1221 + 99 -> 1320
Job 7 Operation 5 on Machine 7 : 1242 + 213 -> 1455
Job 4 Operation 7 on Machine 4 : 1254 + 205 -> 1459
Job 3 Operation 4 on Machine 8 : 1320 + 103 -> 1423
Job 0 Operation 6 on Machine 5 : 1332 + 62 -> 1394
Job 3 Operation 5 on Machine 1 : 1423 + 82 -> 1505
Job 1 Operation 6 on Machine 8 : 1423 + 271 -> 1694
Job 7 Operation 6 on Machine 5 : 1455 + 43 -> 1498
Job 5 Operation 6 on Machine 7 : 1455 + 83 -> 1538
Job 6 Operation 5 on Machine 3 : 1477 + 226 -> 1703
Job 8 Operation 8 on Machine 5 : 1498 + 268 -> 1766
Job 2 Operation 7 on Machine 1 : 1505 + 241 -> 1746
Job 3 Operation 6 on Machine 2 : 1505 + 198 -> 1703
Job 5 Operation 7 on Machine 6 : 1538 + 33 -> 1571
Job 0 Operation 7 on Machine 7 : 1538 + 231 -> 1769
Job 1 Operation 7 on Machine 0 : 1694 + 228 -> 1922
Job 5 Operation 8 on Machine 2 : 1703 + 9 -> 1712
Job 7 Operation 7 on Machine 3 : 1703 + 143 -> 1846
Job 4 Operation 8 on Machine 2 : 1712 + 31 -> 1743
Job 2 Operation 8 on Machine 2 : 1746 + 41 -> 1787
Job 6 Operation 6 on Machine 5 : 1766 + 93 -> 1859
Job 0 Operation 8 on Machine 1 : 1769 + 204 -> 1973
Job 3 Operation 7 on Machine 7 : 1769 + 68 -> 1837
Job 3 Operation 8 on Machine 6 : 1837 + 100 -> 1937
Job 6 Operation 7 on Machine 7 : 1859 + 103 -> 1962
Job 1 Operation 8 on Machine 5 : 1922 + 116 -> 2038
Job 7 Operation 8 on Machine 6 : 1937 + 33 -> 1970
Job 6 Operation 8 on Machine 2 : 1962 + 47 -> 2009
Makespan: 2038.0, as it is the maximum end completion time of Operation 8 |
5 | 4 | Optimize schedule for 5 Jobs across 4 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 1 duration 197 mins.
Operation 1 on Machine 0 duration 395 mins.
Operation 2 on Machine 3 duration 411 mins.
Operation 3 on Machine 2 duration 386 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 2 duration 31 mins.
Operation 1 on Machine 1 duration 363 mins.
Operation 2 on Machine 0 duration 200 mins.
Operation 3 on Machine 3 duration 356 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 0 duration 55 mins.
Operation 1 on Machine 2 duration 15 mins.
Operation 2 on Machine 1 duration 184 mins.
Operation 3 on Machine 3 duration 161 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 2 duration 287 mins.
Operation 1 on Machine 3 duration 6 mins.
Operation 2 on Machine 0 duration 187 mins.
Operation 3 on Machine 1 duration 246 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 0 duration 321 mins.
Operation 1 on Machine 1 duration 406 mins.
Operation 2 on Machine 3 duration 219 mins.
Operation 3 on Machine 2 duration 228 mins.
| Optimize schedule for 5 Jobs across 4 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 2 Operation 0 duration 55 mins.
Job 4 Operation 0 duration 321 mins.
Job 0 Operation 1 duration 395 mins.
Job 1 Operation 2 duration 200 mins.
Job 3 Operation 2 duration 187 mins.
Machine 1 is used for the following Operations:
Job 0 Operation 0 duration 197 mins.
Job 1 Operation 1 duration 363 mins.
Job 4 Operation 1 duration 406 mins.
Job 2 Operation 2 duration 184 mins.
Job 3 Operation 3 duration 246 mins.
Machine 2 is used for the following Operations:
Job 1 Operation 0 duration 31 mins.
Job 3 Operation 0 duration 287 mins.
Job 2 Operation 1 duration 15 mins.
Job 0 Operation 3 duration 386 mins.
Job 4 Operation 3 duration 228 mins.
Machine 3 is used for the following Operations:
Job 3 Operation 1 duration 6 mins.
Job 0 Operation 2 duration 411 mins.
Job 4 Operation 2 duration 219 mins.
Job 1 Operation 3 duration 356 mins.
Job 2 Operation 3 duration 161 mins.
| Solution:
Job 2 Operation 0 on Machine 0 : 0 + 55 -> 55
Job 0 Operation 0 on Machine 1 : 0 + 197 -> 197
Job 1 Operation 0 on Machine 2 : 0 + 31 -> 31
Job 4 Operation 0 on Machine 0 : 55 + 321 -> 376
Job 2 Operation 1 on Machine 2 : 55 + 15 -> 70
Job 3 Operation 0 on Machine 2 : 70 + 287 -> 357
Job 2 Operation 2 on Machine 1 : 197 + 184 -> 381
Job 3 Operation 1 on Machine 3 : 357 + 6 -> 363
Job 0 Operation 1 on Machine 0 : 376 + 395 -> 771
Job 1 Operation 1 on Machine 1 : 381 + 363 -> 744
Job 2 Operation 3 on Machine 3 : 381 + 161 -> 542
Job 4 Operation 1 on Machine 1 : 744 + 406 -> 1150
Job 3 Operation 2 on Machine 0 : 771 + 187 -> 958
Job 0 Operation 2 on Machine 3 : 771 + 411 -> 1182
Job 1 Operation 2 on Machine 0 : 958 + 200 -> 1158
Job 3 Operation 3 on Machine 1 : 1150 + 246 -> 1396
Job 0 Operation 3 on Machine 2 : 1182 + 386 -> 1568
Job 4 Operation 2 on Machine 3 : 1182 + 219 -> 1401
Job 1 Operation 3 on Machine 3 : 1401 + 356 -> 1757
Job 4 Operation 3 on Machine 2 : 1568 + 228 -> 1796
Makespan: 1796.0, as it is the maximum end completion time of Operation 3 |
10 | 7 | Optimize schedule for 10 Jobs across 7 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 1 duration 189 mins.
Operation 1 on Machine 2 duration 32 mins.
Operation 2 on Machine 6 duration 103 mins.
Operation 3 on Machine 3 duration 283 mins.
Operation 4 on Machine 4 duration 92 mins.
Operation 5 on Machine 5 duration 214 mins.
Operation 6 on Machine 0 duration 127 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 0 duration 228 mins.
Operation 1 on Machine 1 duration 193 mins.
Operation 2 on Machine 3 duration 90 mins.
Operation 3 on Machine 2 duration 143 mins.
Operation 4 on Machine 6 duration 35 mins.
Operation 5 on Machine 4 duration 39 mins.
Operation 6 on Machine 5 duration 251 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 0 duration 255 mins.
Operation 1 on Machine 4 duration 215 mins.
Operation 2 on Machine 3 duration 289 mins.
Operation 3 on Machine 2 duration 88 mins.
Operation 4 on Machine 1 duration 140 mins.
Operation 5 on Machine 6 duration 68 mins.
Operation 6 on Machine 5 duration 278 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 6 duration 125 mins.
Operation 1 on Machine 0 duration 268 mins.
Operation 2 on Machine 3 duration 163 mins.
Operation 3 on Machine 4 duration 88 mins.
Operation 4 on Machine 1 duration 148 mins.
Operation 5 on Machine 2 duration 31 mins.
Operation 6 on Machine 5 duration 82 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 6 duration 104 mins.
Operation 1 on Machine 5 duration 51 mins.
Operation 2 on Machine 4 duration 193 mins.
Operation 3 on Machine 0 duration 155 mins.
Operation 4 on Machine 1 duration 272 mins.
Operation 5 on Machine 2 duration 252 mins.
Operation 6 on Machine 3 duration 292 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 0 duration 96 mins.
Operation 1 on Machine 1 duration 89 mins.
Operation 2 on Machine 3 duration 57 mins.
Operation 3 on Machine 2 duration 73 mins.
Operation 4 on Machine 4 duration 113 mins.
Operation 5 on Machine 6 duration 141 mins.
Operation 6 on Machine 5 duration 263 mins.
Job 6 consists of the following Operations:
Operation 0 on Machine 1 duration 59 mins.
Operation 1 on Machine 3 duration 239 mins.
Operation 2 on Machine 4 duration 229 mins.
Operation 3 on Machine 0 duration 172 mins.
Operation 4 on Machine 6 duration 165 mins.
Operation 5 on Machine 5 duration 85 mins.
Operation 6 on Machine 2 duration 21 mins.
Job 7 consists of the following Operations:
Operation 0 on Machine 0 duration 98 mins.
Operation 1 on Machine 5 duration 44 mins.
Operation 2 on Machine 1 duration 102 mins.
Operation 3 on Machine 2 duration 61 mins.
Operation 4 on Machine 4 duration 61 mins.
Operation 5 on Machine 3 duration 16 mins.
Operation 6 on Machine 6 duration 110 mins.
Job 8 consists of the following Operations:
Operation 0 on Machine 0 duration 254 mins.
Operation 1 on Machine 3 duration 5 mins.
Operation 2 on Machine 2 duration 236 mins.
Operation 3 on Machine 5 duration 193 mins.
Operation 4 on Machine 4 duration 82 mins.
Operation 5 on Machine 6 duration 193 mins.
Operation 6 on Machine 1 duration 279 mins.
Job 9 consists of the following Operations:
Operation 0 on Machine 1 duration 47 mins.
Operation 1 on Machine 6 duration 6 mins.
Operation 2 on Machine 2 duration 51 mins.
Operation 3 on Machine 5 duration 11 mins.
Operation 4 on Machine 4 duration 158 mins.
Operation 5 on Machine 0 duration 257 mins.
Operation 6 on Machine 3 duration 227 mins.
| Optimize schedule for 10 Jobs across 7 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 1 Operation 0 duration 228 mins.
Job 2 Operation 0 duration 255 mins.
Job 5 Operation 0 duration 96 mins.
Job 7 Operation 0 duration 98 mins.
Job 8 Operation 0 duration 254 mins.
Job 3 Operation 1 duration 268 mins.
Job 4 Operation 3 duration 155 mins.
Job 6 Operation 3 duration 172 mins.
Job 9 Operation 5 duration 257 mins.
Job 0 Operation 6 duration 127 mins.
Machine 1 is used for the following Operations:
Job 0 Operation 0 duration 189 mins.
Job 6 Operation 0 duration 59 mins.
Job 9 Operation 0 duration 47 mins.
Job 1 Operation 1 duration 193 mins.
Job 5 Operation 1 duration 89 mins.
Job 7 Operation 2 duration 102 mins.
Job 2 Operation 4 duration 140 mins.
Job 3 Operation 4 duration 148 mins.
Job 4 Operation 4 duration 272 mins.
Job 8 Operation 6 duration 279 mins.
Machine 2 is used for the following Operations:
Job 0 Operation 1 duration 32 mins.
Job 8 Operation 2 duration 236 mins.
Job 9 Operation 2 duration 51 mins.
Job 1 Operation 3 duration 143 mins.
Job 2 Operation 3 duration 88 mins.
Job 5 Operation 3 duration 73 mins.
Job 7 Operation 3 duration 61 mins.
Job 3 Operation 5 duration 31 mins.
Job 4 Operation 5 duration 252 mins.
Job 6 Operation 6 duration 21 mins.
Machine 3 is used for the following Operations:
Job 6 Operation 1 duration 239 mins.
Job 8 Operation 1 duration 5 mins.
Job 1 Operation 2 duration 90 mins.
Job 2 Operation 2 duration 289 mins.
Job 3 Operation 2 duration 163 mins.
Job 5 Operation 2 duration 57 mins.
Job 0 Operation 3 duration 283 mins.
Job 7 Operation 5 duration 16 mins.
Job 4 Operation 6 duration 292 mins.
Job 9 Operation 6 duration 227 mins.
Machine 4 is used for the following Operations:
Job 2 Operation 1 duration 215 mins.
Job 4 Operation 2 duration 193 mins.
Job 6 Operation 2 duration 229 mins.
Job 3 Operation 3 duration 88 mins.
Job 0 Operation 4 duration 92 mins.
Job 5 Operation 4 duration 113 mins.
Job 7 Operation 4 duration 61 mins.
Job 8 Operation 4 duration 82 mins.
Job 9 Operation 4 duration 158 mins.
Job 1 Operation 5 duration 39 mins.
Machine 5 is used for the following Operations:
Job 4 Operation 1 duration 51 mins.
Job 7 Operation 1 duration 44 mins.
Job 8 Operation 3 duration 193 mins.
Job 9 Operation 3 duration 11 mins.
Job 0 Operation 5 duration 214 mins.
Job 6 Operation 5 duration 85 mins.
Job 1 Operation 6 duration 251 mins.
Job 2 Operation 6 duration 278 mins.
Job 3 Operation 6 duration 82 mins.
Job 5 Operation 6 duration 263 mins.
Machine 6 is used for the following Operations:
Job 3 Operation 0 duration 125 mins.
Job 4 Operation 0 duration 104 mins.
Job 9 Operation 1 duration 6 mins.
Job 0 Operation 2 duration 103 mins.
Job 1 Operation 4 duration 35 mins.
Job 6 Operation 4 duration 165 mins.
Job 2 Operation 5 duration 68 mins.
Job 5 Operation 5 duration 141 mins.
Job 8 Operation 5 duration 193 mins.
Job 7 Operation 6 duration 110 mins.
| Solution:
Job 8 Operation 0 on Machine 0 : 0 + 254 -> 254
Job 6 Operation 0 on Machine 1 : 0 + 59 -> 59
Job 4 Operation 0 on Machine 6 : 0 + 104 -> 104
Job 0 Operation 0 on Machine 1 : 59 + 189 -> 248
Job 6 Operation 1 on Machine 3 : 59 + 239 -> 298
Job 4 Operation 1 on Machine 5 : 104 + 51 -> 155
Job 4 Operation 2 on Machine 4 : 155 + 193 -> 348
Job 9 Operation 0 on Machine 1 : 248 + 47 -> 295
Job 0 Operation 1 on Machine 2 : 248 + 32 -> 280
Job 2 Operation 0 on Machine 0 : 254 + 255 -> 509
Job 0 Operation 2 on Machine 6 : 280 + 103 -> 383
Job 8 Operation 1 on Machine 3 : 298 + 5 -> 303
Job 8 Operation 2 on Machine 2 : 303 + 236 -> 539
Job 0 Operation 3 on Machine 3 : 383 + 283 -> 666
Job 3 Operation 0 on Machine 6 : 383 + 125 -> 508
Job 9 Operation 1 on Machine 6 : 508 + 6 -> 514
Job 5 Operation 0 on Machine 0 : 509 + 96 -> 605
Job 2 Operation 1 on Machine 4 : 509 + 215 -> 724
Job 9 Operation 2 on Machine 2 : 539 + 51 -> 590
Job 8 Operation 3 on Machine 5 : 539 + 193 -> 732
Job 1 Operation 0 on Machine 0 : 605 + 228 -> 833
Job 5 Operation 1 on Machine 1 : 605 + 89 -> 694
Job 5 Operation 2 on Machine 3 : 694 + 57 -> 751
Job 0 Operation 4 on Machine 4 : 724 + 92 -> 816
Job 9 Operation 3 on Machine 5 : 732 + 11 -> 743
Job 5 Operation 3 on Machine 2 : 751 + 73 -> 824
Job 2 Operation 2 on Machine 3 : 751 + 289 -> 1040
Job 0 Operation 5 on Machine 5 : 816 + 214 -> 1030
Job 5 Operation 4 on Machine 4 : 824 + 113 -> 937
Job 4 Operation 3 on Machine 0 : 833 + 155 -> 988
Job 1 Operation 1 on Machine 1 : 833 + 193 -> 1026
Job 6 Operation 2 on Machine 4 : 937 + 229 -> 1166
Job 5 Operation 5 on Machine 6 : 937 + 141 -> 1078
Job 7 Operation 0 on Machine 0 : 988 + 98 -> 1086
Job 4 Operation 4 on Machine 1 : 1026 + 272 -> 1298
Job 2 Operation 3 on Machine 2 : 1040 + 88 -> 1128
Job 1 Operation 2 on Machine 3 : 1040 + 90 -> 1130
Job 5 Operation 6 on Machine 5 : 1078 + 263 -> 1341
Job 3 Operation 1 on Machine 0 : 1086 + 268 -> 1354
Job 1 Operation 3 on Machine 2 : 1130 + 143 -> 1273
Job 9 Operation 4 on Machine 4 : 1166 + 158 -> 1324
Job 1 Operation 4 on Machine 6 : 1273 + 35 -> 1308
Job 2 Operation 4 on Machine 1 : 1298 + 140 -> 1438
Job 4 Operation 5 on Machine 2 : 1298 + 252 -> 1550
Job 1 Operation 5 on Machine 4 : 1324 + 39 -> 1363
Job 7 Operation 1 on Machine 5 : 1341 + 44 -> 1385
Job 6 Operation 3 on Machine 0 : 1354 + 172 -> 1526
Job 3 Operation 2 on Machine 3 : 1354 + 163 -> 1517
Job 8 Operation 4 on Machine 4 : 1363 + 82 -> 1445
Job 1 Operation 6 on Machine 5 : 1385 + 251 -> 1636
Job 7 Operation 2 on Machine 1 : 1438 + 102 -> 1540
Job 2 Operation 5 on Machine 6 : 1438 + 68 -> 1506
Job 8 Operation 5 on Machine 6 : 1506 + 193 -> 1699
Job 3 Operation 3 on Machine 4 : 1517 + 88 -> 1605
Job 9 Operation 5 on Machine 0 : 1526 + 257 -> 1783
Job 7 Operation 3 on Machine 2 : 1550 + 61 -> 1611
Job 4 Operation 6 on Machine 3 : 1550 + 292 -> 1842
Job 3 Operation 4 on Machine 1 : 1605 + 148 -> 1753
Job 7 Operation 4 on Machine 4 : 1611 + 61 -> 1672
Job 2 Operation 6 on Machine 5 : 1636 + 278 -> 1914
Job 6 Operation 4 on Machine 6 : 1699 + 165 -> 1864
Job 8 Operation 6 on Machine 1 : 1753 + 279 -> 2032
Job 3 Operation 5 on Machine 2 : 1753 + 31 -> 1784
Job 0 Operation 6 on Machine 0 : 1783 + 127 -> 1910
Job 7 Operation 5 on Machine 3 : 1842 + 16 -> 1858
Job 9 Operation 6 on Machine 3 : 1858 + 227 -> 2085
Job 7 Operation 6 on Machine 6 : 1864 + 110 -> 1974
Job 6 Operation 5 on Machine 5 : 1914 + 85 -> 1999
Job 6 Operation 6 on Machine 2 : 1999 + 21 -> 2020
Job 3 Operation 6 on Machine 5 : 1999 + 82 -> 2081
Makespan: 2085.0, as it is the maximum end completion time of Operation 6 |
8 | 3 | Optimize schedule for 8 Jobs across 3 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 2 duration 47 mins.
Operation 1 on Machine 0 duration 86 mins.
Operation 2 on Machine 1 duration 359 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 0 duration 270 mins.
Operation 1 on Machine 1 duration 290 mins.
Operation 2 on Machine 2 duration 280 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 2 duration 222 mins.
Operation 1 on Machine 0 duration 353 mins.
Operation 2 on Machine 1 duration 17 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 1 duration 301 mins.
Operation 1 on Machine 2 duration 293 mins.
Operation 2 on Machine 0 duration 9 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 1 duration 89 mins.
Operation 1 on Machine 0 duration 363 mins.
Operation 2 on Machine 2 duration 250 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 0 duration 409 mins.
Operation 1 on Machine 1 duration 173 mins.
Operation 2 on Machine 2 duration 206 mins.
Job 6 consists of the following Operations:
Operation 0 on Machine 0 duration 106 mins.
Operation 1 on Machine 2 duration 409 mins.
Operation 2 on Machine 1 duration 248 mins.
Job 7 consists of the following Operations:
Operation 0 on Machine 2 duration 397 mins.
Operation 1 on Machine 0 duration 223 mins.
Operation 2 on Machine 1 duration 367 mins.
| Optimize schedule for 8 Jobs across 3 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 1 Operation 0 duration 270 mins.
Job 5 Operation 0 duration 409 mins.
Job 6 Operation 0 duration 106 mins.
Job 0 Operation 1 duration 86 mins.
Job 2 Operation 1 duration 353 mins.
Job 4 Operation 1 duration 363 mins.
Job 7 Operation 1 duration 223 mins.
Job 3 Operation 2 duration 9 mins.
Machine 1 is used for the following Operations:
Job 3 Operation 0 duration 301 mins.
Job 4 Operation 0 duration 89 mins.
Job 1 Operation 1 duration 290 mins.
Job 5 Operation 1 duration 173 mins.
Job 0 Operation 2 duration 359 mins.
Job 2 Operation 2 duration 17 mins.
Job 6 Operation 2 duration 248 mins.
Job 7 Operation 2 duration 367 mins.
Machine 2 is used for the following Operations:
Job 0 Operation 0 duration 47 mins.
Job 2 Operation 0 duration 222 mins.
Job 7 Operation 0 duration 397 mins.
Job 3 Operation 1 duration 293 mins.
Job 6 Operation 1 duration 409 mins.
Job 1 Operation 2 duration 280 mins.
Job 4 Operation 2 duration 250 mins.
Job 5 Operation 2 duration 206 mins.
| Solution:
Job 3 Operation 0 on Machine 1 : 0 + 301 -> 301
Job 0 Operation 0 on Machine 2 : 0 + 47 -> 47
Job 0 Operation 1 on Machine 0 : 47 + 86 -> 133
Job 2 Operation 0 on Machine 2 : 47 + 222 -> 269
Job 6 Operation 0 on Machine 0 : 133 + 106 -> 239
Job 1 Operation 0 on Machine 0 : 239 + 270 -> 509
Job 6 Operation 1 on Machine 2 : 269 + 409 -> 678
Job 0 Operation 2 on Machine 1 : 301 + 359 -> 660
Job 5 Operation 0 on Machine 0 : 509 + 409 -> 918
Job 6 Operation 2 on Machine 1 : 678 + 248 -> 926
Job 3 Operation 1 on Machine 2 : 678 + 293 -> 971
Job 4 Operation 0 on Machine 1 : 926 + 89 -> 1015
Job 3 Operation 2 on Machine 0 : 971 + 9 -> 980
Job 7 Operation 0 on Machine 2 : 971 + 397 -> 1368
Job 4 Operation 1 on Machine 0 : 1015 + 363 -> 1378
Job 5 Operation 1 on Machine 1 : 1015 + 173 -> 1188
Job 1 Operation 1 on Machine 1 : 1188 + 290 -> 1478
Job 5 Operation 2 on Machine 2 : 1368 + 206 -> 1574
Job 7 Operation 1 on Machine 0 : 1378 + 223 -> 1601
Job 4 Operation 2 on Machine 2 : 1574 + 250 -> 1824
Job 2 Operation 1 on Machine 0 : 1601 + 353 -> 1954
Job 7 Operation 2 on Machine 1 : 1601 + 367 -> 1968
Job 1 Operation 2 on Machine 2 : 1824 + 280 -> 2104
Job 2 Operation 2 on Machine 1 : 1968 + 17 -> 1985
Makespan: 2104.0, as it is the maximum end completion time of Operation 2 |
9 | 6 | Optimize schedule for 9 Jobs across 6 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 2 duration 196 mins.
Operation 1 on Machine 4 duration 2 mins.
Operation 2 on Machine 5 duration 465 mins.
Operation 3 on Machine 1 duration 106 mins.
Operation 4 on Machine 3 duration 389 mins.
Operation 5 on Machine 0 duration 23 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 2 duration 81 mins.
Operation 1 on Machine 5 duration 356 mins.
Operation 2 on Machine 4 duration 387 mins.
Operation 3 on Machine 3 duration 240 mins.
Operation 4 on Machine 1 duration 183 mins.
Operation 5 on Machine 0 duration 294 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 2 duration 426 mins.
Operation 1 on Machine 4 duration 95 mins.
Operation 2 on Machine 1 duration 334 mins.
Operation 3 on Machine 0 duration 301 mins.
Operation 4 on Machine 3 duration 153 mins.
Operation 5 on Machine 5 duration 401 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 0 duration 17 mins.
Operation 1 on Machine 3 duration 123 mins.
Operation 2 on Machine 5 duration 431 mins.
Operation 3 on Machine 1 duration 344 mins.
Operation 4 on Machine 2 duration 112 mins.
Operation 5 on Machine 4 duration 231 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 2 duration 24 mins.
Operation 1 on Machine 0 duration 360 mins.
Operation 2 on Machine 4 duration 42 mins.
Operation 3 on Machine 1 duration 211 mins.
Operation 4 on Machine 5 duration 259 mins.
Operation 5 on Machine 3 duration 414 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 2 duration 453 mins.
Operation 1 on Machine 1 duration 203 mins.
Operation 2 on Machine 5 duration 261 mins.
Operation 3 on Machine 4 duration 302 mins.
Operation 4 on Machine 3 duration 368 mins.
Operation 5 on Machine 0 duration 446 mins.
Job 6 consists of the following Operations:
Operation 0 on Machine 4 duration 429 mins.
Operation 1 on Machine 1 duration 131 mins.
Operation 2 on Machine 5 duration 12 mins.
Operation 3 on Machine 3 duration 132 mins.
Operation 4 on Machine 2 duration 373 mins.
Operation 5 on Machine 0 duration 443 mins.
Job 7 consists of the following Operations:
Operation 0 on Machine 4 duration 467 mins.
Operation 1 on Machine 5 duration 109 mins.
Operation 2 on Machine 2 duration 425 mins.
Operation 3 on Machine 0 duration 177 mins.
Operation 4 on Machine 1 duration 397 mins.
Operation 5 on Machine 3 duration 430 mins.
Job 8 consists of the following Operations:
Operation 0 on Machine 0 duration 80 mins.
Operation 1 on Machine 4 duration 229 mins.
Operation 2 on Machine 1 duration 48 mins.
Operation 3 on Machine 2 duration 104 mins.
Operation 4 on Machine 3 duration 416 mins.
Operation 5 on Machine 5 duration 418 mins.
| Optimize schedule for 9 Jobs across 6 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 3 Operation 0 duration 17 mins.
Job 8 Operation 0 duration 80 mins.
Job 4 Operation 1 duration 360 mins.
Job 2 Operation 3 duration 301 mins.
Job 7 Operation 3 duration 177 mins.
Job 0 Operation 5 duration 23 mins.
Job 1 Operation 5 duration 294 mins.
Job 5 Operation 5 duration 446 mins.
Job 6 Operation 5 duration 443 mins.
Machine 1 is used for the following Operations:
Job 5 Operation 1 duration 203 mins.
Job 6 Operation 1 duration 131 mins.
Job 2 Operation 2 duration 334 mins.
Job 8 Operation 2 duration 48 mins.
Job 0 Operation 3 duration 106 mins.
Job 3 Operation 3 duration 344 mins.
Job 4 Operation 3 duration 211 mins.
Job 1 Operation 4 duration 183 mins.
Job 7 Operation 4 duration 397 mins.
Machine 2 is used for the following Operations:
Job 0 Operation 0 duration 196 mins.
Job 1 Operation 0 duration 81 mins.
Job 2 Operation 0 duration 426 mins.
Job 4 Operation 0 duration 24 mins.
Job 5 Operation 0 duration 453 mins.
Job 7 Operation 2 duration 425 mins.
Job 8 Operation 3 duration 104 mins.
Job 3 Operation 4 duration 112 mins.
Job 6 Operation 4 duration 373 mins.
Machine 3 is used for the following Operations:
Job 3 Operation 1 duration 123 mins.
Job 1 Operation 3 duration 240 mins.
Job 6 Operation 3 duration 132 mins.
Job 0 Operation 4 duration 389 mins.
Job 2 Operation 4 duration 153 mins.
Job 5 Operation 4 duration 368 mins.
Job 8 Operation 4 duration 416 mins.
Job 4 Operation 5 duration 414 mins.
Job 7 Operation 5 duration 430 mins.
Machine 4 is used for the following Operations:
Job 6 Operation 0 duration 429 mins.
Job 7 Operation 0 duration 467 mins.
Job 0 Operation 1 duration 2 mins.
Job 2 Operation 1 duration 95 mins.
Job 8 Operation 1 duration 229 mins.
Job 1 Operation 2 duration 387 mins.
Job 4 Operation 2 duration 42 mins.
Job 5 Operation 3 duration 302 mins.
Job 3 Operation 5 duration 231 mins.
Machine 5 is used for the following Operations:
Job 1 Operation 1 duration 356 mins.
Job 7 Operation 1 duration 109 mins.
Job 0 Operation 2 duration 465 mins.
Job 3 Operation 2 duration 431 mins.
Job 5 Operation 2 duration 261 mins.
Job 6 Operation 2 duration 12 mins.
Job 4 Operation 4 duration 259 mins.
Job 2 Operation 5 duration 401 mins.
Job 8 Operation 5 duration 418 mins.
| Solution:
Job 3 Operation 0 on Machine 0 : 0 + 17 -> 17
Job 1 Operation 0 on Machine 2 : 0 + 81 -> 81
Job 6 Operation 0 on Machine 4 : 0 + 429 -> 429
Job 8 Operation 0 on Machine 0 : 17 + 80 -> 97
Job 3 Operation 1 on Machine 3 : 17 + 123 -> 140
Job 0 Operation 0 on Machine 2 : 81 + 196 -> 277
Job 3 Operation 2 on Machine 5 : 140 + 431 -> 571
Job 4 Operation 0 on Machine 2 : 277 + 24 -> 301
Job 4 Operation 1 on Machine 0 : 301 + 360 -> 661
Job 2 Operation 0 on Machine 2 : 301 + 426 -> 727
Job 6 Operation 1 on Machine 1 : 429 + 131 -> 560
Job 8 Operation 1 on Machine 4 : 429 + 229 -> 658
Job 6 Operation 2 on Machine 5 : 571 + 12 -> 583
Job 6 Operation 3 on Machine 3 : 583 + 132 -> 715
Job 1 Operation 1 on Machine 5 : 583 + 356 -> 939
Job 8 Operation 2 on Machine 1 : 658 + 48 -> 706
Job 0 Operation 1 on Machine 4 : 658 + 2 -> 660
Job 4 Operation 2 on Machine 4 : 661 + 42 -> 703
Job 4 Operation 3 on Machine 1 : 706 + 211 -> 917
Job 8 Operation 3 on Machine 2 : 727 + 104 -> 831
Job 2 Operation 1 on Machine 4 : 727 + 95 -> 822
Job 7 Operation 0 on Machine 4 : 822 + 467 -> 1289
Job 5 Operation 0 on Machine 2 : 831 + 453 -> 1284
Job 8 Operation 4 on Machine 3 : 831 + 416 -> 1247
Job 2 Operation 2 on Machine 1 : 917 + 334 -> 1251
Job 4 Operation 4 on Machine 5 : 939 + 259 -> 1198
Job 4 Operation 5 on Machine 3 : 1247 + 414 -> 1661
Job 2 Operation 3 on Machine 0 : 1251 + 301 -> 1552
Job 5 Operation 1 on Machine 1 : 1284 + 203 -> 1487
Job 6 Operation 4 on Machine 2 : 1284 + 373 -> 1657
Job 1 Operation 2 on Machine 4 : 1289 + 387 -> 1676
Job 7 Operation 1 on Machine 5 : 1289 + 109 -> 1398
Job 3 Operation 3 on Machine 1 : 1487 + 344 -> 1831
Job 5 Operation 2 on Machine 5 : 1487 + 261 -> 1748
Job 6 Operation 5 on Machine 0 : 1657 + 443 -> 2100
Job 7 Operation 2 on Machine 2 : 1657 + 425 -> 2082
Job 2 Operation 4 on Machine 3 : 1661 + 153 -> 1814
Job 5 Operation 3 on Machine 4 : 1748 + 302 -> 2050
Job 0 Operation 2 on Machine 5 : 1748 + 465 -> 2213
Job 1 Operation 3 on Machine 3 : 1814 + 240 -> 2054
Job 1 Operation 4 on Machine 1 : 2054 + 183 -> 2237
Job 5 Operation 4 on Machine 3 : 2054 + 368 -> 2422
Job 3 Operation 4 on Machine 2 : 2082 + 112 -> 2194
Job 7 Operation 3 on Machine 0 : 2100 + 177 -> 2277
Job 3 Operation 5 on Machine 4 : 2194 + 231 -> 2425
Job 8 Operation 5 on Machine 5 : 2213 + 418 -> 2631
Job 0 Operation 3 on Machine 1 : 2237 + 106 -> 2343
Job 1 Operation 5 on Machine 0 : 2277 + 294 -> 2571
Job 7 Operation 4 on Machine 1 : 2343 + 397 -> 2740
Job 0 Operation 4 on Machine 3 : 2422 + 389 -> 2811
Job 5 Operation 5 on Machine 0 : 2571 + 446 -> 3017
Job 2 Operation 5 on Machine 5 : 2631 + 401 -> 3032
Job 7 Operation 5 on Machine 3 : 2811 + 430 -> 3241
Job 0 Operation 5 on Machine 0 : 3017 + 23 -> 3040
Makespan: 3241.0, as it is the maximum end completion time of Operation 5 |
8 | 2 | Optimize schedule for 8 Jobs across 2 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 0 duration 66 mins.
Operation 1 on Machine 1 duration 233 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 0 duration 246 mins.
Operation 1 on Machine 1 duration 279 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 0 duration 77 mins.
Operation 1 on Machine 1 duration 74 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 0 duration 99 mins.
Operation 1 on Machine 1 duration 191 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 0 duration 19 mins.
Operation 1 on Machine 1 duration 90 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 0 duration 106 mins.
Operation 1 on Machine 1 duration 73 mins.
Job 6 consists of the following Operations:
Operation 0 on Machine 0 duration 21 mins.
Operation 1 on Machine 1 duration 194 mins.
Job 7 consists of the following Operations:
Operation 0 on Machine 0 duration 198 mins.
Operation 1 on Machine 1 duration 278 mins.
| Optimize schedule for 8 Jobs across 2 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 0 Operation 0 duration 66 mins.
Job 1 Operation 0 duration 246 mins.
Job 2 Operation 0 duration 77 mins.
Job 3 Operation 0 duration 99 mins.
Job 4 Operation 0 duration 19 mins.
Job 5 Operation 0 duration 106 mins.
Job 6 Operation 0 duration 21 mins.
Job 7 Operation 0 duration 198 mins.
Machine 1 is used for the following Operations:
Job 0 Operation 1 duration 233 mins.
Job 1 Operation 1 duration 279 mins.
Job 2 Operation 1 duration 74 mins.
Job 3 Operation 1 duration 191 mins.
Job 4 Operation 1 duration 90 mins.
Job 5 Operation 1 duration 73 mins.
Job 6 Operation 1 duration 194 mins.
Job 7 Operation 1 duration 278 mins.
| Solution:
Job 4 Operation 0 on Machine 0 : 0 + 19 -> 19
Job 6 Operation 0 on Machine 0 : 19 + 21 -> 40
Job 4 Operation 1 on Machine 1 : 19 + 90 -> 109
Job 0 Operation 0 on Machine 0 : 40 + 66 -> 106
Job 2 Operation 0 on Machine 0 : 106 + 77 -> 183
Job 6 Operation 1 on Machine 1 : 109 + 194 -> 303
Job 3 Operation 0 on Machine 0 : 183 + 99 -> 282
Job 5 Operation 0 on Machine 0 : 282 + 106 -> 388
Job 2 Operation 1 on Machine 1 : 303 + 74 -> 377
Job 3 Operation 1 on Machine 1 : 377 + 191 -> 568
Job 7 Operation 0 on Machine 0 : 388 + 198 -> 586
Job 5 Operation 1 on Machine 1 : 568 + 73 -> 641
Job 1 Operation 0 on Machine 0 : 586 + 246 -> 832
Job 0 Operation 1 on Machine 1 : 641 + 233 -> 874
Job 7 Operation 1 on Machine 1 : 874 + 278 -> 1152
Job 1 Operation 1 on Machine 1 : 1152 + 279 -> 1431
Makespan: 1431.0, as it is the maximum end completion time of Operation 1 |
7 | 5 | Optimize schedule for 7 Jobs across 5 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 2 duration 446 mins.
Operation 1 on Machine 3 duration 321 mins.
Operation 2 on Machine 1 duration 245 mins.
Operation 3 on Machine 0 duration 173 mins.
Operation 4 on Machine 4 duration 26 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 3 duration 337 mins.
Operation 1 on Machine 4 duration 35 mins.
Operation 2 on Machine 2 duration 97 mins.
Operation 3 on Machine 0 duration 147 mins.
Operation 4 on Machine 1 duration 377 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 0 duration 43 mins.
Operation 1 on Machine 4 duration 76 mins.
Operation 2 on Machine 3 duration 432 mins.
Operation 3 on Machine 1 duration 319 mins.
Operation 4 on Machine 2 duration 143 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 0 duration 354 mins.
Operation 1 on Machine 4 duration 270 mins.
Operation 2 on Machine 2 duration 137 mins.
Operation 3 on Machine 1 duration 27 mins.
Operation 4 on Machine 3 duration 180 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 3 duration 325 mins.
Operation 1 on Machine 1 duration 306 mins.
Operation 2 on Machine 0 duration 85 mins.
Operation 3 on Machine 4 duration 126 mins.
Operation 4 on Machine 2 duration 165 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 0 duration 424 mins.
Operation 1 on Machine 1 duration 289 mins.
Operation 2 on Machine 3 duration 232 mins.
Operation 3 on Machine 2 duration 9 mins.
Operation 4 on Machine 4 duration 203 mins.
Job 6 consists of the following Operations:
Operation 0 on Machine 4 duration 14 mins.
Operation 1 on Machine 0 duration 142 mins.
Operation 2 on Machine 2 duration 340 mins.
Operation 3 on Machine 3 duration 358 mins.
Operation 4 on Machine 1 duration 264 mins.
| Optimize schedule for 7 Jobs across 5 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 2 Operation 0 duration 43 mins.
Job 3 Operation 0 duration 354 mins.
Job 5 Operation 0 duration 424 mins.
Job 6 Operation 1 duration 142 mins.
Job 4 Operation 2 duration 85 mins.
Job 0 Operation 3 duration 173 mins.
Job 1 Operation 3 duration 147 mins.
Machine 1 is used for the following Operations:
Job 4 Operation 1 duration 306 mins.
Job 5 Operation 1 duration 289 mins.
Job 0 Operation 2 duration 245 mins.
Job 2 Operation 3 duration 319 mins.
Job 3 Operation 3 duration 27 mins.
Job 1 Operation 4 duration 377 mins.
Job 6 Operation 4 duration 264 mins.
Machine 2 is used for the following Operations:
Job 0 Operation 0 duration 446 mins.
Job 1 Operation 2 duration 97 mins.
Job 3 Operation 2 duration 137 mins.
Job 6 Operation 2 duration 340 mins.
Job 5 Operation 3 duration 9 mins.
Job 2 Operation 4 duration 143 mins.
Job 4 Operation 4 duration 165 mins.
Machine 3 is used for the following Operations:
Job 1 Operation 0 duration 337 mins.
Job 4 Operation 0 duration 325 mins.
Job 0 Operation 1 duration 321 mins.
Job 2 Operation 2 duration 432 mins.
Job 5 Operation 2 duration 232 mins.
Job 6 Operation 3 duration 358 mins.
Job 3 Operation 4 duration 180 mins.
Machine 4 is used for the following Operations:
Job 6 Operation 0 duration 14 mins.
Job 1 Operation 1 duration 35 mins.
Job 2 Operation 1 duration 76 mins.
Job 3 Operation 1 duration 270 mins.
Job 4 Operation 3 duration 126 mins.
Job 0 Operation 4 duration 26 mins.
Job 5 Operation 4 duration 203 mins.
| Solution:
Job 2 Operation 0 on Machine 0 : 0 + 43 -> 43
Job 0 Operation 0 on Machine 2 : 0 + 446 -> 446
Job 4 Operation 0 on Machine 3 : 0 + 325 -> 325
Job 6 Operation 0 on Machine 4 : 0 + 14 -> 14
Job 5 Operation 0 on Machine 0 : 43 + 424 -> 467
Job 2 Operation 1 on Machine 4 : 43 + 76 -> 119
Job 4 Operation 1 on Machine 1 : 325 + 306 -> 631
Job 1 Operation 0 on Machine 3 : 325 + 337 -> 662
Job 3 Operation 0 on Machine 0 : 467 + 354 -> 821
Job 5 Operation 1 on Machine 1 : 631 + 289 -> 920
Job 0 Operation 1 on Machine 3 : 662 + 321 -> 983
Job 1 Operation 1 on Machine 4 : 662 + 35 -> 697
Job 1 Operation 2 on Machine 2 : 697 + 97 -> 794
Job 6 Operation 1 on Machine 0 : 821 + 142 -> 963
Job 3 Operation 1 on Machine 4 : 821 + 270 -> 1091
Job 4 Operation 2 on Machine 0 : 963 + 85 -> 1048
Job 6 Operation 2 on Machine 2 : 963 + 340 -> 1303
Job 0 Operation 2 on Machine 1 : 983 + 245 -> 1228
Job 2 Operation 2 on Machine 3 : 983 + 432 -> 1415
Job 1 Operation 3 on Machine 0 : 1048 + 147 -> 1195
Job 4 Operation 3 on Machine 4 : 1091 + 126 -> 1217
Job 0 Operation 3 on Machine 0 : 1228 + 173 -> 1401
Job 1 Operation 4 on Machine 1 : 1228 + 377 -> 1605
Job 3 Operation 2 on Machine 2 : 1303 + 137 -> 1440
Job 0 Operation 4 on Machine 4 : 1401 + 26 -> 1427
Job 6 Operation 3 on Machine 3 : 1415 + 358 -> 1773
Job 4 Operation 4 on Machine 2 : 1440 + 165 -> 1605
Job 3 Operation 3 on Machine 1 : 1605 + 27 -> 1632
Job 2 Operation 3 on Machine 1 : 1632 + 319 -> 1951
Job 5 Operation 2 on Machine 3 : 1773 + 232 -> 2005
Job 6 Operation 4 on Machine 1 : 1951 + 264 -> 2215
Job 5 Operation 3 on Machine 2 : 2005 + 9 -> 2014
Job 3 Operation 4 on Machine 3 : 2005 + 180 -> 2185
Job 2 Operation 4 on Machine 2 : 2014 + 143 -> 2157
Job 5 Operation 4 on Machine 4 : 2014 + 203 -> 2217
Makespan: 2217.0, as it is the maximum end completion time of Operation 4 |
8 | 5 | Optimize schedule for 8 Jobs across 5 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 1 duration 120 mins.
Operation 1 on Machine 3 duration 157 mins.
Operation 2 on Machine 4 duration 97 mins.
Operation 3 on Machine 0 duration 143 mins.
Operation 4 on Machine 2 duration 19 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 1 duration 21 mins.
Operation 1 on Machine 2 duration 72 mins.
Operation 2 on Machine 4 duration 114 mins.
Operation 3 on Machine 3 duration 154 mins.
Operation 4 on Machine 0 duration 118 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 0 duration 73 mins.
Operation 1 on Machine 3 duration 80 mins.
Operation 2 on Machine 1 duration 41 mins.
Operation 3 on Machine 4 duration 88 mins.
Operation 4 on Machine 2 duration 146 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 4 duration 82 mins.
Operation 1 on Machine 1 duration 11 mins.
Operation 2 on Machine 2 duration 45 mins.
Operation 3 on Machine 3 duration 56 mins.
Operation 4 on Machine 0 duration 78 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 1 duration 122 mins.
Operation 1 on Machine 0 duration 132 mins.
Operation 2 on Machine 3 duration 158 mins.
Operation 3 on Machine 4 duration 124 mins.
Operation 4 on Machine 2 duration 151 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 4 duration 103 mins.
Operation 1 on Machine 2 duration 58 mins.
Operation 2 on Machine 0 duration 120 mins.
Operation 3 on Machine 3 duration 14 mins.
Operation 4 on Machine 1 duration 50 mins.
Job 6 consists of the following Operations:
Operation 0 on Machine 1 duration 100 mins.
Operation 1 on Machine 2 duration 8 mins.
Operation 2 on Machine 3 duration 38 mins.
Operation 3 on Machine 4 duration 49 mins.
Operation 4 on Machine 0 duration 54 mins.
Job 7 consists of the following Operations:
Operation 0 on Machine 4 duration 56 mins.
Operation 1 on Machine 2 duration 27 mins.
Operation 2 on Machine 3 duration 28 mins.
Operation 3 on Machine 0 duration 37 mins.
Operation 4 on Machine 1 duration 57 mins.
| Optimize schedule for 8 Jobs across 5 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 2 Operation 0 duration 73 mins.
Job 4 Operation 1 duration 132 mins.
Job 5 Operation 2 duration 120 mins.
Job 0 Operation 3 duration 143 mins.
Job 7 Operation 3 duration 37 mins.
Job 1 Operation 4 duration 118 mins.
Job 3 Operation 4 duration 78 mins.
Job 6 Operation 4 duration 54 mins.
Machine 1 is used for the following Operations:
Job 0 Operation 0 duration 120 mins.
Job 1 Operation 0 duration 21 mins.
Job 4 Operation 0 duration 122 mins.
Job 6 Operation 0 duration 100 mins.
Job 3 Operation 1 duration 11 mins.
Job 2 Operation 2 duration 41 mins.
Job 5 Operation 4 duration 50 mins.
Job 7 Operation 4 duration 57 mins.
Machine 2 is used for the following Operations:
Job 1 Operation 1 duration 72 mins.
Job 5 Operation 1 duration 58 mins.
Job 6 Operation 1 duration 8 mins.
Job 7 Operation 1 duration 27 mins.
Job 3 Operation 2 duration 45 mins.
Job 0 Operation 4 duration 19 mins.
Job 2 Operation 4 duration 146 mins.
Job 4 Operation 4 duration 151 mins.
Machine 3 is used for the following Operations:
Job 0 Operation 1 duration 157 mins.
Job 2 Operation 1 duration 80 mins.
Job 4 Operation 2 duration 158 mins.
Job 6 Operation 2 duration 38 mins.
Job 7 Operation 2 duration 28 mins.
Job 1 Operation 3 duration 154 mins.
Job 3 Operation 3 duration 56 mins.
Job 5 Operation 3 duration 14 mins.
Machine 4 is used for the following Operations:
Job 3 Operation 0 duration 82 mins.
Job 5 Operation 0 duration 103 mins.
Job 7 Operation 0 duration 56 mins.
Job 0 Operation 2 duration 97 mins.
Job 1 Operation 2 duration 114 mins.
Job 2 Operation 3 duration 88 mins.
Job 4 Operation 3 duration 124 mins.
Job 6 Operation 3 duration 49 mins.
| Solution:
Job 2 Operation 0 on Machine 0 : 0 + 73 -> 73
Job 1 Operation 0 on Machine 1 : 0 + 21 -> 21
Job 5 Operation 0 on Machine 4 : 0 + 103 -> 103
Job 0 Operation 0 on Machine 1 : 21 + 120 -> 141
Job 1 Operation 1 on Machine 2 : 21 + 72 -> 93
Job 2 Operation 1 on Machine 3 : 73 + 80 -> 153
Job 5 Operation 1 on Machine 2 : 103 + 58 -> 161
Job 3 Operation 0 on Machine 4 : 103 + 82 -> 185
Job 4 Operation 0 on Machine 1 : 141 + 122 -> 263
Job 0 Operation 1 on Machine 3 : 153 + 157 -> 310
Job 5 Operation 2 on Machine 0 : 161 + 120 -> 281
Job 7 Operation 0 on Machine 4 : 185 + 56 -> 241
Job 7 Operation 1 on Machine 2 : 241 + 27 -> 268
Job 1 Operation 2 on Machine 4 : 241 + 114 -> 355
Job 3 Operation 1 on Machine 1 : 263 + 11 -> 274
Job 6 Operation 0 on Machine 1 : 274 + 100 -> 374
Job 3 Operation 2 on Machine 2 : 274 + 45 -> 319
Job 4 Operation 1 on Machine 0 : 281 + 132 -> 413
Job 7 Operation 2 on Machine 3 : 310 + 28 -> 338
Job 3 Operation 3 on Machine 3 : 338 + 56 -> 394
Job 0 Operation 2 on Machine 4 : 355 + 97 -> 452
Job 2 Operation 2 on Machine 1 : 374 + 41 -> 415
Job 6 Operation 1 on Machine 2 : 374 + 8 -> 382
Job 6 Operation 2 on Machine 3 : 394 + 38 -> 432
Job 7 Operation 3 on Machine 0 : 413 + 37 -> 450
Job 4 Operation 2 on Machine 3 : 432 + 158 -> 590
Job 7 Operation 4 on Machine 1 : 450 + 57 -> 507
Job 0 Operation 3 on Machine 0 : 452 + 143 -> 595
Job 2 Operation 3 on Machine 4 : 452 + 88 -> 540
Job 2 Operation 4 on Machine 2 : 540 + 146 -> 686
Job 6 Operation 3 on Machine 4 : 540 + 49 -> 589
Job 1 Operation 3 on Machine 3 : 590 + 154 -> 744
Job 4 Operation 3 on Machine 4 : 590 + 124 -> 714
Job 6 Operation 4 on Machine 0 : 595 + 54 -> 649
Job 3 Operation 4 on Machine 0 : 649 + 78 -> 727
Job 0 Operation 4 on Machine 2 : 686 + 19 -> 705
Job 4 Operation 4 on Machine 2 : 714 + 151 -> 865
Job 1 Operation 4 on Machine 0 : 744 + 118 -> 862
Job 5 Operation 3 on Machine 3 : 744 + 14 -> 758
Job 5 Operation 4 on Machine 1 : 758 + 50 -> 808
Makespan: 865.0, as it is the maximum end completion time of Operation 4 |
7 | 2 | Optimize schedule for 7 Jobs across 2 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 0 duration 44 mins.
Operation 1 on Machine 1 duration 32 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 0 duration 30 mins.
Operation 1 on Machine 1 duration 73 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 0 duration 75 mins.
Operation 1 on Machine 1 duration 41 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 0 duration 52 mins.
Operation 1 on Machine 1 duration 20 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 1 duration 61 mins.
Operation 1 on Machine 0 duration 70 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 0 duration 59 mins.
Operation 1 on Machine 1 duration 62 mins.
Job 6 consists of the following Operations:
Operation 0 on Machine 0 duration 44 mins.
Operation 1 on Machine 1 duration 55 mins.
| Optimize schedule for 7 Jobs across 2 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 0 Operation 0 duration 44 mins.
Job 1 Operation 0 duration 30 mins.
Job 2 Operation 0 duration 75 mins.
Job 3 Operation 0 duration 52 mins.
Job 5 Operation 0 duration 59 mins.
Job 6 Operation 0 duration 44 mins.
Job 4 Operation 1 duration 70 mins.
Machine 1 is used for the following Operations:
Job 4 Operation 0 duration 61 mins.
Job 0 Operation 1 duration 32 mins.
Job 1 Operation 1 duration 73 mins.
Job 2 Operation 1 duration 41 mins.
Job 3 Operation 1 duration 20 mins.
Job 5 Operation 1 duration 62 mins.
Job 6 Operation 1 duration 55 mins.
| Solution:
Job 1 Operation 0 on Machine 0 : 0 + 30 -> 30
Job 4 Operation 0 on Machine 1 : 0 + 61 -> 61
Job 3 Operation 0 on Machine 0 : 30 + 52 -> 82
Job 0 Operation 0 on Machine 0 : 82 + 44 -> 126
Job 3 Operation 1 on Machine 1 : 82 + 20 -> 102
Job 1 Operation 1 on Machine 1 : 102 + 73 -> 175
Job 2 Operation 0 on Machine 0 : 126 + 75 -> 201
Job 0 Operation 1 on Machine 1 : 175 + 32 -> 207
Job 6 Operation 0 on Machine 0 : 201 + 44 -> 245
Job 2 Operation 1 on Machine 1 : 207 + 41 -> 248
Job 5 Operation 0 on Machine 0 : 245 + 59 -> 304
Job 6 Operation 1 on Machine 1 : 248 + 55 -> 303
Job 4 Operation 1 on Machine 0 : 304 + 70 -> 374
Job 5 Operation 1 on Machine 1 : 304 + 62 -> 366
Makespan: 374.0, as it is the maximum end completion time of Operation 1 |
10 | 8 | Optimize schedule for 10 Jobs across 8 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 4 duration 440 mins.
Operation 1 on Machine 7 duration 81 mins.
Operation 2 on Machine 5 duration 156 mins.
Operation 3 on Machine 0 duration 108 mins.
Operation 4 on Machine 6 duration 368 mins.
Operation 5 on Machine 2 duration 160 mins.
Operation 6 on Machine 3 duration 102 mins.
Operation 7 on Machine 1 duration 180 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 6 duration 313 mins.
Operation 1 on Machine 1 duration 346 mins.
Operation 2 on Machine 7 duration 343 mins.
Operation 3 on Machine 2 duration 295 mins.
Operation 4 on Machine 3 duration 359 mins.
Operation 5 on Machine 5 duration 231 mins.
Operation 6 on Machine 4 duration 95 mins.
Operation 7 on Machine 0 duration 401 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 5 duration 35 mins.
Operation 1 on Machine 1 duration 342 mins.
Operation 2 on Machine 4 duration 167 mins.
Operation 3 on Machine 3 duration 108 mins.
Operation 4 on Machine 0 duration 87 mins.
Operation 5 on Machine 2 duration 107 mins.
Operation 6 on Machine 7 duration 244 mins.
Operation 7 on Machine 6 duration 323 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 5 duration 9 mins.
Operation 1 on Machine 4 duration 373 mins.
Operation 2 on Machine 0 duration 408 mins.
Operation 3 on Machine 7 duration 175 mins.
Operation 4 on Machine 3 duration 167 mins.
Operation 5 on Machine 2 duration 99 mins.
Operation 6 on Machine 6 duration 50 mins.
Operation 7 on Machine 1 duration 228 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 2 duration 250 mins.
Operation 1 on Machine 5 duration 459 mins.
Operation 2 on Machine 6 duration 481 mins.
Operation 3 on Machine 1 duration 32 mins.
Operation 4 on Machine 3 duration 301 mins.
Operation 5 on Machine 0 duration 15 mins.
Operation 6 on Machine 4 duration 301 mins.
Operation 7 on Machine 7 duration 21 mins.
Job 5 consists of the following Operations:
Operation 0 on Machine 3 duration 315 mins.
Operation 1 on Machine 2 duration 244 mins.
Operation 2 on Machine 6 duration 406 mins.
Operation 3 on Machine 1 duration 92 mins.
Operation 4 on Machine 7 duration 21 mins.
Operation 5 on Machine 0 duration 122 mins.
Operation 6 on Machine 5 duration 212 mins.
Operation 7 on Machine 4 duration 356 mins.
Job 6 consists of the following Operations:
Operation 0 on Machine 0 duration 88 mins.
Operation 1 on Machine 2 duration 8 mins.
Operation 2 on Machine 7 duration 310 mins.
Operation 3 on Machine 1 duration 420 mins.
Operation 4 on Machine 6 duration 312 mins.
Operation 5 on Machine 4 duration 484 mins.
Operation 6 on Machine 3 duration 400 mins.
Operation 7 on Machine 5 duration 109 mins.
Job 7 consists of the following Operations:
Operation 0 on Machine 2 duration 131 mins.
Operation 1 on Machine 6 duration 354 mins.
Operation 2 on Machine 3 duration 445 mins.
Operation 3 on Machine 7 duration 291 mins.
Operation 4 on Machine 4 duration 416 mins.
Operation 5 on Machine 1 duration 473 mins.
Operation 6 on Machine 0 duration 313 mins.
Operation 7 on Machine 5 duration 381 mins.
Job 8 consists of the following Operations:
Operation 0 on Machine 1 duration 280 mins.
Operation 1 on Machine 0 duration 323 mins.
Operation 2 on Machine 6 duration 130 mins.
Operation 3 on Machine 7 duration 472 mins.
Operation 4 on Machine 2 duration 60 mins.
Operation 5 on Machine 3 duration 251 mins.
Operation 6 on Machine 5 duration 273 mins.
Operation 7 on Machine 4 duration 42 mins.
Job 9 consists of the following Operations:
Operation 0 on Machine 4 duration 125 mins.
Operation 1 on Machine 1 duration 325 mins.
Operation 2 on Machine 3 duration 477 mins.
Operation 3 on Machine 0 duration 391 mins.
Operation 4 on Machine 6 duration 321 mins.
Operation 5 on Machine 2 duration 7 mins.
Operation 6 on Machine 7 duration 282 mins.
Operation 7 on Machine 5 duration 80 mins.
| Optimize schedule for 10 Jobs across 8 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 6 Operation 0 duration 88 mins.
Job 8 Operation 1 duration 323 mins.
Job 3 Operation 2 duration 408 mins.
Job 0 Operation 3 duration 108 mins.
Job 9 Operation 3 duration 391 mins.
Job 2 Operation 4 duration 87 mins.
Job 4 Operation 5 duration 15 mins.
Job 5 Operation 5 duration 122 mins.
Job 7 Operation 6 duration 313 mins.
Job 1 Operation 7 duration 401 mins.
Machine 1 is used for the following Operations:
Job 8 Operation 0 duration 280 mins.
Job 1 Operation 1 duration 346 mins.
Job 2 Operation 1 duration 342 mins.
Job 9 Operation 1 duration 325 mins.
Job 4 Operation 3 duration 32 mins.
Job 5 Operation 3 duration 92 mins.
Job 6 Operation 3 duration 420 mins.
Job 7 Operation 5 duration 473 mins.
Job 0 Operation 7 duration 180 mins.
Job 3 Operation 7 duration 228 mins.
Machine 2 is used for the following Operations:
Job 4 Operation 0 duration 250 mins.
Job 7 Operation 0 duration 131 mins.
Job 5 Operation 1 duration 244 mins.
Job 6 Operation 1 duration 8 mins.
Job 1 Operation 3 duration 295 mins.
Job 8 Operation 4 duration 60 mins.
Job 0 Operation 5 duration 160 mins.
Job 2 Operation 5 duration 107 mins.
Job 3 Operation 5 duration 99 mins.
Job 9 Operation 5 duration 7 mins.
Machine 3 is used for the following Operations:
Job 5 Operation 0 duration 315 mins.
Job 7 Operation 2 duration 445 mins.
Job 9 Operation 2 duration 477 mins.
Job 2 Operation 3 duration 108 mins.
Job 1 Operation 4 duration 359 mins.
Job 3 Operation 4 duration 167 mins.
Job 4 Operation 4 duration 301 mins.
Job 8 Operation 5 duration 251 mins.
Job 0 Operation 6 duration 102 mins.
Job 6 Operation 6 duration 400 mins.
Machine 4 is used for the following Operations:
Job 0 Operation 0 duration 440 mins.
Job 9 Operation 0 duration 125 mins.
Job 3 Operation 1 duration 373 mins.
Job 2 Operation 2 duration 167 mins.
Job 7 Operation 4 duration 416 mins.
Job 6 Operation 5 duration 484 mins.
Job 1 Operation 6 duration 95 mins.
Job 4 Operation 6 duration 301 mins.
Job 5 Operation 7 duration 356 mins.
Job 8 Operation 7 duration 42 mins.
Machine 5 is used for the following Operations:
Job 2 Operation 0 duration 35 mins.
Job 3 Operation 0 duration 9 mins.
Job 4 Operation 1 duration 459 mins.
Job 0 Operation 2 duration 156 mins.
Job 1 Operation 5 duration 231 mins.
Job 5 Operation 6 duration 212 mins.
Job 8 Operation 6 duration 273 mins.
Job 6 Operation 7 duration 109 mins.
Job 7 Operation 7 duration 381 mins.
Job 9 Operation 7 duration 80 mins.
Machine 6 is used for the following Operations:
Job 1 Operation 0 duration 313 mins.
Job 7 Operation 1 duration 354 mins.
Job 4 Operation 2 duration 481 mins.
Job 5 Operation 2 duration 406 mins.
Job 8 Operation 2 duration 130 mins.
Job 0 Operation 4 duration 368 mins.
Job 6 Operation 4 duration 312 mins.
Job 9 Operation 4 duration 321 mins.
Job 3 Operation 6 duration 50 mins.
Job 2 Operation 7 duration 323 mins.
Machine 7 is used for the following Operations:
Job 0 Operation 1 duration 81 mins.
Job 1 Operation 2 duration 343 mins.
Job 6 Operation 2 duration 310 mins.
Job 3 Operation 3 duration 175 mins.
Job 7 Operation 3 duration 291 mins.
Job 8 Operation 3 duration 472 mins.
Job 5 Operation 4 duration 21 mins.
Job 2 Operation 6 duration 244 mins.
Job 9 Operation 6 duration 282 mins.
Job 4 Operation 7 duration 21 mins.
| Solution:
Job 6 Operation 0 on Machine 0 : 0 + 88 -> 88
Job 7 Operation 0 on Machine 2 : 0 + 131 -> 131
Job 5 Operation 0 on Machine 3 : 0 + 315 -> 315
Job 9 Operation 0 on Machine 4 : 0 + 125 -> 125
Job 3 Operation 0 on Machine 5 : 0 + 9 -> 9
Job 1 Operation 0 on Machine 6 : 0 + 313 -> 313
Job 2 Operation 0 on Machine 5 : 9 + 35 -> 44
Job 9 Operation 1 on Machine 1 : 125 + 325 -> 450
Job 3 Operation 1 on Machine 4 : 125 + 373 -> 498
Job 6 Operation 1 on Machine 2 : 131 + 8 -> 139
Job 4 Operation 0 on Machine 2 : 139 + 250 -> 389
Job 6 Operation 2 on Machine 7 : 139 + 310 -> 449
Job 7 Operation 1 on Machine 6 : 313 + 354 -> 667
Job 5 Operation 1 on Machine 2 : 389 + 244 -> 633
Job 4 Operation 1 on Machine 5 : 389 + 459 -> 848
Job 1 Operation 1 on Machine 1 : 450 + 346 -> 796
Job 9 Operation 2 on Machine 3 : 450 + 477 -> 927
Job 3 Operation 2 on Machine 0 : 498 + 408 -> 906
Job 0 Operation 0 on Machine 4 : 498 + 440 -> 938
Job 5 Operation 2 on Machine 6 : 667 + 406 -> 1073
Job 8 Operation 0 on Machine 1 : 796 + 280 -> 1076
Job 1 Operation 2 on Machine 7 : 796 + 343 -> 1139
Job 7 Operation 2 on Machine 3 : 927 + 445 -> 1372
Job 4 Operation 2 on Machine 6 : 1073 + 481 -> 1554
Job 8 Operation 1 on Machine 0 : 1076 + 323 -> 1399
Job 2 Operation 1 on Machine 1 : 1076 + 342 -> 1418
Job 1 Operation 3 on Machine 2 : 1139 + 295 -> 1434
Job 0 Operation 1 on Machine 7 : 1139 + 81 -> 1220
Job 0 Operation 2 on Machine 5 : 1220 + 156 -> 1376
Job 7 Operation 3 on Machine 7 : 1372 + 291 -> 1663
Job 0 Operation 3 on Machine 0 : 1399 + 108 -> 1507
Job 6 Operation 3 on Machine 1 : 1418 + 420 -> 1838
Job 2 Operation 2 on Machine 4 : 1418 + 167 -> 1585
Job 1 Operation 4 on Machine 3 : 1434 + 359 -> 1793
Job 9 Operation 3 on Machine 0 : 1507 + 391 -> 1898
Job 8 Operation 2 on Machine 6 : 1554 + 130 -> 1684
Job 7 Operation 4 on Machine 4 : 1663 + 416 -> 2079
Job 8 Operation 3 on Machine 7 : 1684 + 472 -> 2156
Job 2 Operation 3 on Machine 3 : 1793 + 108 -> 1901
Job 1 Operation 5 on Machine 5 : 1793 + 231 -> 2024
Job 4 Operation 3 on Machine 1 : 1838 + 32 -> 1870
Job 6 Operation 4 on Machine 6 : 1838 + 312 -> 2150
Job 5 Operation 3 on Machine 1 : 1870 + 92 -> 1962
Job 4 Operation 4 on Machine 3 : 1901 + 301 -> 2202
Job 7 Operation 5 on Machine 1 : 2079 + 473 -> 2552
Job 1 Operation 6 on Machine 4 : 2079 + 95 -> 2174
Job 9 Operation 4 on Machine 6 : 2150 + 321 -> 2471
Job 8 Operation 4 on Machine 2 : 2156 + 60 -> 2216
Job 5 Operation 4 on Machine 7 : 2156 + 21 -> 2177
Job 6 Operation 5 on Machine 4 : 2174 + 484 -> 2658
Job 5 Operation 5 on Machine 0 : 2177 + 122 -> 2299
Job 3 Operation 3 on Machine 7 : 2177 + 175 -> 2352
Job 8 Operation 5 on Machine 3 : 2216 + 251 -> 2467
Job 2 Operation 4 on Machine 0 : 2299 + 87 -> 2386
Job 5 Operation 6 on Machine 5 : 2299 + 212 -> 2511
Job 2 Operation 5 on Machine 2 : 2386 + 107 -> 2493
Job 3 Operation 4 on Machine 3 : 2467 + 167 -> 2634
Job 0 Operation 4 on Machine 6 : 2471 + 368 -> 2839
Job 9 Operation 5 on Machine 2 : 2493 + 7 -> 2500
Job 9 Operation 6 on Machine 7 : 2500 + 282 -> 2782
Job 8 Operation 6 on Machine 5 : 2511 + 273 -> 2784
Job 7 Operation 6 on Machine 0 : 2552 + 313 -> 2865
Job 3 Operation 5 on Machine 2 : 2634 + 99 -> 2733
Job 6 Operation 6 on Machine 3 : 2658 + 400 -> 3058
Job 5 Operation 7 on Machine 4 : 2658 + 356 -> 3014
Job 2 Operation 6 on Machine 7 : 2782 + 244 -> 3026
Job 9 Operation 7 on Machine 5 : 2784 + 80 -> 2864
Job 0 Operation 5 on Machine 2 : 2839 + 160 -> 2999
Job 3 Operation 6 on Machine 6 : 2839 + 50 -> 2889
Job 4 Operation 5 on Machine 0 : 2865 + 15 -> 2880
Job 7 Operation 7 on Machine 5 : 2865 + 381 -> 3246
Job 1 Operation 7 on Machine 0 : 2880 + 401 -> 3281
Job 3 Operation 7 on Machine 1 : 2889 + 228 -> 3117
Job 4 Operation 6 on Machine 4 : 3014 + 301 -> 3315
Job 2 Operation 7 on Machine 6 : 3026 + 323 -> 3349
Job 0 Operation 6 on Machine 3 : 3058 + 102 -> 3160
Job 0 Operation 7 on Machine 1 : 3160 + 180 -> 3340
Job 6 Operation 7 on Machine 5 : 3246 + 109 -> 3355
Job 8 Operation 7 on Machine 4 : 3315 + 42 -> 3357
Job 4 Operation 7 on Machine 7 : 3315 + 21 -> 3336
Makespan: 3357.0, as it is the maximum end completion time of Operation 7 |
5 | 2 | Optimize schedule for 5 Jobs across 2 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Job 0 consists of the following Operations:
Operation 0 on Machine 1 duration 438 mins.
Operation 1 on Machine 0 duration 451 mins.
Job 1 consists of the following Operations:
Operation 0 on Machine 0 duration 325 mins.
Operation 1 on Machine 1 duration 366 mins.
Job 2 consists of the following Operations:
Operation 0 on Machine 0 duration 251 mins.
Operation 1 on Machine 1 duration 52 mins.
Job 3 consists of the following Operations:
Operation 0 on Machine 0 duration 265 mins.
Operation 1 on Machine 1 duration 216 mins.
Job 4 consists of the following Operations:
Operation 0 on Machine 1 duration 130 mins.
Operation 1 on Machine 0 duration 167 mins.
| Optimize schedule for 5 Jobs across 2 Machines to minimize makespan. Each job involves a series of Operations needing specific machines and times. Operations are processed in order, without interruption, on a single Machine at a time.
Problem:
Machine 0 is used for the following Operations:
Job 1 Operation 0 duration 325 mins.
Job 2 Operation 0 duration 251 mins.
Job 3 Operation 0 duration 265 mins.
Job 0 Operation 1 duration 451 mins.
Job 4 Operation 1 duration 167 mins.
Machine 1 is used for the following Operations:
Job 0 Operation 0 duration 438 mins.
Job 4 Operation 0 duration 130 mins.
Job 1 Operation 1 duration 366 mins.
Job 2 Operation 1 duration 52 mins.
Job 3 Operation 1 duration 216 mins.
| Solution:
Job 2 Operation 0 on Machine 0 : 0 + 251 -> 251
Job 4 Operation 0 on Machine 1 : 0 + 130 -> 130
Job 0 Operation 0 on Machine 1 : 130 + 438 -> 568
Job 4 Operation 1 on Machine 0 : 251 + 167 -> 418
Job 3 Operation 0 on Machine 0 : 418 + 265 -> 683
Job 2 Operation 1 on Machine 1 : 568 + 52 -> 620
Job 1 Operation 0 on Machine 0 : 683 + 325 -> 1008
Job 3 Operation 1 on Machine 1 : 683 + 216 -> 899
Job 0 Operation 1 on Machine 0 : 1008 + 451 -> 1459
Job 1 Operation 1 on Machine 1 : 1008 + 366 -> 1374
Makespan: 1459.0, as it is the maximum end completion time of Operation 1 |
End of preview. Expand
in Dataset Viewer.
Dataset Card for Dataset Name
This dataset card aims to be a base template for new datasets. It has been generated using this raw template.
Dataset Details
Dataset Description
- Curated by: [More Information Needed]
- Funded by [optional]: [More Information Needed]
- Shared by [optional]: [More Information Needed]
- Language(s) (NLP): [More Information Needed]
- License: [More Information Needed]
Dataset Sources [optional]
- Repository: [More Information Needed]
- Paper [optional]: [More Information Needed]
- Demo [optional]: [More Information Needed]
Uses
Direct Use
[More Information Needed]
Out-of-Scope Use
[More Information Needed]
Dataset Structure
[More Information Needed]
Dataset Creation
Curation Rationale
[More Information Needed]
Source Data
Data Collection and Processing
[More Information Needed]
Who are the source data producers?
[More Information Needed]
Annotations [optional]
Annotation process
[More Information Needed]
Who are the annotators?
[More Information Needed]
Personal and Sensitive Information
[More Information Needed]
Bias, Risks, and Limitations
[More Information Needed]
Recommendations
Users should be made aware of the risks, biases and limitations of the dataset. More information needed for further recommendations.
Citation [optional]
BibTeX:
[More Information Needed]
APA:
[More Information Needed]
Glossary [optional]
[More Information Needed]
More Information [optional]
[More Information Needed]
Dataset Card Authors [optional]
[More Information Needed]
Dataset Card Contact
[More Information Needed]
- Downloads last month
- 30